Dams

Six years after PM Laying the Foundation Stone: No Clearance, No Work for 3000 MW Dibang Dam

The foundation stone of 3000 MW Dibang Multipurpose Dam was laid on 31st January 2008, by Prime Minister Manmohan Singh. Six years have passed since then but the project is yet to get the necessary  forest and environment clearances. This in a way reflects the state of environment governance in India where the foundation stone of mega dam is laid without getting any necessary clearance. 

The affected people stopping the public hearing in 2008 since they knew that that was their only chance to be heard. Source: http://www.roingcorrespondent.in/this-circus-should-stop-no-public-hearing/
The affected people stopping the public hearing in 2008 since they knew that that was their only chance to be heard. Source: http://www.roingcorrespondent.in/this-circus-should-stop-no-public-hearing/

This project was considered for forest clearance in the FAC meeting held on July 11th and 12th 2013. The FAC meeting minutes noted “Felling of more than 3.5 lakh trees most likely to have adverse impact on general eco-system of the area, recovery of which may be very difficult through any type of mitigate measures”.

The Expert Appraisal Committee (EAC) on River valley and Hydroelectric projects considered Dibang multipurpose project in its 68th meeting on September 23rd 2013 for environment clearance but this was in complete violation of  norms. Following the “Lafarge vs Union of India and others” case of 2011, the Supreme Court of India had said that a project without forest clearance cannot be considered for environment clearance. SANDRP had pointed this out in our submission to EAC dated 20/09/2013. But EAC seemed to take no account of that.

Out of the 168 projects proposed for Arunachal Pradesh, this is the only multipurpose project. The minutes of 68th EAC meeting states that this project has dual objectives. The primary objective is flood moderation while electricity generation is its secondary objective. This is highly doubtful though since the project does not have the adequate storage capacity. On the other hand, the installed capacity of the project i.e. 3000 MW is also one of the highest among 168 hydropower projects.

The Dibang multipurpose dam is located 1.5 km upstream of confluence of Ashu Pani with Dibang river at Munli village in Lower Dibang Valley district. Construction of this dam involves two districts of  Arunachal  Pradesh  viz.  Lower Dibang Valley and  Dibang Valley districts. All the project components e.g. dam, power house will be are located in Lower Dibang Valley District while reservoir which will submerge 43 km length of the river will fall in both districts.  The total land requirement for this dam is 5794.142 ha out of the 5022.842 is forest area with very rich bio-diversity. Submergence of such a huge forest is one of the major concerns associated with this dam and that is why the Forest Advisory Committee (FAC) has refused forest clearance to this project.

The Dibang multipurpose project plans to construct 288 meter high concrete gravity dam with an underground dam toe power house. The reservoir of this project will submerge 40.09 sq km area. The total cost of the project at November 2007 price level was estimated at 15886.39 crores.

It is important to note that the public hearing for the project faced vehement opposition of the local people. The public hearing of the project has been halted for several times. The local people expressed serious concern regarding Dibang multipurpose project and feared that influx of outsiders for dam building will lead to a demographic imbalance in the Dibang valley. This is a serious issue since the primary inhabitants of Dibang valley are Mishmi (Idu) which is a very small community with a population of 11,023 according to 2001 census. According to NHPC estimation a workforce of 5800 people (labour and technical staff) would be needed for the Dibang multipurpose project. But All Idu Mishmi Students Union (AIMSU) has contested this figure and opined that a single project would bring about 15,000 people into the region. It is also reported that NHPC claim that the project will cause ‘negligible human displacement’ grossly undermines its harmful impacts on smaller ethnic community such as Idu Mishmis. A video of the protest by local people can be seen here – http://www.youtube.com/watch?v=m8TCUKh2hQY

No cumulative impact assessment of dams in Dibang valley has been conducted e even though 17 projects have been proposed for this region. The TOR clearance had been given to 86 MW Ithum and 3097MW Etalin HEP in the basin by EAC. Without any cumulative impact assessment study of the basin no project should be given environment clearance. People from Dibang valley has also written to previous EAC on demanding cumulative impact assessment study. A letter to EAC from a local person Raju Mimi, dated January 31st 2013 stated “Since the 3097 MW Etalin project is on agenda again for the 64th EAC meeting to be held on Feb 1st – 2nd 2013, we re-iterate our demand to have prior cumulative impact assessment of multiple hydropower projects by urgently commissioning a Dibang river basin study.”

Other Glaring Issues of Dibang Multipurpose Along with the above mentioned issues SANDRP had made detailed submission to EAC pointing to some of the glaring concerns associated with the project. Some of these issues are –

Incomplete and Shoddy Downstream Impact Assessment: The downstream impact assessment done for the Dibang multipurpose does not take into account impacts of the dam in Assam. The downstream impact assessment study does no assessment beyond   Dibru-Saikhowa and whatever has been done is also very much inadequate.

No Public Hearing Held in Assam: Even though the Dibang multipurpose will have severe impacts in downstream Assam, there was no public hearing held for the project in Assam.

Mining for the Dibang Multipurpose will lead to Catastrophes: Mining of boulder, sand and other construction material for the Dibang multipurpose project will have very severe impacts on the river as well as on the local environment. The amount of boulder required for the construction of this project is 193 lakh cubic meter as stated in the project document. This is really astonishing figure and impact of such mining on the river bed and nearby areas will be catastrophic. The fragility of the Himalayan mountain range is not unknown to anyone and mining in such a sensitive hilly area will area will only increase the risk of landslide and disaster. The catastrophe of Uttarakhand floods is a clear example of this.

No Climate Change Assessment Impact of climate change on the project and impact of the project on the local climate. No attempt has been made to assess the impact of green house gas emissions from the reservoir of the dam which extends to 43 km.

No assessment impacts of peaking power operations Impacts Detail assessment of impacts of peaking power operation during non-monsoon months not done. Impacts on the flow characters of the river due to this dam, what will be the changes and how these will impact downstream areas.

No Assessment of Disaster Potential Impact of the project on disaster potential in the project area as well in the downstream including Assam due to construction and also operation at various stages, say on landslides, flash floods, etc.

No Assessment of Silt Flushing Impact of changing silt flows downstream from desilting chamber and from silt flushing in monsoon on the downstream areas not analyzed. A detail account of how the silt from the dam would be flushed out annually and what would be the impact of this in the downstream  as well as on the geo morphology, erosion, stability of structures etc was not done.

What did the EAC say in 68th Meeting The EAC in its 68th meeting did not recommend environment clearance to the project and instead pointed out several issues in the EIA – EMP report. Some of the important issue pointed out by EAC are –

1. Attempts may be made to avoid  submergence  of huge area  of rich forest land. It merits mention that  due to the very high forest land  submergence,  forest clearance has not yet been accorded by FAC.

2. Environmental Flow in the diverted portion of about 1.2 km  i.e. between dam and TWL  of dam toe PH  is to be reassessed and  a  suitable quantity is to be proposed for release as per extant norms. 4% flow as suggested was found to be inadequate.

3. Numbers of Fish species  reported was found to be on lower side and NHPC was asked  to verify this and report accurately.

4. Number  of  plant  species  reported  also  appeared  to  be  on  lower  side    and  to  be rechecked by NHPC.

5.At  this  altitude  of  the  project  (about  3000m),  snow  leopard  should  have  been sighted. It may be erroneous to report that leopard was not found  in the study area. Therefore, this may be relooked.

6. Study  area  in back water/ submergence is also to be  extended for proper inventory of both flora, fauna/bio-diversity.

The impacts of the Dibang multipurpose project are going to severe on the river, people and overall ecology of Dibang river basin. But sad part is that no proper assessment of these impacts has been done till now. Looking back at the six years since the laying foundation stone for the project we reiterate what Forest Advisory Committee said about the project “ecological, environmental and social costs of diversion of such a vast tract of forest land, which is a major source of livelihood of the tribal population of the State, will far outweigh the benefits likely to accrue from the project.”

Parag Jyoti Saikia

Ministry of Environment and Forests · Western Ghats

Open Letter to Dr. Veerappa Moily as he supports foundation stone laying of Yettinahole Diversion Project

 January 30, 2014

To,

Dr. M. Veerappa Moily

Union Minister of Environment and Forests

Paryavaran Bhawan, CGO Complex, Lodhi Road,

New Delhi 110 003

vmoily@kar.nic.in

Subject: Issues about the laying of Yettinahole Diversion Project’s foundation Stone

Respected Dr. Moily,

We learnt about your announcement and support for laying the foundation stone of the controversial Yettinahole Diversion Project on January 31, 2014 in your parliamentary constituency of Chikkaballapur, from several media reports[i]. The project has not conducted any impact assessment study and does not have any statutory clearance from your ministry. This is in complete violation of several norms and laws and is shocking, to say the least.

Dr. Moily, our assessments based on local interactions, site visits, study of the Project report (the DPR for the project is still not ready) indicate that the project involves eight dams inside the Western Ghats, deforestation of more than 100 ha of forests inside the Western Ghats eco-sensitive region, water diversion without any ecological studies, 370 MW of power for pumping, a canal of 250 kms length, 1200 ha submergence near Devaranyadurga including submergence of 2 villages and 600 ha forest land. [ii]

The foundation stone laying ceremony is supposed to take place on the 31st January 2014 at Muddenahalli, Chikkaballapur, which also happens to be your current constituency.  It is clear why you chose Chikkaballapur to lay the foundation stone, and not Sakaleshpur, from where the water will be diverted, or Dakshin Kannada, which will face most of the impacts of the project. In Sakaleshpur and entire Dakshin Kannada, (which was your constituency in the past) there is a huge and mounting opposition to Yettinahole Diversion and also to your decision.

Just in the last two weeks, there have been attempts to a stop train in protest, numerous dharnas, hunger strikes, letters in opposition and a Satyagraha in Netravathi River to oppose this project.[iii]

Rail Roko prtest against Yettinahole Diversion Photo: Daiji World
Rail Roko protest against Yettinahole Diversion Photo: Daiji World

Despite this growing discontent, you, as an MP from Chikkaballapur and the Union Environment Minister, or the Karnataka Government did not feel the need to initiate a dialogue with the people of this region. Has the government learnt no lessons from Delhi as to what happens when local voices are ignored and unheeded?

Protest in Hassan (in addition to Dakshin Kannada) against Yettinahole Diversion Photo: The Hindu
Protest in Hassan (in addition to Dakshin Kannada) against Yettinahole Diversion. Photo: The Hindu

Why has the Karnataka Government or the Union Ministry of Environment and Forests, which you now head, not thought it necessary to assess and address the serious ecological impacts of this project? Why have you supported the fraudulent tactics of this project to escape environmental clearance?  Our letter to the Ministry in his regard dated 10 Sept 2013, which was endorsed by several experts remains unanswered till date[iv].

As the  Minister of Environment and Forests, it is your duty to see that projects with significant impacts on ecology and dependent communities are assessed. Why are you escaping that duty?

Why is the Karnataka Government and the MoEF, under you leadership, hiding behind weak technical clauses of the EIA Notification 2006 to claim that the project does not qualify for Environment appraisal?

In fact the EIA Notification 2006 requires that there is thorough appraisal of the project. We have sent you a letter in this regard again on the 28th of January 2014, with scanned pages from the project report proving  this.

How can you support foundation stone laying ceremony when RTI reveals that Forest Department has not even assessed the forest area affected by this project?

How can a Minister of Environment and Forests of India indulge in an illegal act of formal initiation of a project that does not have environmental or forest clearances?

The project will come to the Ministry of Environment and Forests, headed by you, for Forest Clearances. But you have supported the foundation stone for this project already, giving a signal that forest clearance is a foregone conclusion.

If this is not conflict of interest, what is?

And all this for 2.8 TMC drinking water for Kolar and Chikkaballpur Districts. Has the government conducted any studies to prove that project with Rs 100 Billion cost and severe environmental impacts is the least-cost option to get drinking water for Kolar and Chikkaballapur in whose name the project is being pushed?

Dr. Moily, as the Union Environment Minister, it is you duty to address these questions before you support the foundation stone laying of Yettinahole Diversion Project.

Not doing so is in violation of environmental norms and legal stipulations.

We are looking forward to getting a point-wise response from you.

Sincerely,

Parineeta Dandekar, Himanshu Thakkar, SANDRP, Pune and Delhi

Dr. T. V. Ramchandra, Energy and Wetlands Group, Centre for Ecological Sciences, Indian Institute of Science, Bangalore, Karnataka 

Panduranga Hegde,Parisara Samrakshana Samithi, Appiko Movemenr, Sirsi, Karnataka

Dr. Shrinivas Badigere, Water and Irrigation Expert, Bangalore, Karnataka

Dr. Latha Anantha, River Research Center, Kerala

Dr. Rajeev Raghavan, South Asia Co-Chair, IUCN SSC/WI Freshwater Fish Specialist Group
Member, IUCN SSC Red List Committee 

Debi Goenka on behalf of Conservation Action Trust, Mumbai

Shankar Sharma, Power Policy Analyst, Tirthahalli, Karnataka

R. Sreedhar, Managing Trustee, Environics Trust and Chairpserson, Mines , Minerals and People

Vidyadhar Atkore, Fisheries Researcher, Bangalore, Karnataka

Neethi Mahesh, Mahseer Conservancy, Karnataka

Dr. Ashok Kundapur, Udupi, Karnataka

Anand Krishnamurthy, Bangalore, Karnataka

Dr. Nitya Ghotge, Anthra, Pune

Ms. Nyla Coelho on behalf of  Paryavarni, Belgaum, Karnataka

Pratim Roy on behalf of Keystone Foundation, Kotagiri, Tamilnadu

Dr. Archana Godbole, Jayant Sarnaik, AERF, Pune

Dr. K. Amitha Bachan, Western Ghats Hornbill Foundation

Vijay Sambare, Lok Panchayat, Sangamner, Maharashtra

Dr. Bhaskar Acharya, Independent Researcher, Bangalore

Ramesh Gauns, Environmental Activist, Goa

Ramaswamy Selvam for Tamilnadu organic farmers federation, Arachalur,Erode.

Headwaters of Netravathi and Gundia threatened by Yettinahole Diversion Photo: Parineeta Dandekar, SANDRP
Headwaters of Netravathi and Gundia threatened by Yettinahole Diversion Photo: Parineeta Dandekar, SANDRP
Himalayas · Nepal

Explained: Seti River floods in May 2012, Nepal- A chain of events, starting at 25,000 feet!

In late April and early May 2012, what was usually a roaring Seti river in Northwestern Nepal had slowed to a trickle. The milky-white turbid water had turned blue and clear. And then suddenly on May 5, 2012, the flooded river laden with slurry of sediment, rock, and water surged through the Seti valley in the Kaski district, obliterating dozens of homes and sweeping 72 people to their deaths. The floods waters were upto 30 m high at places. It reminded of the sequence of events leading to Tsunami. Questions swirled about where the water had come from and how it arrived with so little warning and that too in a non-monsoon season.

nepal1

 NASA Earth Observatory (acquired October 7, 2013)

The abstract of the paper by Shreekamal Dwivedi and Yojana Neupane of Department of Water Induced Disaster Prevention of Government of Nepal (presented in a conference in Nov 2012 and published in Nepal Geological Society (2013, Vol. 46)) provided some details of what happened in the floods: “Comparative Analysis of the Landsat ETM satellite images of 20th April, 2012 and 6th May, 2012 revealed that the area of about 32000 square meter of the southern ridge 1.5 kilometer away from the Annapurna IV peak failed in the north western direction. The impact of descending mass of the failed mountain from 6850 meters to 4500 meters almost vertically pulverized the ice, sediment and rock. The impact even triggered seismicity at 9:09.56 AM. local time which was recorded all over the 21 stations of National Seismological Centre. The closest seismic station at Dansing which is 32 km. south west from the area recorded the high signals for 70 minutes which corresponds to the duration of the debris flow. (The seismicity was equivalent to magnitude 3.8-4 in Richter Scale.) Lab analysis of the flood water sample revealed the density of the flow as 1.88 gm/cc. Analysis of the satellite based hourly rainfall GSMaP NRT from the period form 20th April -6th May 2012 revealed that there were just 4 occurrences of rainfall which amounted less than 1 mm/hour in the source area of the avalanche. The rainfall > 6mm/hour which occurred in the Kharapani area on 4 May was localized rainfall which did not extend to the avalanche area. Lack of systematic disaster preparedness caused huge loss of life and property even though the early warning message was received from the Ultralight pilot who was flying close to the area. The avalanche triggered high intensity floods which have similar characteristics to glacier lake outburst floods (GLOFs) have emerged as a new hazard in the Himalaya.”

Now, twenty months after the disaster, experts like Dr Jeffrey Kargel, hydrologist at University of Arizona, are in a position to throw more light what happened. Dr. Kargel has concluded that it was not just one event but a series of event that combined to produce the devastation.

NASA Earth Observatory site describes the affected landscape as: “The landscape in this part of Nepal is shaped by a cycle of landslides and subsequent erosion. As the tectonic collision of India with Asia pushes the Himalaya upward, ice, water, and gravity, assisted by sporadic earthquakes, combine to grind the mountains down. The channel of the SetiRiver itself is cut into the remnants of a much larger debris flow, perhaps 1,000 times as big. 60 to 100 meters (200–330 feet) thick, the landslide deposits are composed of the same limestone as the peaks to the north. Likewise, the May 2012 flow left behind jagged fragments of limestone, carried from the crest of the Himalaya to the foothills in a single event.”

‘Seti’ in local languages means white, and Seti is the ‘White River’, its water is glacial white, turbid and laden with sediment.

The high intensity floods in May 2012 came in waves, and the first wave alone had around a quarter of a million cubic meters of water in just a few minutes. There were about 27 waves in all over the next hours, according to eyewitnesses, so several million cubic meters of water flowed overall. As Dwivedi et al note, “The huge mass of debris along with ice chunks rushed down the river as a debris flow for 20 kilometres downstream at Kharapani in just 28 minutes (almost 12 meters/second). The flood arrived at Kharapani, where most of casualties occurred, at 9:38 AM and reached the dam of the Seti irrigation system at 10:35 AM… The high-water level at the dam weir at Pokhara was 2.15 meters. The discharge estimation based on the water mark revealed the peak as 935 m3/s (B. Poudel, personal communication). The eye-witnesses in Kharapani area reported huge ice blocks floating in the flood. They felt vibrating ground and heard very loud sound similar to flying of several helicopter together. The smell of the flood water was muddy… Kharapani was a popular spot for picnic and natural hot spring bath… Most of the causalities occurred in this area as the warning message from the Pokhara Airport tower could not reach this area”.

It is heart warming to see that many lives were saved, as Dwivedi et all write, “Capt. Alexander Maximov, the pilot of ultra-light plane of Avia Club Nepal in the morning of May 5 was in a regular sightseeing flight close to the Mountain Machhapuchhre. He noticed a huge dark cloud in the high-mountain depression (Fig. 9) and immediately turned back. He sent a message to the tower of Pokhara Airport. His quick understanding of the unusual event and timely response has saved hundreds of lives during the Seti flood of 5th May 2012. He informed the tower at 9:16 AM and the message was broadcasted through FM radio; police forces evacuated hundreds of people living and working in the bank of the Seti River. Some eye- witnesses in the field said that information about the flood was also received in Kharapani bazar by mobile calls from the people who saw the flooding in the upstream area. This message has helped many people to run to safety. However there was no organized approach of the warning dissemination in the ground.”

Video shot by Capt. Maximov from his aircraft, as the event was was happening:

Nepal2

NASA Earth Observatory image (acquired Dec 22 2013)

However, the series of event started weeks before the flood with a series of rockfalls that sent debris tumbling into the SetiRiver, backing water up in the extremely deep and narrow gorge. The last of these landslides occurred just a week or so before the flood. The situation grew dire on May 5, 2012, when an unusually powerful ice avalanche and rockfall tumbled down a vertical cliff on a ridge just south of Annapurna IV Mountain peak. The total drop from the Annapurna IV ridgeline to the bed of the Seti below Pokhara is about 6,100 meters (20,000 feet) spread over a distance of only 40 kilometers. The distance between the landslide dam and sight of worst floods was about 29 km.

Prof Jeffrey Kargel, writes (http://earthobservatory.nasa.gov/blogs/fromthefield/2014/01/24/setiriverclues/), “A flash flood—what geologists call a hyper concentrated slurry because it was thick with suspended silt—had torn through some villages along the Seti River, in north-central Nepal, just north of the country’s second largest city, Pokhara. It was immediately recognized as a very deadly event, but the death toll—and a tally of those who remain missing but were clearly also killed—was not known exactly for several months. 72 souls lost. Though not large on the scale of global disasters, this event was terrifying for the fact that it seemed to come from nowhere—literally from beneath a blue sky.”

Neapl3

 AFTER IMAGE: shows the area on May 6, 2012, roughly 25 hours after the landslide

 nepal4

BEFORE IMAGE: the same area on April 20.  The diagonal lines are gaps in the data, due to a partial failure of the satellite.

One scenario (see: http://earthobservatory.nasa.gov/IOTD/view.php?id=78070&eocn=image&eoci=related_image) estimates that roughly 22 million cubic meters of rock broke off the slope of Annapurna IV. Colin Stark at Lamont-Doherty Earth Observatory at ColumbiaUniversity said: “There’s a drop of about 2,000 meters into the canyon, so we’re talking an enormous gain in momentum. Then I think the debris ran down the canyon at speeds upwards of 30 meters per second—a guess but what we see for the landslide itself.” Stark estimated that events unfolded in a matter of minutes with no time for a temporary dam to form.

This flood appeared to behave like a glacier lake outburst flood, and the news media can be pardoned for having assumed that it was. Prof Kargel adds: “Seeing that the disaster occurred at the foot of the AnnapurnaRange, within the Greater Himalaya, probably every expert’s first thought was “glacial lake outburst flood” (GLOF), because these were common in Nepal’s Himalaya, and the news accounts of the disaster event resembled accounts of GLOFs”. However, available satellite images showed there were no such lakes. “It was, however, clearly a disaster that had its source in a high Himalayan amphitheatre-like bowl, a glacially-carved structure called the Sabche Cirque. This structure was rimmed by some of Nepal’s most famous, picturesque mountain peaks, including the storied, holy Machapuchare ( “fishtail” peak) & Annapurna IV, a 24,688 ft” mountain.

Nepal5

Annotated photo from Dr. Kargel

Thanks to video from winged camera of a 2 seater plane incidentally flying over the area at the time of the event, the disaster’s trigger was sourced on a ridgeline near Annapurna IV.  Apparently part of this ridge—probably initially the glacier ice— collapsed, dropping ice and rock over 3000 m almost vertically onto unconsolidated rock debris (glacial moraines and ancient glacial lake silts and gravels) resting unstably in the deep bowl of the Sabche Cirque.  Some of that loose debris was also swept up by the avalanche, and the mass flowed and dropped through an additional 1,500 m into the SetiRiver gorge. Indeed, the conversion of gravitational potential energy to heat could have melted roughly a tenth of the falling snow and ice by the time it reached the SetiRiver.

nepal6

A view of the gorges and also the distant peaks of the Sabche Cirque and the ancient glacial deposits in between. The avalanche entered the gorge from the upper right corner of the scene. (Photo: Dr. Kargel)

One source seemed to be definitely involved, and that was a rockslide-dammed reservoir in the gorge. This was definitely not a GLOF, but was caused by a rockslide into the SetiRiver gorge, formation of an impoundment reservoir over a several week period due to damming of spring snow and ice melt, and then the final triggering event of the mighty rock and ice avalanche off Annapurna IV.

Nepal7

The source area for the avalanche of May 5, 2012. Annapurna IV is just off image to the upper left. (Photo: Dr. Kargel)

Warning: More such events could occur As Dwivedi et al have noted, “The southern slopes of Annapurna range have been experiencing avalanche-triggered high intensity floods also in the past. On August 15, 2003, the Madi River had experienced an unprecedented flash flood which destroyed the recently built rural road and triggered many landslides along its course and killed 5 people”.

“There are good reasons to be concerned,” Jeffrey says, “Something like this will happen again. It’s inevitable.” The Seti River Gorge is unusually prone to dangerous blockages because of how narrow and deep it is. And the same processes that triggered the spring 2012 rockfalls and avalanche are still at work. “The only question is whether future events will be as destructive or whether people in the SetiRiverValley will have absorbed the lessons of 2012 and found ways to move their homes out of the flood plain.” India should not forget that we are downstream country in Seti basin and what happens there will flow down here too.

In an earlier excellent paper on this event, Jorg Hanisch et al recommends that this event requires deep investigations and “Marsyangdi Khola, Madi Khola, Modi Khola and Kali Gandaki, all with apparent origin in the high-mountain environment of Annapurna Range (Hormann 1974; Yamanaka and Iwata 1982) should be included in the investigations… A new catastrophe of similar size would have an apocalyptic impact: about half a million people live in the valley today. A detailed investigation of the circumstances of the disaster on May 5th, especially the possible influence of global warming on the trigger of the disaster, and a reliable forecast of a potential recurrence of similar events or of even much greater scope, are urgently required. For this, the thorough understanding of the conditions, triggers and mechanisms of the huge flows in the past to compare it with the recent flood is indispensable as well.”

The proposal for a 140 MW Tanahu Seti storage project downstream of this flood event & supported by the Asian Development Bank, Japan International Cooperation Agency, European Investment Bank and Abu Dhabi Fund is questionable, says Ratan Bhandari of Nepal. Considering that the Seti River Basin is prone to such events in future, the proposal seems disastrous.

More significantly, this whole episode raises the question as to how much do we really know about the Himalayas. Uttarakhand disaster of June 2013 was a wake up call to understand the Himalayan ecosystem and its implications for future well being of the people and environment of India. However, in stead of learning any lessons, our governments in Uttarakhand (as also in Himachal Pradesh, Kashmir and North East) and at the Centre, with environmentally-challenged Mr Veerappa Moily as the environment minister, are playing into the hands of short sighted vested interests. This is also apparent in the recent decision to sanction the massive Lakhwar dam on YamunaRiver in Uttarakhand without so much as an Environmental Impact Assessment!

We still do not have full explanation for the Uttarakhand disaster of June 2013. This explanation of the Seti River Disaster in the same Himalayas, which happened just a year before the Uttarakhand disaster highlights the urgent need for more serious studies and applying precautionary principle while dealing with the Himalayas, its  rivers and flood plains.

Compiled by SANDRP

Sources:

1. http://earthobservatory.nasa.gov/NaturalHazards/view.php?id=82937&src=nha dated January 25, 2014

2. http://earthobservatory.nasa.gov/blogs/fromthefield/2014/01/24/setiriverclues/ This entry was posted on Friday, January 24th, 2014 at 10:34 am. See the absolutely amazing photos on the site that gives an insight into the situation in the head reaches of Seti River… possibly indicates how little we know about the catchments of our Himalayan Rivers.

3. http://earthobservatory.nasa.gov/IOTD/view.php?id=78070&eocn=image&eoci=related_image dated May 6, 2012

4. http://earthobservatory.nasa.gov/NaturalHazards/view.php?id=78117&eocn=image&eoci=morenh dated May 23, 2012

5. http://blogs.agu.org/landslideblog/2012/05/23/understanding-the-seti-river-landslide-in-nepal/, dated May 23, 2012

6. http://www.icimod.org/?q=7377, dated June 25, 2012

7. “Cause and mechanism of the Seti River flood, 5th May 2012, western Nepal” by Shreekamal Dwivedi and Yojana Neupane, Department of Water Induced Disaster Prevention, Pulchwok, Lalitpur, Nepal (shreekamal @gmail.com), published in Journal of Nepal Geological Society, 2013, Vol. 46, pp. 11-18

8. Famous movie clip of the area, http://www.youtube.com/watch?v=Uk82ggshSKs&feature=related   you can see landslide in the clip at 56-57 seconds of the movie. At this time the avalanche had not occurred yet. After taking one round the aircraft pilot has noticed the dark grey brown cloud formed by the avalanche (see the movie at 2 minute 7 seconds). This is thanks to Shreekamal Dwivedi

9. “The Pokhara May 5th fl ood disaster: A last warning sign sent by nature?” by Jörg Hanisch, Achyuata Koirala and Netra P. Bhandary, Journal of Nepal Geological Society, 2013, Vol. 46, pp. 1-10

Beas · Hydropower Performance · Sutlej

Insider view: BBMB is inefficient, slow, heavy, bureaucratic; Does not work to preserve its massive resources

Bhakra Beas Management Board (BBMB, http://bbmb.gov.in/english/index.asp) is the manager of India’s celebrated icons: Temples of Modern India as our first Prime Minister called it. In a rare occasion, when we get a candid account of insider’s view of this organisation, it is worth taking note of it.

bhakra1

 Bhakhra Dam: Photo from BBMB 

BBMB, created on Oct 1, 1967, has current annual budget of massive Rs 1000 crores and manages the Bhakra Nangal Project, the Beas Project I (Pandoh dam, the Beas Sutlej Link and the Dehar Power House) and the Beas Project II (Beas Dam and Pong power houses). With close to 3000 MW of installed capacity it generates about 12.5 billion units of power annually.

Mr Satish Loomba, who served as Financial Advisor to BBMB between 1996 and 2001 has just provided an interesting view about the functioning of BBMB in his article Need to corporatise BBMB in The Tribune of January 23, 2014: http://www.tribuneindia.com/2014/20140123/edit.htm#6. While the author, as the title suggests, is advocating a corporate restructuring of BBMB, what he has said in the process provides a valuable insights from an insider. Here are some snippets:

Þ    “This organisation, which has become heavy, slow and bureaucratic…”

Þ    “However, despite a façade of running smoothly, the BBMB, from the organizational standpoint, suffers from several infirmities, limitations and internal contradictions.”

Þ    “At the core of the inadequacies in the BBMB are the… systems which do not promote efficiency, cost control and long term health of its vast assets… It has no concern with the value of its output…”

Þ    “… capital of the BBMB is not being preserved in accordance with accepted principles…” In fact in recent years, the illegal dumping of humungous quantities of muck (even a 100 MW project creates several million meter cube of muck) by the numerous major, medium and small hydropower projects in upstream Sutlej (see: https://sandrp.in/basin_maps/Hydro_Electric_Projects_on_Sutlej_River_in%20HP.pdf) and Beas (see: https://sandrp.in/basin_maps/Hydropower_Projects_in_Beas_Basin.pdf) basins is  leading to accelerated silting up of the Bhakra, Pong and Pandoh reservoirs, but no one, not even BBMB has shown the slightest concern.

Þ    “For the ageing irrigation wing assets, which are colossal and could be in sudden need of massive recapitalization…”

Þ    “… there is no account which summarises its results for a specific time period…”

This is a very serious indictment, not only of BBMB but also the way the “icons” of India are being managed by an organisation controlled by the Union Ministry of Power. Are these remediable infirmities or are these the implications of the kind and size of structures that BBMB manages? The author of the above article does not even pose this question, but is a very relevant one.

Declining Hydropower generation As per our analysis of hydropower generation from the three BBMB projects in Himachal Pradesh, namely Bhakra (1325 MW), Dehar (990 MW) and Pong (396 MW), with total installed capacity of 2711 MW, the generation per MW installed capacity has shown hugely declining trend with trend line declining by 18-20% in less than three decades. We also have graphs of individual BBMB hydropower projects that show similar trend line. This is a massive decline and in any responsible governance, questions would be asked as to why this is happening, but here, there are no questions.

bhakra2

Unravelling Bhakra In a comprehensive critique Unravelling Bhakra, (see: http://www.manthan-india.org/spip.php?rubrique1, available in both English and Hindi), author Shripad Dharmadhikary has shown that it is a myth to assume that Bhakra dams were the only or major reasons behind India’s food security, green revolution or irrigation in North West India. He has shown with facts and figures that are yet to be proven wrong that the contribution of Bhakra dams was limited.

unravellingBhakara

Displaced people still awaiting justice Over five decades after commissioning of the Bhakra project, the people displaced by this most celebrated of Indian dams are still awaiting justice, as is clear from this latest news report (http://www.tribuneindia.com/2014/20140120/haryana.htm#10) in January 2014. This has been highlighted by many in the past including Govt of India’s Water Resources Minister in his autobiography, by SANDRP in 2002, by Shripad Dharmadhikary in above  mentioned book and continuous media coverage. This also shows the callous attitude of BBMB and concerned state and central governments.

Ad hoc, callous reservoir operation It is no secret that even this irrigation system is in bad and declining health. This is due to many reasons, including due to lack of maintenance and participatory governance. Several times it has been pointed out how unaccountable and inefficient has been the operation of the Bhakra reservoirs. Two recent occasions when SANDRP pointed this out include the following:

Þ       July 2012: Precarious situation of Bhakra dams: BBMB says emergency measures are imminent: Callous, ad-hoc reservoir operation again? Could this situation have been avoided? https://sandrp.in/dams/PR_Why_precarious_water_situation_at_Bhakra_dams_was_avoidable_July_2012.pdf

Þ    Sept 2010: Bhakra reservoir is being operated in casual, adhoc manner? Need for clearly defined norms of accountability in reservoir operations https://sandrp.in/dams/Bhakra_and_Need_for_accountability_in_Reservoir_Operations_Sept_19_2010.pdf

Þ    With general elections approaching in coming April May 2014, we have to wait and see if the Bhakra reservoirs will again be operated in an ad hoc manner like it happened before previous two national elections.

We hope right lessons will be learnt from this insider’s view of the alarmingly inadequate functioning of the BBMB and efforts will be made to make its functioning more participatory, transparent and accountable.

Himanshu Thakkar (ht.sandrp@gmail.com)

Arunachal Pradesh

Arunachal Pradesh Groups Ask MoEF to Cancel Illegal Public Hearing of Lower Siang

22nd January 22, 2014

Dr. V. Rajgopalan

Secretary,

Ministry of Environment and Forests,

New Delhi.

Sub: 2700 MW Lower Siang project – Cancel Illegal Public Hearings proposed for January 31st 2014.

Dear Dr. Rajgopalan,

We write to you on behalf of the Forum for Siang Dialogue (FSD), Siang Peoples’ Forum (SPF) Sirit-Siyom Banggo Dam Affected peoples’ Forum (SSBDAPF), Siang Bachao Andolan (SBF), Nyiko Bachao  Forum (NBF) to seek cancellation of the Three public hearings proposed to be held for the 2700 MW Lower Siang hydroelectric project in the East Siang, West Siang and Upper Siang districts of Arunachal Pradesh  on January 31, 2014.

Through a notification dated 30th December 2013 published in the Arunachal Times dated 31st December 2013 the Arunachal Pradesh State Pollution Control Board (APSPCB) has announced the conduct of public hearings for the 2700 MW Lower Siang project in three districts of Arunachal Pradesh. A scanned copy of the notice is attached for reference (Annexure 1).

There are a number of legal reasons due to which the public hearings need to be cancelled, here are a few of them:

1)      Public hearing on the same day and time in the West Siang, East Siang and Upper Siang districts of Arunachal Pradesh 

There are a number of local persons/clans/local communities who have land directly affected by the Lower Siang project cross-cutting the district boundaries. Such persons/clans/local communities will not be able to exercise their legal right to participate in all the public hearings in the districts where their ancestral lands are affected, since they are being held on the same day, at the same time. This is a gross violation of the letter and spirit of the EIA notification 2006 as well as the article 14 of Right to equality and article 19, the freedom of Speech under the Constitution of India.  

It is crucial that the public hearings are held in the three districts with sufficient days in between to enable the affected persons to participate in the public hearings wherever their ancestral lands are affected.

It cannot be argued that they should put their viewpoints in one of the public hearings in one of the districts. It is their legal right to participate in the public hearings wherever their lands are affected. This is a clear ground for cancellation of the public hearings and re-announcement  by keeping sufficient days in between hearings being held in different districts.

2)      Location of public hearing venue more than 100 km. away from 11 villages

The public hearing venue fixed for the East Siang district is Pasighat, the district headquarters, in the downstream-affected area of the project. While the APSPCB is welcome to organise a separate public hearing for the downstream-affected area, this is an extremely inconvenient location for the upstream-affected villagers in the East Siang district who are directly affected. And Pasighat town is nowhere listed as an affected village/area/circle in the EIA,EMP and Social Impact Assessment report of the Project Proponent. (Attached is the list of the affected villages as prepared by WAPCOS for the project.

The Public Hearing for Upper Siang District is also fixed at Katan which is 40 Kms away from Geku villages, which is encompassing the majority of the villages to be affected by the dam and above all there are not even a single Govt/Public or Private transport plying/ operating there. And the only village which is going to be completely submerged happens to be Pongging village under Upper Siang district, and the people have to walk on foot covering a distance of 17 kilometers to reach Katan as there is no Public/Private/Govt Transport system plying there.

Out of the 25 villages directly affected in East Siang district, at least 11 are more than 100 kms. away from the public hearing venue! In fact Riga village, one of the severely affected village under East Siang District is 172 km. away from Pasighat. A further nine villages are 60 – 100 km. away. Please note that 6 (Six) villages have to walk for up to 12 km. even before reaching the motor able road.

It is clear that the public hearing venue in East Siang district has been decided in order to disallow active participation of directly affected villages. This is completely unacceptable as per the letter and spirit of the EIA notification 2006 and various court orders/judgements on the need for proximity of the public hearing venue to the affected area. Public hearings cannot be located as per convenience of government officials who do not want to travel to affected areas and stay in the district headquarters. This another strong ground why the public hearings announced for 31st January 2014 have to be cancelled immediately.

And Chapter II U/s 5 of The Right to Fair Compensation and Transparent Land Acquisition Relief and Resettlement Act 2013 also clearly states that Public Hearing should be held in the Affected area and not otherwise.

3)      Siang river basin cumulative impact assessment study is not complete and placed in the public domain at designated places before public hearing

Section 9.4 of Form I of the EIA notification requires that cumulative impacts of a project are examined during the EC process. Further the Ministry of Environment and Forests (MoEF) has issued an OM dated 28th May 2013 stating that it will consider hydropower projects based on cumulative impact assessment and carrying capacity studies. The OM is attached as Annexure 2.

The OM states that:

“While  the first project in a basin could come up without insisting on cumulative study for all subsequent hydro-power projects in the basin it should be incumbent on the developer’ of the second/other project(s) to incorporate all possible and potential impact of other project(s) in the basin to get a cumulative impact assessment done.”

An important aspect of Appraisal done by EAC/MoEF is detailed scrutiny done of all documents including public consultation proceedings. As per the EIA notification 2006 (section 9.4 of Form I) and the MoEF’s OM dated 28th May 2013 if cumulative impacts studies have to be the basis for decision-making, then such studies have to placed in the public domain at designated places 30 days prior to the public hearing.

However, the Siang river basin cumulative impact assessment is neither complete nor placed in the public domain at the designated places prior to the public hearing. Please note that this study currently underway is looking at all projects in the Siang river basin (Siang and its tributaries).

Although we disagree with the logic that the first project could come up without ‘insisting’ on a cumulative impact assessment study (since that project could be the most ecologically and socially destructive), in this case Lower Siang is NOT even the first project in the river basin for which either a public hearing is being held or being considered for environmental clearance. A number of public hearings have been held for other projects in Siang river basin and projects have also been already considered for Appraisal by EAC/MoEF. In fact 1000 MW Siyom and 700 MW Tato II project in the Siang river basin have already received final environmental clearance from the MoEF.

By no stretch of imagination is the 2700 MW Lower Siang project the first project being considered in the Siang river basin. Therefore as per the MoEF’s own OM dated 28th May 2013, Siang river basin cumulative impact assessment will first have to be completed. Public hearing should only be held after this is completed and these reports are placed in the public domain at least 30 days before the hearing.

Keeping all this in mind we strongly urge the MoEF to direct the APSPCB to cancel the Illegally notified public hearings proposed for the 2700 MW Lower Siang project on 31st January 2014.

Thanking you,

Sincerely,

Vijay Taram  Oyar Gao   Tayek Mize  Tasong Mibang    Takar Komut   Kento Jini  Reken Ingo

Forum for Siang Dialogue, Siang Peoples’ Forum, Sirit Siyom Banggo Dam Affected Peoples’ Forum, Siang Bachao Andolan, Nyiko Bachao Forum

Cc:

1) EAC on River Valley & Hydroelectric projects

2) Chairperson, Arunachal Pradesh State Pollution Control Board

3) Member Secretary, Arunachal Pradesh State Pollution Control Board

Arunachal Pradesh

Letter to APSPCB – Non-availability of Complete EIA-EMP Report of Lower Siang HEP is a Violation of statutory Norms

21st January 2014

To

Chairman and Member Secretary,

Arunachal Pradesh State Pollution Control Board

Paryavaran Bhawan, Yupia Road

Pappu Hills, Naharlagun

E-mail id – arunachalspcb@gmail.com

Sub: Lower Siang HEP (2700 MW) EIA-EMP Report not fully available on APSPCB website; many links not working; Public hearing will be illegal without full EIA-EMP in public domain

Respected Sir,

This is regarding the EIA-EMP report of Lower Siang HEP (2700 MW) uploaded on APSPCB website. The public hearing for the Lower Siang HEP is schedule to be held on 31st January 2014.

As per the EIA notification of 2006 the full and complete EIA and EMP report should be made available on State Pollution Control Board website, in this case your website at least 30 days in advance of public hearing date as this is necessary not only for the affected people but also for wider consultations for concerned individuals and groups, as required under the EIA Notification. However, full EIA-EMP are not available on your website, with at least three chapters of EIA, one chapter of EMP and several annexures not opening, even ten days before the public hearing date.

It is very surprising and confusing to most people to see that the reports have been uploaded in 145 parts totaling 320 MB file size. These documents should have been uploaded as five reports as done for EIA-EMP report of several other projects. However, we have gone through all the files available on APSPCB website and based on perusal of these files, we find that crucial parts of the statutorily required documents are not available on APSPCB website. The list of missing chapters and annexures with the name of the report is given below. A screenshot of the links to these chapters are also attached and annexure as mentioned below. 

No Chapter/Figure Report Status Attached
1 Chapter 2 – CONCEPT & METHODOLOGY EIA Failed to upload Annexure 1
2 Chapter 10 – AQUATIC ECOLOGY FISH & FISHERIES EIA An incomplete, possibly irrelevant table on a 1-page Annexure 2
3 Chapter 12 – CONSTRUCTION METHODOLOGY EIA Failed to upload Annexure 3
4 Chapter 10 –  REHABILITATION & RESETTLEMENT PLAN EMP Failed to upload Annexure 4
5 Fig 3.3 – Gradient profile of Siang river including its major and minor tributaries of the Siang river catchment EIA Not uploaded
6 Fig 3.4 – Gradient profile of the Siang river with its main tributaries in the Siang river catchment area EIA Not uploaded
7 Fig 7.3 – Land use/ land cover map of the submergence area of the proposed Lower Siang H.E. project EIA Failed to upload Annexure 5
8 Fig. 2.3 – Drainage map of the free-draining catchment area of the proposed Lower Siang H.E. project EMP Not uploaded
9 Fig 7.3 & 7.4 – Cross-section at the proposed dumping site EMP Incomplete, failed to upload Annexure 6

We therefore request you to upload these chapters immediately and also upload smaller size single documents of each report for the perusal of the local people and all concerned. In the meanwhile, since non availability of full EIA-EMP on pollution control website a month before the public hearing is a statutory violation, we request you to cancel the public hearing now slated for Jan 31st, 2014 as holding a public hearing without full EIA-EMP on the APSPCB website a month before the PH will not be legally tenable.

Thanking you, we will look for your early response,

Yours Sincerely

Parag Jyoti Saikia

South Asia Network on Dams, Rivers & People (SANDRP), 86-D, AD Block, Shalimar Bagh, Delhi – 110 088

Tel: 91-11- 2748 4654/55; https://sandrp.wordpress.com/, https://sandrp.in/

Arunachal Pradesh

Kalai II Public Hearing Held by Suppressing the Public

Lohit Basin Peoples’ forum for Project Affected Families

Tezu, Arunachal Pradesh

Press Note                                                                                                                                        January 20, 2014

Kalai II Public hearing was full of violations, must be cancelled 

Affected people intimidated, beaten up and not allowed to speak by police & politicians

The statutory Public hearing conducted on Saturday, January 18, 2014 at Hawaii in Anjaw district in Arunachal Pradesh about the proposed 1200 MW Kalai II hydropower project in Lohit River Basin was marked by some serious violations that included intimidation of the affected people who wanted to raise questions and speak up, several people getting beaten up by the police and others, people that were not allowed to speak up, taking over of the public hearing by the MLA with his  six hour long speech and public hearing stretched beyond midnight, apparently to manipulate the minutes of the public hearing. All these are serious violations of all the accepted norms of public hearing and cannot be acceptable. This is in addition to many procedural violations that were communicated  through our written letter to Arunachal Pradesh State Pollution Control Board, Deputy Commissioner of the Anjaw district and members of the Expert Appraisal Committee  on River Valley Projects in Union Ministry of Environment and Forests, the letter remains unanswered.

A public hearing without public: Chairs remain vacant at the  Kalai II public hearing venue
A public hearing without public: Chairs remain vacant at the Kalai II public hearing venue

 

The hearing began at 10 AM with officials of WAPCOS (the EIA consultant agency) briefing the public about the EIA report. When Mr. Bihenso Pul, one of the project affected person stood up to question the officials on their false claim that a consultation was held with the affected land owners in the third stage of EIA, all of a sudden, the local MLA Mr. Kalikho Pul along with his close relatives and workers started threatening him and warning him of dire consequences. Witnessing this, the whole project affected public who had come to take part in the public hearing stood up in support and defense of Mr. Bihenso Pul. Following this, the personnel of Arunachal Pradesh Police started indiscriminately assaulting and lathi charging the public. Mr. Soti Tawsik, a Gram Panchayat Member from Nukung village from INC ticket was also grievously injured due to the lathi charge by police personnel when he tried to raise questions and express his opinion on the project. He was referred to Dibrugarh for further treatment as he was in a critical condition. Others injured include Baah Tawsik and Checheso Tawsik.

A Public hearing held by Suppressing the Public:  The Injury Mark from the Lathi charge is Clear on his Forehead
A Public hearing held by Suppressing the Public:
The Injury Mark from the Lathi charge is Clear on his Forehead

During the presentation on EIA by WAPCOS (it is an agency under Union Ministry of Water Resources, which itself functions like a Big Dam lobby and hence there is conflict  of interest in WAPCOS doing any impact assessment  work since impact assessment is supposed to be done by an unbiased, independent agency. Moreover WAPCOS is also involved in feasibility studies and detailed project reports for justification of projects, its track record is also very poor with both Expert Appraisal Committee and Forest Adivosry Committee of MoEF having crticised their work), even the illiterate villagers started expressing resentment over WAPCOS’s complete lack of knowledge on the topology, flora and fauna of the project affected region which was evident from the multiple factual mistakes made by the during the presentation. They were showing pictures of common fishes found in Parshuram Kund region and telling the villagers that the fishes were photographed from must higher elevation Kalai II project affected region. They did not even recognize the species of common Mynah available in the region and were calling it with different names.

The Public hearing was completely dominated by Shri. Kalikho Pul, the local MLA who spoke for 6 hours at a stretch starting from 6 pm, trying to convince the project affected families with misleading facts, while his workers and the Police personnel were highhandedly suppressing and manhandling every single person who stood to express his opinion or raise a question. Mr. Kalikho Pul also levelled baseless allegation of corruption against Mr. Bihenso Pul who is not even a government servant. Eventually, after being frustrated by the arbitrary, coercive and one sided conduct of the Public hearing, the project affected people started leaving the venue shouting slogans against the MLA and the administration stating they would never succumb to such illegitimate pressure tactics. If the public had not shown restrain and maturity during the mindless repressive act by police the incident could have taken an extremely dangerous turn.

An overwhelming about 60% of the affected people are against the project now being taken up. Even those 30% of affected who may be giving conditional support, have put forward a list of 23 conditions that are yet to be responded to. The rest 10% of the affected are as yet undecided. It is thus clear that the project as it stands do not have public support and with people not allowed to participate in the public hearing, the opposition will only get stronger. It may also be added that the same WAPCOS had done a shoddy EIA of the under construction Lower Subansiri project that remains stall for over 25 months now due to public opposition. The fate of  Kalai II, if pushed without proper credible assessment of the  project  and basin level impacts and credible public hearing, will  not be any different.

Finally, all the members of public left the meeting venue. The request to postpone the Public hearing in view of the incident to the next day by Mr. Bihenso Pul too was turned down and the hearing continued past 12 in midnight with only the Deputy Commissioner of Anjaw District, officials of Reliance Power Limited, Officials of WAPCOS & APSPCB and Mr. Kalikho Pul, Local MLA Anjaw district present during the meeting. This was clearly done to ensure finalization of manipulated minutes of public hearing.

This public hearing must be cancelled, an independent, credible enquiry conducted in the way in was sought to be conducted and in any case a fresh public hearing should be ordered after taking care of all the legal violations.

Bihensu Pul                                                                                                                                Birenso Pul

Chairman, 09402230335/ 08974543363,                                                                          Affected farmer

pulbihenso2012@gmail.com

Dams

Pinjal and Gargai Dams: Affecting Tribal Areas, Tansa Sanctuary, Western Ghats: Shall we still go ahead?

 SANDRP made the following submissions on Pinjal and Gargai Dam proposals which will be considered for First Satge Environmental Clearance ( Terms of References or TORs) by the Expert Appraisal Committee (EAC) of the Ministry of Environment and Forests (MoEF) of the 20th and 21st of January.

As is clear from the submissions below, there are major issues with these projects: Pinjal Dam will submerge 2100 hectares of forest land in 11 villages in Western Ghats, it falls under the Schdeule 5 of Indian Constituion: a special schedule for tribal areas. Local tribal communities are opposing the dam, but need support.

Gargai Dam will submerge 6 villages and 750 hectares of Tansa Sanctuary. Tansa Sanctuary is already scarred by many developments, including the Middle Vaitarna Dam. Putting more pressure on a protected area which also provides ecological services to Mumbai region is not justified.

Finally, these dams are for supply drinking and industrial water to Mumbai. But is the Mumbai Metropolitan region using its available water wisely? Has it explored any options like recycling and reuse of sewage water, the way Singapore or Chennai has? Is it serious about Rainwater harvesting? Has it taken accountable steps against the 1000+ MLD water that is wasted every day through leakages?

If answeres to the above are negative, is the region justified in asking for more dams, affecting people and nature? (SANDRP’s detailed (draft) report on the many dams coming up around Mumbai can be found here:https://sandrp.in/Mumbai_Dams_Draft_Report_Dec_2013.pdf)

If you agree with the points in the submission below, please consider making a similar submission to the MoEF.

__________________________

To,

Chairperson and Members,

Expert Appraisal Committee, River Valley and Hydroelectric Projects

Ministry of Environment and Forests,

New Delhi

Subject: Urgent, multiple concerns about considering Pinjal Multipurpose Project for TORs

Respected Chairperson and members,

We are writing to you as Pinjal Multipurpose Project is on agenda of EAC for TORs for the 71st meeting to be held in January 2014.

This is a second submission we are making about Pinjal Multipurpose Project. The project was on Agenda for the 70th EAC meeting, but was dropped without stating any reasons.

We had organized a meeting on dams coming up around Mumbai on the 18th December 2013 and were also a part of farmers meeting at Pinjal Dam site. This submission draws on both these events. (Please see a Background Report on Dams around Mumbai here:https://sandrp.in/Mumbai_Dams_Draft_Report_Dec_2013.pdf)

At these meetings, there was unanimous conclusion that:

1.      No dams should be considered for Mumbai Metro Region (which includes MCGM) before cumulative impact assessment of the dams and developments in the region:

More than 12 dams in close proximity are in various stages of completion, construction and planning for supplying drinking and industrial water to Mumbai Metropolitan region (MMR). The affected region is home to various tribes and majority area id under the Fifth Schedule of the Constitution of India.

As per cursory account of the current (unassessed) cumulative impacts, these dams will result in submergence of more than 22000 hectares of this region, including 7000 hectares of forest land and will affect more than 100,000 tribals.

Looking at these massive impacts, Forest Advisory Committee, MoEF, while giving stage I clearance to Kalu Dam (also in Thane district), has recommended “A cumulative Impact Assessment of all drinking water projects in the region on the flora and fauna of the area will be undertaken by the state government at the cost of the User Agency and mitigative measures and other conditions suggested in the study will be binding on the User Agency.” This has been reiterated in the Stage I clearance letter of the MoEF dated 31st May 2013 (attached).

Even according to MoEF’s May 28, 2013 notification, cumulative impacts of multiple projects should be done before considering clearances for the next project. Hence, per MoEFs instructions itself, TORs should be issued only in light of the Cumulative Impact Assessment Study.

Hence, TORs should not be recommended to Pinjal Project without such an assessment is completed and public consultations on the same conducted.

Planned, under construction and existing dams around Mumbai. Map: SANDRP
Planned, under construction and existing dams around Mumbai. Map: SANDRP

2.       Strong opposition to the project:

Pinjal Project will be submerging 11 villages in Jawhar and Mokhada talukas in Thane district. This is predominantly a tribal region, with many areas falling under Schedule 5 of the Constitution and tribal sub plan. All the tribals from affected villages are strongly against the project. They have convened many meetings and have also passed Gram Sabha resolutions against the project. Considering the strong local opposition, Pinjal Dam should not be recommended TORs because:

a.     Violation of Panchayat (Extension to Scheduled Areas) Act 1996:

As the entire affected region falls under the fifth schedule of the constitution, it comes under the PESA Act. PESA mandates that Gram Sabha consent is a mandatory pre requisite for any project being considered in scheduled region. In addition, PESA lays stress on local self-governance of tribal regions by tribals. Considering this and unanimous opposition to Pinjal Dam project, it should not be considered for TORs by the MoEF.

People meeting protesting Pinjal Dam. Date: 04.01.14, Photo: Amit Tillu for SANDRP
People’s meeting protesting Pinjal Dam. Date: 04.01.14, Photo: Amit Tillu for SANDRP

b.    Forest Rights as per the Forest Rights Act 2006 are not settled: 

Lives of the tribals in this region an inextricably linked with their forests. However, their community and individual Forest Rights on their forests have not yet been recorded or settled. In the absence of this, no project should be considered from this region that will affect their forests, as per the Forest Rights Act 2006.

Seeta Bai from Tansa Forests, Western Ghats
Seeta bai, from Tansa Forests, Ogade village which will be submerged for Gargai Dam. Photo: Parineeta Dandekar, SANDRP

c.     Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act (2013), section 42 (i)says: “As far as possible no land acquisition shall be made in scheduled areas”.

It also says: Section 42 (3) prior informed consent of gram sabhas is mandatory in Schedule 5 regions.

Considering the above legal issues and current local opposition, Pinjal Dam should not be considered by the MoEF.

3.     Ecosensitive Zone of the Western Ghats world Heritage Site:

Almost all of the affected villages by Pinjal Dam fall under Ecosensitive Area as per HLWG (High Level Working Group) on Western Ghats report and Eco-sensitive Zone I By WGEEP (Western Ghats Expert Ecology Panel) Report. While The HLWG mandates Gram Sabha consent prior to any developmental activity in Eco-sensitive Region, WGEEP bans large dams in ESZ I. Hence, looking at both these reports as well as extremely rich local biodiversity, TORs should not be recommended for Pinjal Dam Project.

Forests to be submergec by Gargai Dam Photo: Parineeta Dandekar, SANDRP
Forests to be submergec by Gargai Dam Photo: Parineeta Dandekar, SANDRP

4.       Serious misrepresentation of Clearance from NBWL:

Form I ( Table 3, Page 10) submitted by the project developer to MoEF says: “Permission from National Wild Life Board, New Delhi, Government of India for geo-technical investigations.”

To the best of our knowledge and from the minutes of the NBWL meetings, Pinjal project has never been considered by the NBWL for any clearance. If this is indeed the case, we ask the EAC to take strong action against the user agency for providing false and misleading information.

5.       Contradictions in PFR, Form I and additional information:

There are several serious errors in the Form I and the PFR uploaded on MoEF website. For example:

Form I states that the Gross Storage Capacity of the dam will be 421.6 MCM (Table 1, Section 5). But, PFR states that gross Storage Capacity of the dam will be 483 MCM (Page 8, PFR)

Additional information sheet says that annual yield at Pinjal dam site at 95% dependability is 421.6 MCM, while PFR states the same as 524 MCM.

PFR states 865 MLD water from Pinjal is earmarked for Mumbai, while the Additional information letter puts the same value at 1073 MLD!

Looking at these serious contradictions, the PFR, Form I and the letter about additional information needs to be reworked and the project should not be considered for TORs on the basis of such fundamentally misleading information.

Tribal settlement at Ogade village which will be submerged. Photo: Parineeta Dandekar, SANDRP
Tribal settlement at Ogade village which will be submerged for Gargai Dam. Photo: Parineeta Dandekar, SANDRP

6.       Form I says ‘No cumulative impacts”:

Form I says that there are no cumulative impacts envisaged (Section 9.4). However, there are very serious cumulative impacts of dams planned and under construction in the region, in addition to the existing projects. As states above, even the FAC and the MoEF has asked for a Cumulative Impact Assessment study of all dams in the region. Hence, the information provided in the Form I is wrong and the project should not be recommended TORs based on such misleading information.

7.       Serious errors in the Prefeasibility Report

The prefeasibility Report prepared by Mott Macdonald who is also the contractor for MCGM) has many errors. Some examples:

·         2011 Report gives MCGMs population as 14.5 million. (Page 1). According to Census of India Reports, population of Municipal Corporation of Greater Mumbai (MCGM) in 2011 was in fact 12.4 million.

·         Pre-feasibility report has not relied on census, but on projections, which have proved wrong. Its water demand calculation based on these incorrect predictions are also wrong,

·         It assumes that in 2011, the slum population is 40% and planned is 60%, in fact according to census as well as Deputy Commissioner of Mumbai[1], it is exactly opposite ( slum population is 60% and planned is 40%) Thus, again changing the water demand projections.

·         Further water demand projects are based on exuberant figures like 240 lpcd. This is unjustified and no dam development should happen at a huge social and ecological cost for lavish water usage.

8.       Current water demand of Mumbai is misrepresented

·         The PFR as well as Municipal Commissioner’s note state that current water demand in Mumbai is 4240 MLD and there is a shortfall in supply currently.

·         This is completely wrong. According to Census 2011, population of Mumbai is 12.4 million, with a majority population living in the slums. According to Deputy Municipal Commissioner of Mumbai[2], slum population gets 100 lpcd (liters per capita per day) and non-slum population gets 200 lpcd water. Consumption is 686 MLD (Million Liters per Day) for slum and 1297 MLD for non-slum population, which comes to a total of 1983 MLD. It should be added here that slums constructed post 1995 are currently not entitled to any water from BMC.

·         Total water supply to MCGM at source is 3520 MLD.[3] According to the Deputy Commissioner, per capita water availability currently is greater than 180 lpcd, which is still higher than water supplied to London (150 lpcd), Singapore (160 lpcd) and Paris (150 lpcd). It is clear that there is NO current shortfall of water in Mumbai.

·         At the same time, if supply at source is 3520 MLD and the use is 1983 MLD for drinking water, 260 MLD for commercial and industrial uses[4] and 120 MLD en route supply, there is an additional 1157 MLD water that is available. That is 32.86% of the current water supplied at source is unaccounted for. It is assumed that leakages are to the tune of 25% supply at the source (which is very high), we still have 7.86% water supplied that is unaccounted for. This means 880 MLD of water! Nearly equal to two large dams Mumbai is planning to build!

·         But MCGM and PFR is stating that current demand is 4240 MLD[5] and that there is a current shortfall of at least 720 MLD. Where does this 4240 MLD figure come from? This is assuming 240 lpcd water supply which is extremely high and unjustified even by international standards!

This indicates that the PFR and Additional Information letter are misrepresenting and exaggerating the water demand of Mumbai, to justify an ecologically and socially destructive dam projects in the Western Ghats. MoEF should not recommend TORs for Pinjal Dam in this case.

9.       No options Assessment about Mumbai’s Water supply options

Before exploring options like new dams, Mumbai needs to explore and exploit its existing options. Some of these include:

Inequitable water supply: parts of MCGM get less than 40 lpcd water, some slum areas receive no water, while affluent addresses get over 300 lpcd water. Equitable, metered water supply will reduce the misleading water demand.

Fixing leakages and wastage: As per the PFR itself, MCGM wastes an unbelievable 1208 MLD water every day in leakages, which is more than the capacity of Pinjal and more than twice the capacity of Middle Vaitarna Dam which is completed this year for water supply to MCGM. There is no transparent program for fixing leakages and wastages in the system.

Rainwater harvesting: MMR receives average rainfall upto 2500 mm annually and thus has a huge potential of rainwater harvesting. MCGM has made rainwater harvesting compulsory for buildings above 300 sq. meters since 2007. However, MCGM needs to make RWH compulsory for all government buildings, all institutional buildings, all commercial buildings, all colleges, schools, parks, stations, flyovers, malls, multiplexes and give them one year time limit after which consequences should follow. This should be accompanied by credible monitoring and compliance systems. MCGM has not done this.

There are several examples where residents themselves have set up RWH plants either to recharge bore wells or to store water. Examples of Sea Line Apartments in KharJago Mumbai Movement, or Shivaji Park in the heart of the city indicate the potential and benefits of Rain water harvesting. In Khotwadi slum, a public toilet with washrooms is managed by Triratna Prerna Mandal and does not use a drop of water from MCGM. The facility is used by nearly 1400 people daily and needs approx. 8000 liters of water per day. An ingenuous rainwater harvesting and ring well facility with a storage tank supplies all water needed. (Dhaval Desai, Time is Running out: Does Mumbai have enough water? Observer Research Foundation, 2012). Observer Research Foundation’s report “Why is there a drought of Rainwater harvesting in Mumbai indicated MCGM’s Rainwater harvesting Cell is functioning dismally and does not even have data on number of building that have functioning rainwater harvesting systems or the status of RWH in government buildings. “The condition of the cell is pathetic and it functions in a small room, with leakages, no place for paperwork and severely limited manpower”. This indicates how non-serious Mumbai administration.

Navin Chandra, Sea Line Apratment with harvested rainwater. Photo: Times of India
Navin Chandra, Sea Line Apratment with harvested rainwater. Photo: Times of India

Reuse and recycle sewage MCGM also needs to ensure that as much reuse and recycle of the sewage is affected in the city as possible. MCGM needs to make such systems compulsory for all government buildings, all institutional buildings, all commercial buildings, all colleges, schools, parks, stations, flyovers, malls, multiplexes and give them one year time limit after which consequences should follow. This should be accompanied by credible monitoring and compliance systems. MCGM has not done this.

Protection of local water systems Mumbai Metro Region also needs to protect all local water bodies including tanks, rivers, forests and wetlands that help harvest and recharge water. There is again no effective step in this direction.

Several lakes exist in Vasai Virar, Kalyan Dombivali, navi Mumbai, etc which can be protected and used as conjunctive sources. Bhiwandi still uses a lake in the city.  Photo: Vasai Today
Several lakes exist in Vasai Virar, Kalyan Dombivali, navi Mumbai, etc which can be protected and used as conjunctive sources. Bhiwandi still uses a lake in the city. Photo: Vasai Today

Demand Side Management In addition to above there are many other demand side management measures can be adopting, including use and incentives for water conserving flushes and such other appliances, among others.

No new projects for exogenous water supply sources should be considered until all these options have not been explored by the Mumbai Municipal Corporation and MMR bodies through credible policies and programmes.

10.   Contradicts the 12th Five Year Plan:

The 12th Five Year Plan Working Group Report on Urban Water states: “cities must only get funds for water projects, when they have accounted for the water supply from local water bodies and have protected these water bodies and their catchments. This precondition will force protection and build the infrastructure, which will supply locally and then take back sewage also locally”[6]. And that rather than focussing only on supply management, Investments in water supply must focus on demand management, reducing intra-city inequity and on quality of water supplied.

We hope that the EAC considers this roadmap laid out by the 12th Five Year Plan, Working Group on Urban and Industrial Water Supply and Sanitation.

Conclusion Looking at all the serious issues above, we are sure that the EAC will not recommend TORs for Pinjal Dam and will respect the ecological integrity of the region as well as the protests from tribals who are entirely dependent on their forests for survival. These forests are also the lungs of Mumbai Metro Region and Western Ghats.

We and the affected tribals of Pinjal are looking forward to a wise decision by the EAC considering all the issues mentioned above and reject the Pinjal Dam proposal.

Thanking You,

Sincerely,

SANDRP

 

Submission on Gargai Dam:

It is based on the same lines as above. Additional points:

Serious misrepresentation of Clearance from NBWL in case of Gargai Dam:

Form I (Table 3, Page 10) submitted by the project developer to MoEF says: “Permission from National Wild Life Board, New Delhi, Government of India for geo-technical investigations.” This is completely false information.

The project was considered by the Standing Committee of the National Board for Wildlife in its 28th meeting (minutes attached) which states:

  • “At the time of approval for the Shahi project, the project authority had given a written undertaking that “It is not necessary to construct any new source for water supply up to year 2031”. He (Kishor Rithe, NBWL) also mentioned that the former Chief Wildlife Warden himself had rejected this proposal as this dam will destroy 750 ha of good forest area of Tansa sanctuary and hence he would not support this proposal.”
  • “The committee, after discussions, decided to have a site inspection by Dr Asad Rahmani and take a view based on the site inspection report.”

However, in the 29th meeting, (See here: http://www.moef.nic.in/sites/default/files/NBWL-29th-MOM-06-06-13.pdf)non-official member Kishore Rithe writes: “The Proposal for survey and investigation for Gargai project in Tansa Sanctuary for Gargai River Project, Maharashtra   which requires 750 ha forest from Tansa Sanctuary, was rejected by all the non-official members and not suggested any site inspection. However the final minutes has recorded that the “The committee, after discussions, decided to have a site inspection by Dr Asad Rahmani and take a view based on the site inspection report.”

Considering the above, it is clear that not only does the project not have ANY clearance from NBWL, but ALL non-official members have rejected the project. When this is clearly stated in NBWL minutes, it is shocking to read the false information being provided by the user agency. We urge the EAC to take strong action against such misleading information being provided to the MoEF.

________________

Selected media reports about dams around Mumbai:

1. Front page report in Hindustan Times on 18th Dec

http://paper.hindustantimes.com/epaper/viewer.aspx

2. Report in Times of India

http://timesofindia.indiatimes.com/home/environment/developmental-issues/Planned-for-urban-needs-12-dams-to-hit-tribals-hard/articleshow/27548259.cms

3. News report about the meeting on ABPhttp://www.youtube.com/watch?v=WpGPcEpL9eI

Arunachal Pradesh

EIA-EMP of Kalai II Hydropower Project Doesn’t Comply with its Terms of Reference

Kalai II HEP – Status of compliance with TOR in EIA and EMP:

Serious non compliance of EIA-EMP: EIA-EMP must go back to consultants WAPCOS

Public hearing based on such EIA-EMP will not be legally valid

The EIA EMP reports of the proposed 1200 MW Kalai II HEP in Lohit basin in Anjaw district in Arunachal Pradesh has been put up on the Arunachal Pradesh Pollution Control Board in advance of the public hearing slated for January 18, 2014. The EIA-EMP report is supposed to comply with the Terms of Reference (TOR) for the EIA-EMP given by the EAC and MoEF, this is statutory requirement as per the EIA notification of Sept 2006. We have just checked this compliance and find that the EIA and EMP reports have not fulfilled a very large number of the TOR (Terms of Reference) that the project was to cover in EIA-EMP as per the TOR clearance given for the project on 9.12.2009. Such EIA-EMP will clearly not be acceptable even from statutory and legal point of view and cannot be basis for a public hearing. Hence Arunachal Pradesh State Pollution Control Board (APSPCB) and MoEF should immediately cancel the public hearing and ask the EIA-EMP consultants to comply first with the TOR.

A letter has been sent to APSPCB pointing out the violation of norms in organizing the public hearing and asking them to cancel the public hearing. This letter is available at “Letter to APSPCB – Public Hearing for Kalai-II HEP to be held Violating the Norms”. A detailed critique of the EIA-EMP report of Kalai II project is also available at “Critique of Kalai II HEP’s Environment Impact Assessment (EIA) Study and Environment Management Plan

Invalid extension since EIA-EMP does not comply with the TOR Here it may be added that as per minutes of 70th EAC meeting dated Dec 10-11, 2013, “In the mean while, MOEF issued an Office Memorandum dated 22-Mar-10 which stipulates that the proposals which were granted TORs prior to the issue of this OM, the EIA / EMP reports should be submitted after public consultation no later than four years from the date of the grant of the TORs with primary data not older than three years. Thus the TOR issued to the project on 9th December 2009 is valid up to 8th December 2013”. By this norm, the Kalai II TOR clearance should have lapsed on Dec 8, 2013. However, EAC decided to give an extension to TOR for this project, since the project developer claimed, as noted in EAC minutes, “With the completion of all the studies, the draft EIA/EMP report for 1200MW Kalai-II HEP was prepared and submitted by the developer to Arunachal Pradesh State Pollution Control Board (APSPCB) vide letter dated 31st July 2013…”. However, this assumes that the EIA-EMP submitted complies with the TOR given by MoEF. But this analysis shows that there is serious non compliance of the EIA-EMP with the TOR and hence submission of such fundamentally inadequate EIA-EMP cannot be a valid reason for providing TOR extension beyong legally stipulated period.

Location of Kalai II HEP. Source: EIA report
Location of Kalai II HEP. Source: EIA report

A list of TOR noncompliancein the EIA-EMP is given below.

Noncompliance in EIA Report:

Geological and Geophysical Aspects

  1. Regional Geology and structure of the catchment – some details only about has been mentioned in the EIA, the latter is not available
  2. Seismicity , tectonics and history of past earthquakes in the area – the EIA only mentioned about seismicity, the latter two has been completely ignored
  3. Critical review of the geological features around the project area – not available
  4. Impact of project on geological environment – not available
  5. Justification for location & execution of the project in relation to structural components (Dam height) – not available

Hydrology

  1. Graph of 10 – daily discharge before and after the project at the dam site immediately below the dam should be provided i n the EIA study – Not available
  2. The TOR mentioned “An elementary stream gauging station should be established at a suitable location downstream to the Dam site of the project” and “Installation of two Rainfall Gauge Stations at upstream of dam site” but none of these has been complied with.

Surprisingly the EIA also mentioned “No gauge and discharge (G&D) data is available at the Kalai-II project site or in the neighborhood.”

Biological resources

1)   “Cropping and horticulture pattern and practices in the study area” – no mention of this in the EIA

2)   Regarding identification of rare and endangered flora and fauna the EIA report mentioned only one “During the study in various seasons in Kalai-II HE project area, following IUCN Red List of threatened plant, Lagerstroemia minuticarpa falls under endangered category. Rest of the species are common in Arunachal Pradesh. However, this species though observed in the study area but not found in the land to be acquired for the project.” (section 8.7 page 8 -22) This is a strange claim that the species is observed in the study area but not found in the land for the project.

3) Fish and Fisheries

a)   The 5 location of study of Fish migrations & Breeding grounds was not done

b)   Impact of Barrage building on fish migration and habitat degradation was not studied

c)   Overall ecological impact upto 10 Km d/ s from the confluence of the TRT with the river or reach of the river in India have not been not studied. The impact of untreated and waste water into the river was not studied and no alternatives explored.

4)                  In the part of impact prediction, impacts on flora and fauna due to changed water quality has not been assessed

Socio Economic aspects In terms of Socio-economic aspects the following should have been included in the EIA report.

· Land details*

· Demographic profile

· Ethnographic Profile

· Economic structure

· Development profile

· Agricultural practices

· Cultural and aesthetics sites

· Infrastructure facilities: education, health and hygiene, communication network, etc.

· Impact on socio- cultural and ethnographic aspects due to Construction of Barrage

But the EIA does not do several of these profiles and limits itself to – Demographic profile, Educational levels, Occupational Profile, Land holding pattern, Assets owned and Livestock and other socio-economic parameters etc.

In page 11- 8 EIA report says “Impacts on cultural, archeological and religious properties Monuments of cultural/ religious/ historical/ archaeological importance are not reported in the project area. Thus, no impacts on such structures is envisaged.” However, the EIA should have looked into the impact of project on places of cultural, religious importance for the  local communities.

Impacts related to Land The EIA ignores what has been suggested in terms of impact prediction for land. The EIA completely ignores –

a) Changes in land use and drainage pattern

b) Changes in land quality including effects of waste disposal

c) River bank and their stability

d) Impact due to submergence

However, in page no 10-23 in the section “Impact of Impoundment on Landuse” the EIA mentions: “The construction of the dam would form the reservoir which will submerge about 640 ha of area in upstream. The area witnessed jhum/shift cultivation practiced by local inhabitants. Submergence of the area would not impact much on the prevailing land use pattern.” This is a false and misleading statement since in the hilly areas of Arunachal Pradesh, shifting cultivation is the main process of cultivation and submergence of such a large area is sure to have impacts on land environment.

TOR Noncompliance in Environment Management Plan:

Under Catchment Area Treatment Plan, the TOR letter had asked the project proponent to prepare 5 thematic maps v i z . Slope map, Drainage map, soil map, Land use/ Land cover Map, Aspect map. Basing on these maps an Erosion Intensity map should have been prepared. But the EMP only has two maps Slope map and Land use Map. No Erosion Intensity map was prepared.

Under Compensatory Afforestation Plan it was mentioned that “The choice of species for Afforestation should be suggested and the proper sites for the same should be demarcated on the maps.” There is no map in the EMP report’s chapter on Compensatory Afforestation Plan.

Under Greenbelt Plan the scoping clearance asked for “….suitable plant species should be recommended with physical and financial details. A layout map showing the proposed sites for developing the green belt should be prepared.” But the EMP report chapter on greenbelt does not at all comply with it. It makes no mention of any species and no map had been prepared.

The TOR clearance letter under “Reservoir Rim Treatment Plan” asked for “Layout map showing the landslide/ landslip zones should be prepared.” But the maps provided in chapter 17 of the EMP report are not at all clear and the when zoomed in they get blurred. So the sites, even if they exist in the maps cannot at all the located.

The TOR clearance letter under “Muck Disposal Plan” had asked for “The quantity of muck to be generated and the quantity of muck proposed to be utilized should be calculated.” This was not complied with and EMP report in chapter 6 mentioned only about the muck generated from excavation. Under the same, the scoping clearance also asked for “Layout map showing the dumping sites viz – viz other project components should be prepared.” There is no layout map showing the dumping sites.

The TOR clearance letter under “Restoration Plan For Stone Quarries” asked for “Layout map showing quarry sites vis-à-vis other project components should be prepared.” There is no map prepared for complying with this condition.

For “Landscaping and Restoration Plan” TOR letter asked for proper map showing landscaping and restoration site but this was not complied with in the EIA report.

The TOR letter asked the consultant to include a “Certificate” in EIA/EMP report regarding portion of EIA/EMP prepared by them and data provided by other organization (s)/Laboratories including status of approval of such laboratories. The consultant WAPCOS did not comply with this.

Conclusion These are crucial issues which were specifically mentioned in the TOR letter and EIA-EMP not complying with such crucial issues is unacceptable. The public hearing of the project is schedule to be held on 18.01.2014 but going for public hearing without complying with the condition mentioned in the TOR clearance is against the due process of law. The public hearing of Kalai II project should not be held and the EIA should be sent back to the projects developer. Moreover, as pointed out at the outset, the TOR extension given to the project beyond the stipulated period was based on false claim of submission of EIA-EMP that adheres to the TOR. Thus the extension given is invalid and the project must be asked to apply for TOR clearance afresh as per the MoEF norms. The public hearing if conducted on January 18, 2014 in spite of this, will not stand legal scrutiny.

Parag Jyoti Saikia  (meandering1800@gmail.com)

South Asia Network on Dams, Rivers and People (SANDRP)

 

Arunachal Pradesh

Critique of Kalai II HEP’s Environment Impact Assessment (EIA) Study and Environment Management Plan

The 1200 MW Kalai II HEP located on LohitRiver in Anjaw district of Arunachal Pradesh is being developed by Kalai Power Private Limited (KPPL), which is the Special Purpose Vehicle of Reliance Power Limited. The company had signed the Memorandum of Agreement (MOA) with Govt. of Arunachal Pradesh on 2-Mar-09. The EIA consultant for the project is WAPCOS. The project was recommended for scoping clearance in 31st Meeting of Expert Appraisal Committee (EAC) held on 21-22 October 2009. The project was considered in the 70th EAC meeting on 10-11 Dec 2013 for extension of TOR validity. The advertisement published in Arunachal Times suggests the date as 18th January 2014.

The EIA study cannot clearly state whether Kalai II is a storage project or a run of the river project. The EIA study is also not clear about the height of the dam. Detail analysis of the EIA study reveals that the study is incomplete, inadequate and shoddy. The study cannot qualify to be called an EIA study.

It is also important to note that EIA and EMP reports prepared by WAPCOS have not fulfilled a very large number of the TOR (Terms of Reference) that the project was to cover in EIA-EMP as per the TOR clearance given for the project on 9.12.2009. Such EIA-EMP will clearly not be acceptable even from statutory and legal point of view and cannot be basis for a public hearing. A report on the status of compliance with TOR in EIA and EMP is available here – https://sandrp.wordpress.com/2014/01/15/eia-emp-of-kalai-ii-hydropower-project-doesnt-comply-with-its-terms-of-reference/. Arunachal Pradesh State Pollution Control Board (APSPCB) and MoEF should immediately cancel the public hearing and ask the EIA-EMP consultants to comply with the TOR first. A letter sent to APSPCB in this regard can be found here – https://sandrp.wordpress.com/2014/01/15/letter-to-apspcb-public-hearing-for-kalai-ii-hep-to-be-held-violating-the-norms/.

Issues Related with EIA consultant WAPCOS

Cumulative Impacts Assessment Study of Lohit Basin Prepared by WAPCOS is Farce The local people from Lohit basin have categorically stated that the cumulative impact assessment study done for the Lohit basin by WAPCOS is farce. In a news published in Arunachal Times (available in Annexure I) people have stated “Water and Power Consultancy Services (WAPCOS) had earlier conducted a cumulative impact assessment of various hydropower projects in the entire Lohit river basin, as per the directives of MoEF. WAPCOS made a farce report, completing within 2-3 weeks. The study is very poor and shoddy…..” Now for the Kalai II project the same organization is preparing the EIA report. From the track record of WAPCOS and from the experiences of the people in the Lohit basin, it is clear that an EIA prepared by WAPCOS cannot at be accepted as a complete, unbiased study.

People of Lohit Basin will not Accept Studies done by WAPCOS It is important to note that people of Lohit basin have already expressed their anger and disbelief on studies done by WAPCOS. In a letter written to the Union Minister on Environment and Forests on 15 march 2012 the, Peoples Forum For Project Affected Family (PFPAF) had clearly stated the following “….no study of WAPCOS would be acceptable to the people of the Lohit Valley and other social and environment conscious people for two main reasons. Firstly, WAPCOS is an organisation under the Union Water Resources Ministry, and Union Water Resources Ministry is basically a pro dam lobby. WAPCOS also does other pro dam studies like the feasibility reports and Detailed Project Reports for Big dams, such studies are done in favour of Big dams and an organisation that is doing such business cannot be entrusted to do an environment or cumulative impact assessment study. Secondly, WAPCOS also has had very poor track record and has done very poor quality EIA and CIA reports. Hence, in future, we will not accept any reports done by such organisations.”

It is important to note that when the people of the whole Lohit basin had raised objections against WAPCOS, the government and companies should not have hired WAPCOS the project consultant. This indicates a hidden strategy on the part of the project authorities to employ only pro-dam EIA consultants to get favourable outcomes. 

Location of Kalai II HEP. Source: EIA report
Location of Kalai II HEP. Source: EIA report

Critique of the Kalai II EIA study

Biased EIA An EIA report should be an unbiased assessment of impacts of the project. The EIA report of Kalai II HEP is a biased towards hydropower, as can be seen from what has been written in section 1.3, page 1-3: “In Arunachal Pradesh so far a capacity of 423.5 MW has been developed which is just 0.84 % of the total potential. Hydro projects of about 2600 MW are being constructed which is about 5.17 % of the total potential. It is evident from the above that the capacity developed and under development will be achieved for 3023.5 MW in very near future, still leaving behind a potential of about 47304.5 MW (93.99%).” This shows clear towards hydropower project and this EIA report of Kalai II HEP prepared by WAPCOS cannot be considered a neutral assessment of impacts of the project.

EIA does not mention Maximum Water Level of the reservoir The EIA study does not mention the Maximum Water Level of the reservoir when the dam passes peak flood. It only mentions the FRL as 904.80 m.

Large Submergence Area The area which Kalai II project will submerge is very large considering that it is RoR project. The EIA document in Section 6.4 mentioned “The construction of a 198 m high concrete gravity dam shall create a reservoir of area approx. 640 Ha at FRL of El.904.8m. The reservoir will extend up to 15 km along the river Lohit. The reservoir width shall range from about 600 m to 1000 m over most of its length.” But news report published Arunachal Times states that submergence route extends upto 23 km upstream. The report also stated that the project will submerge the entire Hawai circle and all the major villages directly affecting 1500 people.

It is important to note here is that size of the total area required, the number of affected villages and population mentioned in this EIA is much higher than the numbers mentioned for the project when it was considered for TOR clearance in EAC on 21.10.2009. The minutes of that EAC for Kalai II stated that Total land requirement is 830 ha, which has now grown by 32.5% to 1100 ha (Section 2.2 of EIA), No of affected villages has grown from four villages to 25 (525% increase), No of PAFs has grown from 22 to 595 (2605% increase) and no of affected people has grown from 122 to 2279 (1768% increase). This means that the impacts were grossly understated at scoping stage. Is such gross and deliberate understatement acceptable?

Huge land requirement not justified The project claims to require 1100 ha of land, 370 ha more than the land requirement of 830 ha stated at the time of scoping. This land demand seems unjustified and inflated and cannot be accepted at face value. The EIA does not even attempt to look into this issue.

EIA under estimates the number of affected population Even though the EIA has stated 595 as PAFs it still seems a hugely under stated number of affected families. The report claims that their survey team contacted a total of 595 PAFs where the total population of the project affected area is stated as 2279. But the detailed news report of Arunachal Times says that the project will submerge the entire Hawai circle and all the major villages. If this is true then the project will affect much larger no of people.

It is also relevant to note that even as the Kalai II project will affect 595 families (according to the EIA) in order to generate electricity, 565 families or 91.6% project affected families already have electricity supply. (EIA report page 9-13)

Submergence of the existing national highway: Impacts of alternative road not assessed The reservoir of Kalai II HEP will submerge 16 km of existing national highway. The border roads organization will construct two lane road at a higher elevation in place of this. The construction of this alternative road will imply land use, more social impacts, more blasting and other construction related activities, but these impacts have not been included in the EIA.

The alternative highway is planned to be constructed at elevation 910 m. However, since MWL is not given and also backwater effect, which will be higher than MWL at times of peak flood, it is not clear if the alternative elevation would be affected by back water effect.

Many Maps are not readable The project layout map at Figure-2.1 is not legible. The map is very small and except title none of the other details or legends are legible. The EIA must provide a detailed layout map for the Kalai II HEP. The same is case with Geological Plan of Reservoir Area map (Fig 6.1 and 6.2) which are two very important maps but they are not at all legible.

In most places the project consultant have used unclear maps. e.g. ‘Fig 7.7 – Water Sampling location map’ or ‘Fig 8.1 Terrestrial Ecological sampling location map’. An EIA with such illegible maps cannot be acceptable.

Impacts on Migratory Fish Construction of Kalai HEP II will have devastating impacts on fish in the river. The path of the migratory fish will be blocked and this has been accepted by the EIA as well – “The dam construction activities will also create a problem for migratory fish species (Tor tor and Tor putitora).” (Page 8-38). The two species of Mahseer, Tor tor and Tor putitora, locally known as Ngorika and Ngauch respectively and have been listed as ‘endangered’ in IUCN list. But it is surprising to see that EIA opining that “These migratory fish species may move into the small tributaries of LohitRiver.” It is no clear what is the basis of this statement by WAPCOS, it does not seem to show sufficient ecological literacy. The EIA prepared by WAPCOS also seem to ignore that several dams have been proposed in the tributaries as well. The EIA also does not say how well the area has been studied and what kind of biodiversity we may be losing.

Wrong claims about reservoir water quality The EIA says about reservoir water quality, “The proposed project is envisaged as a runoff the river scheme, with significant diurnal variations in reservoir water level. In such a scenario, significant re-aeration from natural atmosphere takes place, which maintains Dissolved Oxygen in the water body. Thus, in the proposed project, no significant reduction in D.O. level in reservoir water is anticipated.” This conclusion is clearly wrong. The EIA says about the reservoir: “The Gross and diurnal Storage of the Kalai-II reservoir are 318.8 M cum and 29.76 M cum with FRL at El 904.80 m and MDDL at El 900.00 m respectively”. This means that 93.35% of the reservoir is dead storage and only 6.65% of the reservoir capacity acts as live storage. Such a large quantity of dead storage will have huge impact on the water quality and the claim to the otherwise by the EIA is clearly wrong and misleading. Similarly the EIA claim of no Eutrophication risk due to “significant diurnal variations in reservoir water level” is clearly wrong.

No Options Assessment The EIA of Kalai II HEP does not do any options assessment. The EIA religiously focuses on the construction of 1200 MW project without mentioning the fact that successful sub-megawatt capacity hydropower projects (Less than 1 MW) are operational in Anjaw district (see Annexure II).

Conversion of community land into forest land can have negative impacts on the communities The EIA on page 10-25 states, “The total land requirement for the project, is 1100 ha. The entire land is considered as forest land. A part of the community land also includes forest land as well. For EMP purposes, the entire quantity of land has been considered as the forest land.” This can lead to severe impacts on the communities.

Here it is important note the implications of actions of similar nature on the Meyor community in the Kithibo area of Anjaw district, in the upstream of Kalai II HEP. A news published by Asian Human Rights Commission (see Annexure III) reports, “The Asian Human Rights Commission (AHRC) has received information from civil society groups regarding death threats, arbitrary detention and harassment of members of the Meyor community, a group of indigenous people in Arunachal Pradesh. They are being targeted for their activities on conservation of community land and natural resources.” The leaders of the community reported to have “protested the conversion of the community forest land of Walong and Kibitho area into reserved forest land because it was carried out without the free, prior and informed consent of the Meyor community.” It is important to note that this report also mentioned about impact of dams and other development activities on tribal ethnic communities. However, the EIA is silent on these aspects.

Cumulative impact migrant population in Lohit valley can be catastrophic The Kalai II project EIA states that the maximum number of people coming from outside the region for construction will be 3000 and the impacts are predicted to be only in the construction phase. Here it is important note that the number of outside workers provided by EIAs have proved to be gross under-estimates. But the EIA here does not mention anything about the cumulative impacts of migrant population for other projects along with Kalai II. In fact in a letter written to the Minister of Environment and Forests by the PFPAF, it was mentioned that the whole area of Lohit valley is inhabited by tribal population. The total tribal population as according to 2011 census is 16500. The cumulative number of migrant workers will clearly surpass this population figure, leading to severe impacts on the people of the area.

Lohit river in Anjaw district.  Source: EIA report
Lohit river in Anjaw district.
Source: EIA report

Disaster Management Plans do not mention about seismic risks Discussing the disaster management plan for the dam, the EIA study mentions only few issues and ignores the issue of earthquakes: “However, in the eventuality of dam failures in rare conditions, catastrophic condition of flooding may occur in the downstream area resulting in huge loss to human life and property. Floods resulting from the failure of constructed dams have also produced some of the most devastating disasters of the last two centuries. Major causes of failures identified by Costa are overtopping due to inadequate spillway capacity (34 percent), foundation defects (30 percent), and piping and seepage (28 percent).”

The EIA does not include the following important assessments:

a. Assessment of impacts of quarrying on the river bed and river banks The Kalai II project will require 72.6 lac cumec boulders for construction of the project and all of these will be extracted from the river bed and river banks.

Even though the EIA itself mentions how the removing of boulders and gravel from the river bed will affect spawning areas of fishes (page 10-29), but does not suggest for any detail impacts assessment. It limits itself by stating about adequate precautions during dredging period. But it is highly doubtful that any of those precautions will be followed when actual dredging will be done to extract lakh cumecs of construction material when there are no specific steps or mechanisms suggested. Without full assessment and management plan, the EIA cannot be considered adequate.  

b. Assessment of impacts of blasting for tunneling and other works in the pristine and fragile hill range – Blasting in the fragile hill ranges of Arunachal can have severe impacts, especially in increasing the probability of landslides. In Such circumstances, the EIA stating that no major impacts of blasting are envisaged at the ground level is wrong and puts a big question mark on the EIA.

c. Impact of the project on disaster potential of the area has not been assessed.

d. Impacts of peaking power operation on hydrological regime, biodiversity, and life & livelihoods of people

e. Impact of flushing out of silt from the reservoir

f. Impacts of climate change on the project and project’s impacts on local climate

g. There is no assessment of the value of the river that will be destroyed by submergence in the upstream and drying up and changed hydrology in the downstream.

h. The EIA has not properly assessed the downstream impacts of the project. It may be recalled that the ongoing massive agitation in Assam against such impacts of the under construction 2000 MW Lower Subansiri HEP, that has led to stoppage of work there since Dec 2011 is focused on downstream impacts and this project will face the same fate if this is not attended to.

i. No public consultations in Assam Linked to the above issue is the need for public consultations in downstream Assam about this and all other Lohit basin projects, without which there will be no question of public acceptability of the project and the project may face the same fate as that of Lower Subansiri HEP.

Doubtful, contradictory and sweeping statements in EIA The EIA at several places have stated made such statements:

Page 10 -23, para 4: “The construction of the dam would form the reservoir which will submerge about 640 ha of area in upstream. The area witnessed jhum/shift cultivation practiced by local inhabitants. Submergence of the area would not impact much on the prevailing land use pattern.”

This is clearly wrong, since jhum cultivation is one of the key livelihood supporting activity in these areas and if such land is submerged, it will have major impacts on the land use pattern.

Page 10 – 30, para 3: “As a result, barring for monsoon season, (May to September), the river Lohit will have dry periods for few hours for generation of peaking power.”

The idea of ‘few hours’ a complete misnomer and misleading, it will happen daily for 15-20 hours. In the analysis of Lohit basin study SANDRP had found that for Kalai II, “In lean season river water will be stored for a period of 15-20 hours. As a result, downstream stretch of river from the dam site will remain dry for that period. This will be followed by a continuous flow of 1112.27 cumecs (rated discharge) for a period of 4 to 9 hours.” (Lohit Basin Study by WAPCOS: A mockery of e-flows and cumulative impacts – https://sandrp.in/rivers/Lohit_Basin_Study_by_WAPCOS_A_mockery_of_e-flows_and_cumulative_impacts.pdf)

Parag Jyoti Saikia (meandering1800@gmail.com)

with inputs from Himanshu Thakkar  

——————————————————————————-

Annexure I

Villagers block road demanding scrapping of Kalai II dam

Link : http://www.arunachaltimes.in/wordpress/2012/06/06/villagers-block-road-demanding-scrapping-of-kalai-ii-dam/

Raju Mimi

HAWAI, Jun 05: About 500 villagers of Hawai circle on Monday staged a dawn-to-dusk road blockade at Walong-Hawai road demanding scrapping of the 1200 MW Kalai II dam proposed on LohitRiver.

The villagers protested under the banner of Peoples Forum for Project Affected Families (PFPAF). Road communication at Hawai was totally disrupted for the whole day affecting even the movement of military vehicles.

Talking over telephone from Hawai, PFPAF Chairperson Behenso Pul said: We had earlier submitted memorandum demanding scrapping of Kalai II dam to Union Ministry of Forest and Environment, chief minister, local representatives putting our grievances. But no one is listening to us. So we decided to launch our democratic movement.

The villagers staging protest demanded for permanent halt of property survey, and other survey and investigation being carried out for the hydro electric project. A memorandum was submitted to deputy commissioner, Hawai placing all grievances and the demands.

We are highly encouraged by the massive participation of villagers in such short notice. It is a great moral boost for people working against dam, said Pul. But there was no participation from panchayat leaders, students union and other civil society organization.

The Kalai II Hydro Electric Project is to be developed by one of the major Reliance Power subsidiary, Kalai Power Private Limited (KPPL). It was incorporated on September 26, 2007. The project site is in LohitRiver in Kumblung and the submergence route extends upto 23 km upstream.

The project involves construction of 161 meter high concrete dam. An underground power house will be constructed to house 8 units of 150 MW turbines. The total project cost is estimated at Rs. 69,551 million and is likely to be completed in 7 years time.

The Kalai II project will lead to submergence of entire Hawai circle and all the major villages. Around 1500 people are being directly affected by the dam, said Pul. Since last week, we carried out grassroots campaign on dams. We haven’t met one single person who is in favour of dam. Everyone one is scared and against it. In Anjaw district alone, at least 6 large dams are proposed within 150 km of river route out of 13 projects in the entire Lohit basin. Water and Power Consultancy Services (WAPCOS) had earlier conducted a cumulative impact assessment of various hydropower projects in the entire Lohit river basin, as per the directives of MoEF.

WAPCOS made a farce report, completing within 2-3 weeks. The study is very poor and shoddy, said Pul.

According to PFPAF, they are, however, not opposed to all dams in Anjaw district. They view that projects along the tributaries of Lohit river can be harnessed, instead of building large dams along the main river alone. Citing a report in a national news magazine, Pul said the tributaries of Lohit alone had capacity to produce 8000 MW.

Out of the 7 circles in Anjaw district, 5 are situated along the main Lohit river. Even Hawai headquarter is in the bank of Lohit river. So, if dams are built along the main river, majority of the 18000 Mishmi population will be affected, said Pul.

In April 13 meeting with Chief Minister Nabam Tuki at Tezu, the PFPAF had suggested the government to consider harnessing power in the tributaries of Lohit river, not in the main river, where majority of population live. It is learnt that chief minster had made assurance of stopping all dams wherever not required.

If small dams are built in the tributaries, which are in the interior places, people there can benefit in the form of roads and other developments,Pul said.

———————————————————

Annexure II

Anjaw shines in hydro power sector

Link : http://articles.timesofindia.indiatimes.com/2012-01-02/guwahati/30580969_1_hydropower-projects-hydel-project-power-supply

TNN Jan 2, 2012, 05.50AM IST

ITANAGAR: The remote Anjaw district of Arunachal Pradesh is marching ahead to notch a record in the hydropower sector and is being hailed as the future powerhouse of the country with a 58,000 MW hydropower potential.

Kaho, a village in the district located near Kibithoo along the tri-junction of the China-Myanmar-India border, had created a record in 2007 by becoming the first village in the state to have round-the-clock power supply besides supplying power to the Army personnel guarding the frontier.

This feat was achieved thanks to the determination of the lone elected representative of the district, Kalikho Pul, and the equally committed deputy commissioner, Prashant S Lokhande. The two officials were instrumental in commissioning a micro hydel project in the last border village, a 24-hour trek away from last pitch road, for which all the machines and material had to be transported manually.

The duo’s efforts in turning the odds to their advantage made Anjaw the first of the 17 districts in the state to commission many of the ongoing projects.

Pul, who toured the district and inspected all the project sites recently, said the 2X100 KW Yapak, 2X50 KW Khrowtipani, 2X250 KW Matinala and 2X250 KW Teepani projects were commissioned recently and made the border district self-sufficient in power.

At the moment, Hawai, Hayuliang, Goiliang, Manchal, Walong, Kibithoo and Metengliang administrative centres and adjoining villages are getting 24-hour uninterrupted power supply, Pul said, adding that various development activities would begin now with availability of power, thereby boosting the local economy as well.

Located along the Sino-India border, the district is spread across an area of 9,936 sq km and crisscrossed by numerous perennial rivers, including Lohit, Dav, Dalai, Lati, Kulong, Syang, Helei, Yapak and Kathang, has total hydropower potential of above 7,000 MW.

The projects – 2X50 KW Hatipani at Goiliang, 2X30 KW Ashapani, 2X100 KW Kachopani, 2X30 KW Maipani and 2X200 MW Langpani at Gamliang – are likely to be commissioned within a month or two, Pul informed.

He added despite the locational and other disadvantages, the projects could register speedy growth because of proper utilization of funds and strict monitoring.

The hydropower projects were taken up with the vision to benefit the locals as well as the state in general, he said, adding the 16 MW Haleipani project, which is at an advanced stage, is likely to be commissioned within 2012. “It will cater to the needs of Lohit, Dibang and Changlang districts besides meeting the requirements of Anjaw,” he added.

However, according to official sources, no steps have been initiated so far for erecting transmission lines for evacuation of excess power to be generated by the Haleipan project. Once the transmission lines are commissioned the state would be almost self-sufficient and would not need to purchase power at high prices from outside.

Pul added as the Haleipani project is on the verge of completion, the state government, particularly the hydropower department, should take up the transmission line project proposed in Anjaw. The project is pending with the department for the last many years. Without the transmission lines, any quantity of power generated would be futile as it cannot be utilized for any purpose, he said.

Kaho, a village in the district located near Kibithoo along the tri-junction of the China-Myanmar-India border, had created a record in 2007 by becoming the first village in the state to have round-the-clock power supply

——————————————————————–

Annexure III

INDIA: Violent Attack, Arbitrary Detention, Death Threats to activists of Meyor Community, Arunachal Pradesh

Link: http://www.humanrights.asia/news/urgent-appeals/AHRC-UAC-152-2013

ASIAN HUMAN RIGHTS COMMISSION – URGENT APPEALS PROGRAMME: Urgent Appeal Case: AHRC-UAC-152-2013

9 December 2013

—————————————————————————————

INDIA: Violent Attack, Arbitrary Detention, Death Threats to activists of Meyor Community, Arunachal Pradesh

ISSUES: Arbitrary detention, freedom of speech and expression, indigenous people’s rights, protection of environment, land rights, human rights defenders

—————————————————————————————

Dear friends,

The Asian Human Rights Commission (AHRC) has received information from civil society groups regarding death threats, arbitrary detention and harassment of members of the Meyor community, a group of indigenous people in Arunachal Pradesh. They are being targeted for their activities on conservation of community land and natural resources. The Meyor community with about 450 members is classified as one of the Scheduled Tribes under the Indian Constitution and is mostly confined to the Anjaw district of the state. They have been criticized for opposing government activities that includes conversion of community land to reserved forest land and corruption in the Public Distribution System (PDS).

CASE NARRATIVE Several representatives of the community assumed a leadership role. They are, namely:

Mr. Chung Meyor, 33, Dhanbari village

Mr.Chaping Meyor, 55, Gaon Bura (village chief), Khroati village

Mr. Unchen Meyor, 45, Barakhundun village

Mr. Chethel Meyor, 25, Dhanbari village

Mr. Tharpa Meyor, 26, Musai village

Mr. Tenzing Dorjee Meyor, 30, Sotakhundun village

Mr. Fendey Meyor, 30, Musai village of Arunachal Pradesh

These men protested the conversion of the community forest land of Walong and Kibitho area into reserved forest land because it was carried out without the free, prior and informed consent of the Meyor community.

The conversion of community land into forest land was initiated, allegedly, by Mr. Kalikho Pul, a member of the Arunachal Pradesh Legislative Assembly. He allegedly collected signatures from the Meyor community under the pretext of development works in the area. Conversion of this forest area was completed in 1995-1996 with a proposal of afforestation. Through an application, under the Right to Information Act, 2005 filed by Mr Dimso Manyu of the Meyor community, the people came to know of this development only on 14 March 2012.

The villages of the Meyor community are within a 36 square kilometer perimeter and their livelihood is dependent on natural resources. Over a period of time they faced limited access to the land resources due to the conversion of community land into ‘forest land’. Once they came to know of the conversion, the community vehemently opposed it. Due to their opposition, it is alleged that the police and unknown trouble-makers carried out frequent detentions, arrests, tortures and intimidations of community leaders and representatives of the Meyor tribe.

On 26 April 2013, armed reprobates arrived in a white Scorpio Jeep, threatened and attempted to torture Mr. Chung Meyor near Naraliang village on Tezu-Hayuliang Road. On the same day, Mr. Chung lodged a complaint about the incident at the Khupa police station. Police have not taken any action so far.

On 1 June 2013, Mr. Unchen Meyor filed a complaint at the Khupa Police Station. He cited mismanagement, corruption and illegal activities committed at a Fair Price Shop set up under the government’s Public Distribution System. Incidentally, on 12 November 2013 some local youths discovered that Mr. Agam Rai was selling PDS items illegally to people who were not subscribed under the PDS system. In connection to this discovery, a counter- police complaint was lodged by Mr.Kayawlum Tawsik, Chairperson, Zilla Parishad (local government), Anjaw Disttrict, against Mr. Unchen Meyor, Mr. Chethel Meyor and Mr. Tharpa Meyor.

On the night of 13 November 2013, Mr. Unchen and his family were brutally assaulted by a group of criminals at his residence in Barakhundun village. Mr. Unchen is still in critical condition due to injuries to his head, nose and chest. His daughter made a complaint about the attack on 15 November to the Khupa police station. However, till now, the police have not taken any action.

A second time, on 28 November 2013, Mr. Fendey Meyor, member of Gram Panchayat (local government) was arrested by the police from his village, Musai. They demanded the immediate surrender of Mr. Unchen, Mr. Chethen, Mr.Tenjing at the Khupa police. Mr. Fendey was released on 3 December on bail, with fabricated charges of vandalising still pending. Mr. Unchen is in hospital (at Aditya Diagnostic, Diburgar) struggling for his life. Mr. Chethen and Mr. Tenjing are in hiding, fearing for their lives and personal security. Similarly other community activists like Mr. Chung Meyor, Mr. Chaping Meyor and Mr. Tharpa Meyor are equally exposed to threats to their lives.

ADDITIONAL INFORMATION Arunachal Pradesh, bordering on China, is one of the most thinly populated states in India. It has 101 recognized indigenous tribal groups and about 50 languages. There are several rivers with the potential for generating hydro-electric power. The government has planned to construct some 168 mega-dams in the state, a move opposed by the indigenous people living there. There is a heavily militarized presence due to the international border. Draconian measures under the Armed Forces Special Powers Act, 1958 (AFSPA) is applicable in two districts of Arunachal Pradesh, namely Tirap and Changlang, and a 20 kilometer area bordering Assam.

SUGGESTED ACTION:

1.            Urge the Government Authorities of India and the State Government of Arunachal Pradesh to guarantee the physical and psychological security of the members of the Meyor Community and its leaders.

2.            Urge the authorities to protect the indigenous people’s right to land and resources.

3.            Urge the authorities to protect the environment and not to grant deforestation rights.

The AHRC is writing a separate letter to the UN Special Rapporteur on the Rights of Indigenous People and the UN Special Rapporteur on Protection of Human Rights Defenders for immediate intervention in this matter.

——-ooo——-