Dams · Krishna River · Maharashtra · Marathwada · Ministry of Environment and Forests

Krishna Marathwada Scheme receives Environmental Clearance WITHOUT Water Availability!

Why is the Maharashtra Govt and the MoEF misleading people of Marathwada?

Press Release 29.06.15

On the 24th June 2015, the Union Ministry for Forests, Environment and Climate Change (MoEF for short) granted Environmental Clearance[1] to Krishna Marathwada Lift Irrigation Scheme for diverting 23.66 TMC (Thousand Million Cubic Feet) water from Krishna 1 Sub basin to Krishna 3 Sub basin of Krishna River Basin. The media has reported the development as a “Respite for Marathwada”.

However, as SANDRP had written to the MoEF several times[2], this Environment clearance is based on non-existent water availability and a misleading EIA[3] by Science and Technology Park, University of Pune. Continue reading “Krishna Marathwada Scheme receives Environmental Clearance WITHOUT Water Availability!”

Maharashtra

Krishna Marathwada Project: A costly pipe dream?

Above: A board at the dam site proclaims: “Beware, dam work ahead”. The warning pretty much sums up the situation of Krishna Marathwada Project Photo: Parineeta Dandekar

It was a blazing hot afternoon, made hotter by the subconscious association of Marathwada with all things dry, parched and drought-stricken. I was standing on the half completed dam wall of the Khuntephal Storage Tank in Beed, along with Macchindra Thorave and his colleagues. I’ve seen many dams and many dam walls, but it was impossible to believe this was a dam wall, supposed to impound 5.68 TMC of water (TMC=Thousand Million Cubic Feet. 1 TMC=28.317 billion liters). Primarily because there was no water in sight on either sides of the dam! There was no river in sight either! It actually looked like an under-construction road connecting two hills.

But as I realized later, being a part of the Krishna Marathwada Lift Irrigation Scheme and Krishna Bhima Stabilisation Project, issues like water were inconsequential.  This was Dam for Dam’s sake.

Half completed wall of the Khuntephal/Ashti Storage Tank, part of the Krishna Marathwada Project. Photo: Parineeta Dandekar
Half completed wall of the Khuntephal/Ashti Storage Tank, part of the Krishna Marathwada Project. Photo: Parineeta Dandekar

Continue reading “Krishna Marathwada Project: A costly pipe dream?”