The Union environment ministry issued a new office memorandum on November 18, 2020, that mandates its expert appraisal committee (EAC) to meet “at least” twice every month to “cut down the time” for environmental clearances (ECs).
The EAC is an expert body of the ministry responsible to okay or reject proposed projects – by awarding or withholding ECs – under the environment impact assessment process. Though the EAC is an advisory body, the Union environment ministry in almost all instances goes by its recommendations, since it comprises experts.
Even as the Expert Appraisal Committee (EAC) on River Valley Projects (RVP) appointed by the Union Ministry of Environment and Forests (MoEF) in December 2016 completes three years with the end of 2019, it has kept up its record of green signaling everything that came its way in 2019.
There was just one exception: EAC in its meeting on January 28, 2019 rejected the proposal for EC (Env Clearance) extension for the Brutang Major Irrigation Project in Nayagarh District of Odisha, but it was essentially on procedural issue and the EAC “recommended for taking of the proposal afresh”, so it was not a full stop, but only a comma. The EAC failed to creditably appraise the EIA, the TORs, the public consultation process and decide on merit if the project was fit for approval. It approved everything that came its way, at the most occasionally asking for additional information. Never looking into the adequacy of the impact assessment or public consultation process or optimality of the project. Continue reading “Expert Appraisal Committee on River Valley Projects Green signals all in 2019”→
“Bolo Jai Jai Baba Bhole”, the Prime Minister Narendrabhai Modi, while speaking at Kedarnath in Uttarakhand in Oct 2017[i], asked the people in audience to chant with him. Indian deity Mahadev, the presiding deity at Kedarnath on the banks of Mandakini river is possibly the closest to rivers and nature among all the deities, as is also clear from his attire. Baba Bhole is one of the many names of this deity. Incidentally, the massive, controversial Pancheshwar Dam a pet project of Mr Modi will also submerge the Pancheshwar Mahadev Temple, where too, the presiding deity is same Bhole Baba. But we will come back to Bhole Baba. Continue reading “Who exactly needs the Pancheshwar Dam?”→
Above: Ken Yamuna Confluence at Chilla Ghat (Photo by Siddharth Agarwal)
We are thankful & glad that Dr Sharad Jain has responded to our open letter to MoEF, circulated through email and blog[i] that he holding the charge of NWDA Director General and Chairman of Expert Appraisal Committee (EAC) on River Valley and Hydropower Projects (RVP) involves Conflict of Interest. We are also thankful that through the Indian Express report (on June 3, 2017), he has provided another set of answers.
Union Minister of State of Environment, Forests and Climate Change (Independent Charge)
Paryavaran Bhawan, Jor Bagh, Delhi 110 003
dr.harshvardhan@sansad.nic.in, ps2mefcc@gov.in (PS to MoEF Minister)
Respected Sir,
We have just learnt that Prof Sharad Jain of NIH, Roorkee, and chairman of Expert Appraisal Committee (EAC) on River Valley and Hydropower Projects (RVP), is also holding additional charge of DG of NWDA, see: http://www.nwda.gov.in/writereaddata/linkimages/6419983647.pdf. His office just told one of us that he has been holding this charge since about three months already.
This is a clear case of conflict of interest. As you know, a number of NWDA projects come to EAC for approval at various stages. One such project that came before the EAC headed by Dr. Jain was the Ken Betwa project, which the committee headed by Dr. Jain promptly cleared in very first meeting of the reconstituted EAC in Dec 2016, weeks before Dr. Jain took over as Director General of NWDA, over ruling the issues that earlier four meetings of the EAC had raised about this project. How can one expect that the EAC chairman would be able to objectively, independently and scientifically appraise a project of the organisation (NWDA in this case) of which he is the Director General?
Under the circumstances, we believe there is no option, except that you must ask Dr. Jain to resign from his post as chairman of EAC, as his holding additional charge of NWDA DG, and already in conflict of interest. We also request you to ask the EAC to review their decision about Ken Betwa Project (and any other NWDA project) that the current EAC may have appraised, after appointing a new chairman of EAC.
We would like to bring to your attention that there is already a precedent in this context when in 2009, the then chairman of the EAC (RVP), Dr P Abraham was asked to resign since he was also director of hydropower companies whose projects came before EAC headed by him.
We hope you will act promptly on this issue. There is some urgency of this since the next meeting of EAC (RVP) is on May 31, 2017, that is tomorrow.
Thanking you,
Yours Sincerely,
1. Prof Brij Gopal (Retired Prof from JNU, Delhi), Centre for Inland Waters in South Asia, Jaipur, brij44@gmail.com
2. Dr E A S Sarma, former Secretary, Govt of India, Vishakhapatnam, eassarma@gmail.com
3. Dr Bharat Jhunjhunwala (Formerly with IIM Bangalore), Uttarakhand, bharatjj@gmail.com
4. Vimal Bhai, MATU jan Sangathan, Uttarakhand, bhaivimal@gmail.com
21. Prof Sunil Kumar Choudhary,Prof. & Head, University Dept. of Botany, T. M. Bhagalpur University, Bhagalpur, sunil_vikramshila@yahoo.co.in, 09431875861
Copy to: 1. EAC (River Valley Projects) members
2. Prime Minister’s office
MEDIA COVERAGE:
June 1, 2017: http://timesofindia.indiatimes.com/india/chief-of-eac-on-rivers-faces-conflict-of-interest-charge/articleshow/58937121.cms
June 1, 2017: https://www.nationalheraldindia.com/environment/2017/05/31/ken-betwa-river-linking-project-a-clear-case-of-conflict-of-interest
A fabulous view of Ken river. Nesting sites of Long-billed vultures are to the right. All will go under water if Ken-Betwa linkup is carried out,AJT Johnsingh
In an unprecedented first ever Audit report, the Comptroller and Auditor General of India (CAG) which recently conducted Performance Audit on ‘Environmental Clearance and Post Clearance Monitoring’ has unambiguously stated that the existing processes for grant of Environmental Clearance are fraught with serious violations, noncompliance and deficiencies.[i] In fact River Valley and Hydroelectric Projects have been highlighted for poorest quality of Environmental Impact Assessment (EIA) Reports, maximum irregularities during Public Hearings, and non-compliance of Environmental Clearance conditions.
This is a resounding slap on the face of the functioning of the current and past Expert Appraisal Committee’s (EACs on Dams and vindicates and validates what SANDRP and other civil society groups have been saying for long. This is indeed much needed critical feedback when EAC is seeking to make its proceedings less and less transparent and providing false justifications for the same.Continue reading “CAG validates concerns about shoddy environmental appraisal of Dams”→
काल दि. २३ ऑगस्ट २०१६ रोजी महाराष्ट्र-तेलंगण आंतरराज्य मंडळाच्या आज झालेल्या पहिल्याच बैठकीत तुमडीहेटी, मेडिगट्टा आणि चनाखा-कोर्टा बॅरेज या तीन बॅरेजचे काम सुरू करण्यासाठी दोन्ही राज्यांदरम्यान करार करण्यात आले. कमालीची गोपनीयता पाळत केल्या गेलेल्या या कराराबद्दलची अत्यंत मोघम टिप्पणी प्रसार माध्यमांना पाठविण्यात आली. तुमडीहेटी, मेडिगट्टा आणि चनाखा-कोर्टा बॅरेजमुळे महाराष्ट्र राज्यातील यवतमाळ, चंद्रपूर आणि गडचिरोली जिल्ह्यातील 30 हजार हेक्टर जमीन सिंचनाखाली येणार असून उपसा सिंचन योजनांना बारमाही शाश्वत पाण्याचा स्त्रोत उपलब्ध होणार आहे असे या टिप्पणीत नमूद केले आहे. तसेच या प्रकल्पामुळे महाराष्ट्रातील एकही गाव, गावठाण बुडणार नाही, नदीकाठच्या गावांना पुराचा धोका नाही व हे प्रकल्प दोन्ही राज्यासाठी फायदेशीर ठरणारे असून उपसा सिंचन योजनांना बाराही महिने पाणी मिळणार आहे असा दावा करत या भागातील नागरीकांनी या प्रकल्पांना विरोध करु नये असे आवाहनही महाराष्ट्राच्या मुख्यमंत्र्यांनी त्यांनी केले. Continue reading “महाराष्ट्र-तेलंगण आंतरराज्यीय करार: जनतेच्या मुलभूत हक्कांचे व देशाच्या पर्यावरणीय कायद्यांचे उल्लंघन”→
Maharashtra & Telangana governments, it has been announced, will be signing a pact for three irrigation projects to be constructed on River Godavari. Under the agreement, the two states would take up Tummidihatti, Medigadda (Kaleswaram) and Chanaka–Korata projects. Chief Minister of Telangana K Chandrasekhar Rao has reportedly said that “this would herald a new era in the relations between the two states and would be a standing example of how the states can resolve inter-state disputes without the Centre’s intervention.”[i]
This pact which has been looked at as ‘historical victory’ for Telangana for convincing the neighbouring states is in fact one of the most blatant and outright violations of India’s environmental laws. Tummidihetti Project & Medigadda Project featured in the agreement have long history of gross irregularities and violations exposed by several apex agencies as well as media. SANDRP has visited these project sites multiple times, studied and written extensively about the projects and also repeatedly sent submissions to Chief Minister of Maharashtra pointing out the violations. The agreement is also being signed, keeping the affected people and also people in the Godavari river basin in two states completely in the dark. Some of the links for these articles are given at the end of this article. Continue reading “Proposed Maharashtra Telangana Inter-state Water sharing Agreement of Aug 23, 2016: In complete violation of people’s rights & environmental laws of India”→
Expert Appraisal Committee on River Valley Projects,
Ministry of Environment and Forests,
New Delhi
Respected Chairman and Members,
We have just seen the minutes of the 86th meeting (uploaded on Sept 14, 2015, but clearance letters in some cases have already been issued even before the EAC minutes are made public or the minutes are finalised at the next EAC meeting) of the Expert Appraisal Committee on River Valley Committee, held on Aug 24-25, 2015.
The minutes make a disturbing reading. The EAC seems to be bending every ecological norm, facts and even legal stipulations to push ahead with every project that the government wants them to clear. There seems to be no application of mind from the EAC on the proposals. The minutes are not even internally consistent. It is putting forward facts in misleading fashion to give a wrong picture. Continue reading “Why the Decisions and minutes of the 86th meeting of EAC on River Valley Projects need to be reviewed”→