Why is the Maharashtra Govt and the MoEF misleading people of Marathwada?
Press Release 29.06.15
On the 24th June 2015, the Union Ministry for Forests, Environment and Climate Change (MoEF for short) granted Environmental Clearance[1] to Krishna Marathwada Lift Irrigation Scheme for diverting 23.66 TMC (Thousand Million Cubic Feet) water from Krishna 1 Sub basin to Krishna 3 Sub basin of Krishna River Basin. The media has reported the development as a “Respite for Marathwada”.
However, as SANDRP had written to the MoEF several times[2], this Environment clearance is based on non-existent water availability and a misleading EIA[3] by Science and Technology Park, University of Pune.
The EC letter states that “project involves lifting 21 TMC water from Ujjani Reservoir”. This is nearly 40% of Ujani’s live storage capacity (54 TMC) and there is no such surplus water available in Ujani for any such diversion as all of its water is already over-allocated.
The Krishna Marathwada Project is a part of bigger Krishna Bhima Stabilisation scheme planning to transfer 63 TMC water to Ujani from far off places like Kolhapur. Only after this transfer is there a chance of diverting any water for Krishna Marathwada scheme.
However, the Krishna Water Disputes Award Tribunal (KWDT), in its November 2013 Verdict has categorically rejected any water transfer for the Krishna Bhima Stabilisation Scheme.
The Government of Maharashtra is well-aware of all these happenings. The KWDT Cell of the Water Resource Department (WRD) of the Government of Maharashtra itself has stated that diversion for Krishna Bhima Stabilisation scheme has been rejected and that there is no availability for 21 TMC water from Ujani for Krishna Marathwada Project. The Secretary of Water Resources in a letter in 2009 had stated that Krishna Marathwada Scheme cannot be designed at 21 TMC water availability from Ujani, but has to be scaled down at 7 TMC only because of Tribunal considerations. Amazingly, there is no clarity about the source fo this 7 TMC water either!
Despite all this, the WRD of Government of Maharashtra went ahead and started work on the KMLIS for 23.66 TMC availability long before even applying for environment clearance and in violation of Environmental Protection Act & EIA notification of Sept 2006 and disrespecting letters[4] from Governor’s office sent in 2009.
The current project consists of 3 Lift Irrigation Schemes (LIS) and work on all 3 has been started even before getting the Environment Clearance. But very shockingly, the EIA of the project done by Science and Technology Park, University of Pune[5] does not even mention how 23.66 TMC water will be secured, nor does it mention a word about 1068 hectares of land that is needed for LIS III, which is in Beed. The entire Section on Hydrology of the EIA (completed in August 2014) does not mention a word about LIS III, for which work started in 2010!
The EIA from Science and Technology Park is misleading.
The EC letter also does not mention a word about LIS III in Ashti, Khuntephal (Beed), although it is an integral part of the project and although project affected people had written several times to the Ministry about this!
What is more, the project has been singled out by SIT Committee Report under the Chairperson ship of Dr. Madhav Chitale as a “Flawed Project” and the SIT has recommended: “Detailed further investigation of this project by an independent committee and also action against officials”.
The project does not have a water availability certificate for 23.66 TMC water. Even for a scaled down version of 7 TMC, There is no clarity where the water will come from.
In the absence of any clarity about water, the earlier government already acquired lands through private negotiations, issued tenders and spent over Rs 400 Crores on this project! The Krishna Marathwada project is littered with irregularities, absence of water availability, bad EIA and violations.
News Reports mention that WRD Minister of Maharashtra Shri. Girish Mahajan and Union Minister for Environment and Forests Prakash Javadekar followed up clearance for this project.[6]
The Chief Minister of Maharashtra Shri. Devendra Fadnavis had promised that focus will be shifted from non-performing large Dams and Lift Irrigation Projects to small-scale projects and schemes like Jalyukta Shivar. It is shocking that his government is pushing a project that is mired in irregularities, is based on a nonexistent Water availability and whose EIA is of an extremely poor quality. It is reported that in a meeting, he stated that he will ensure Clearance for this project. In the same meeting, the fact came to light that water availability for the project is only on paper![7] How can the government support such shoddy approach of the Water Resource Department?
Such unviable projects benefiting only contractors have been the reason why Maharashtra, despite spending over Rs 70,000 Cores, could not register any increase in its irrigated area. The New government had promised to go to the roots of the Dam Scam. Why is it forgetting it promises in case of Krishna Marathwada Lift Irrigation Scheme?
The project is also misleading people of Marathwada[8], showing them dreams which cannot be materialized as there is no such water available for diversion. The project stands challenged in the High Court.
We urgently request the Government to take back all permissions given to Krishna Marathwada Scheme, undertake enquiry into the project not only from ACB, but also from technical experts on issues like water availability, flawed EIA, violations of EPA 1986 and EIA notification (2006), KWDT permissions, viability of transferring water from rivers like Warana and Panchaganga to Osmanabad and Beed.
The Union Ministry of Environment and Forests needs to take back the flawed EC urgently and take action against the EIA Agency. It is clear that the EC has been granted based on misleading EIA and information.
Parineeta Dandekar
parineeta.dandekar@gmail.com, SANDRP (https://sandrp.wordpress.com/)
9860030742
END NOTES:
[1] http://environmentclearance.nic.in/writereaddata/Form-1A/EC/06252015158-2008lttr.PDF
[2] For minutes of the EAC where this project was discussed, see: http://environmentclearance.nic.in/writereaddata/Form-1A/Minutes/0_0_12111812261217170thEACMinutes.pdf, http://environmentclearance.nic.in/writereaddata/Form-1A/Minutes/0_0_8112512401217176thEACMinutes.pdf
[3] http://environmentclearance.nic.in/writereaddata/EIA/111125125212101Executivesummaryrevised.pdf
[4] After SANDRP pointed this out to EAC, the Govt of Maharashtra accepted they had violated the laws, see for details: https://sandrp.wordpress.com/2014/08/06/press-release-06-08-2014-maharashtra-and-karnataka-governments-accept-violating-environment-protection-act-and-eia-notification-for-specific-irrigation-projects-on-affidavit-promise-not-to-repeat/
[5] http://www.scitechpark.org.in/
[6] http://www.dainikekmat.com/Osmanabad-2003-कृष्णा%20मराठवाडा%20स्थिरीकरण%20योजना%20पूर्ण%20करणार-1.html#.VZECDKRdz5c, http://www.mahanews.gov.in/Home/MantralayNewsDetails.aspx?str=HUpFdNIHRqY=, http://www.lokmat.com/storypage.php?catid=13&newsid=5128110
[7] http://www.lokmat.com/storypage.php?catid=13&newsid=5128110
[8] For earlier SANDRP analysis of this project based on site visit, see: https://sandrp.wordpress.com/2015/04/01/krishna-marathwada-project-a-costly-pipe-dream/
THANK YOU PAREINEETA.
Its a very nice analytical artical about KMLIS. I want to add some more…….
1. Krushna Bhima satabili proj approved administrativly feb 2004 for Rs. 49000 cr. Consisting diversion of surplus flowing water from 5 rivers, KUMBHI KASARI KRUSHNA NEERA to Ujani Dam.
2. On the basis of KBSP ,KMLIS OF 19 TMC is approved administrativly in Aug 2007 for Rs. 2385 cr consisting LIS I and LIS II for Usmanabad Dist only.
3. Mla of Ahti Suresh Dhas and then minister of Wrd Ajit Pawar pushed third LIS for Ashti Tal without any approval and floated Tender on 12 Feb 2009(Financial year 2008-2009).
3. Three Grampanchyat opposed this tender of constructing KHUNTEPHAL STORAGE TANK of 6 TMC.
4. ED GMIDC gave stay to this Tender notice on the objection of Grampanchyat on 25 March 2009.
4. On 7 july GOM has cleared that ther is only 7 TMC water is available instead of 25 TMC for KMLIS.
5. up to 7 july KMLIS was only for 19 TMC. there was no involvement of III LIS for ASHTI TALUKA.
6. On the same day 7july ED GMIDC vacated stay on Tender notice.
7. Chief Engineer Aurangabad WRD HAS GIVEN TECHNICAL SANCTION on 10 july 2009 for Estimate, on which Tender was floated in Feb
2009 for ASHTI LIS III ASSUMING part of KMLIS (FOR 19TMC ONLY).
8. Contractor RAJ INFRASTRUCTER PVT LTD (Director Jagdish kadam and Ram Nimbalkar) issued Work order of single page costing Rs. 210.06 cr. On 25 Aug 2009.
9. Further GOM has given Revised Administrative Approvel for KMLIS INCLUDING Third Ashti LIS on 27 August 2009.
10. It means GOM has approved RAA to include ASHTI LIS III which ileagle.
Above all points 1-10 are totaly violation of PUBLIC WORKS MANUL and GOM’s RULES AND VARIOU G.R’s.