Assam · Ministry of Water Resources

Present Tensed, Future Expensive: Large Irrigation Projects in Northeast India

The actual construction costs of large dams are too high to yield a positive return” this was the unequivocal conclusion of a recent study done by a group of experts from Oxford University on dams around the world[1]. Similar conclusions can be reached from a recent analysis done by SANDRP on five large irrigation dam projects from northeastern region of India, where project costs have increased as high as 35 times from its original costs and projects are under construction for 35 years but yet not completed. The Oxford study which has assessed 245 large dams built between 1934 and 2007 in 65 different countries in five continents, including 97 hydropower projects, 59 irrigation projects and 89 multipurpose projects with hydropower component, had identified enormous cost and time overrun as a major problem with large dam projects.

SANDRP had recently done an analysis (https://sandrp.wordpress.com/2014/03/19/lack-of-transparency-and-accountability-remains-the-norm-of-functioning-for-mowrs-advisory-committee/) of the decisions of the Advisory Committee in the Union Ministry of Water Resources for consideration of techno-economic viability of Irrigation, Flood Control and Multi Purpose Project Proposals (TAC in short) for North East India. This analysis covered decisions taken by TAC from 95th meeting of January 2009 to 122nd meeting of December 2013. Within these five years, TAC has given clearance to 38 projects in North East India out of which major number of the projects i.e. 26 are flood and erosion control projects. Rest of the 12 projects includes 6 irrigation projects, 3 barrage projects and 3 multipurpose projects. All these 12 projects involve irrigation as a major component.

Among the 12 projects, five projects draw specially attention because of the humongous cost escalation and time overrun in the construction of these projects. But this focus on five projects out of twelve should not be taken as an ‘All is well’ certificate for the remaining seven projects. There are significant issues with those projects as well but from the perspective of time and cost overrun, these five projects present a very critical picture.[2] Besides, all the five projects discussed here are under construction projects. TAC had paid little attention to these critical issues and therefore very little information is available in the TAC meeting minutes regarding the five projects discussed here. In this analysis, along with details cost and time escalation other important issues related with the projects have been brought together. Three out of these five projects are located in Manipur where as two are located in Assam.

Starting with the three projects from Manipur, the table below summarizes the cost incurred in these three projects. All these projects are age old projects and how much benefits will be acquired from them once there construction is complete, still remains uncertain.

Name of the Project Year of Starting Original cost Considered in 2009 Considered in 2012
Khuga Multipurpose Project (Major- Revised) 1980 15 381.28 433.91
Dolaithabi Barrage Project (Medium – Revised) 1992 18.86 251.52 360.05
Thoubal Multipurpose Project (Revised) 1980 47.25 982 1387.85
Total  (all costs in Rs Crores)   81.11 1614.8 2181.81

Khuga multipurpose project was first considered in the year 1980 when the cost of the project was Rs 15 crores. 1. The Khuga multipurpose project is located near Malta village in Churachandpur district of Manipur, at least 10 km from the district headquarter. The project was to irrigate 15,000 ha of land, provide 10 million galons for drinking water and have installed capacity of 7.5 MW hydropower. The Khuga (considered in the 110th and 115th meeting of TAC) project witnessed cost escalations of 25.42 & 28.92 times respectively from its original cost.

Map of Khuga multipurpose project; Source: India WRIS Wiki
Map of Khuga multipurpose project; Source: India WRIS Wiki

In the 115th meeting of TAC held in July 2012, the completion deadline of Khuga multipurpose project was stated as March 2013 which implies that it would take 33 years only to complete the project. The minutes of the 115th meeting stated “The project authorities indicated that the increase in cost was due to frequent blockades and law and order problem in the project area, as a result Project authority were unable to obtain construction materials like cement, steel etc, in time, which in turn slowed down the progress of the project significantly. Regarding revised target date of completion, the Project authorities informed that land acquisition had been completed and the project would be completed by March 2013.

We came across some of very crucial issues about these projects discussed in detail in the Manipur based website Manipur online, Hueiyen Lanpao[3]. These issues were very much related with the viability of the Khuga project but none of these issues found any mention in the TAC meeting discussions. The project proponent seemed to have completely ignored these issues, some of these are given below.

  • The Khuga project is reported to be inaugurated by Congress chairperson Sonia Gandhi in November 2010.
  • This project was visualized to solve the irrigation, drinking water and electricity problem of Churachandpur district in particular and Manipur in general since agriculture is the main livelihood option of the region.
  • But, in terms irrigation it seemed unrealistic to many since Churachandpur is a hill district where jhum cultivation is practiced. In fact an inspection of the main right canal of the Khuga multi-purpose project showed the very sorry state of the canal.[4] The inspection led by an ex-Minister N Mangi came to the conclusion that the canal had never provided any irrigation to nearby paddy fields.
  • An audit report of Khuga multipurpose project of March 1999 on the performance review of the dam had stated “Since 1984, the IFCD, Manipur, carried out construction work on 25.37 km of canal over an area of 40.27 hectares of forest land in Dampi reserve forest without obtaining the required clearance for diversion of forest land. Barring the unaccounted environmental destruction (that still continues) the overall concept of the multipurpose Khuga Dam project in itself was unpractical and paradoxical.”[5]
  • Regarding drinking water, people in the area when faced with drinking water scarcity, were not sure whether the water reserved in Khuga dam would qualify as good enough for drinking. People of several villages living in the vicinity of the dam had reported that stagnant water actually smells.[6]

    Khuga Multipurpose project in Manipur. Source: http://manipuronline.com/
    Khuga Multipurpose project in Manipur. Source: http://manipuronline.com/
  • The electricity generation component had been scrapped totally even after the power house was reported to be completed by almost 80%. It was said that there were flaws in the design of the Khuga multipurpose project right from the beginning and the electricity generation was not a viable option. It was learnt that the power component was planned and designed without studying its operational feasibility and the power component can be operated for only about 3 or 4 months in a year when there is excess water.
  • There was also a report that a Joint Action Committee on Khuga Dam visited the national capital and submitted a petition to Deputy Chairman of Planning Commission demanding an expert team to investigate the execution of the project.[7] The Joint Action Committee also demanded that the 1.5 MW electricity for the people of Churachandpur district and compensation and rehabilitation money to the affected the villages should be cleared.  None of the above, even the petition submitted to the planning commission was not mentioned in the minutes of the TAC meeting.

Dolaithabi Barrage Project was first approved by the Planning Commission of India in 1992 with a cost of Rs 18.86 crores to be constructed in Imphal East district of Manipur.[8] 22 years have passed since then, but the project is yet to be completed.  The cost of the project has increased 19 times from its original cost when it was considered in the 115th TAC meeting held on 24th July 2012. In that meeting price escalation, change in design on the basis of model studies, detail examination of the project proposal by the CWC field unit had been cited as the reasons for increase in costs of the project. But there was no question on why the design of the project had to be changed 20 years after the project had started. TAC meeting minutes did not mention any completion year for the project, but state Chief Minister Okram Ibobi Singh in an inspection tour to the project site in October 2012, had announced that this project would be over by March 2014.[9] This clearly sounds unrealistic. 

Location map of Dolaithabi and Thoubal project. Source: India WRIS Wiki
Location map of Dolaithabi and Thoubal project. Source: India WRIS Wiki

Thoubal multipurpose project was first considered by Planning Commission in the year 1980 and the original cost of the project was Rs 47.25 crores. The project is still far from completion and witnessed huge cost escalations. From 2009 to 2013, the Thoubal multipurpose project was considered in two meetings. In the 101st TAC meeting, when this project was considered the cost escalation was already 20.78 times the original cost. As per minutes of the 115th TAC meeting, the cost by then was 29.37 times higher from the original cost. The Thoubal project was also considered in 123rd meeting held on January 30th, 2014 where the projected cost was Rs 1694.27 crores. This is a 35.86 times increase in costs from its original cost. It is interesting to see that in the minutes of the 115th meeting the reasons provided to justify the delay in the construction of Thoubal Multipurpose project are exactly same as those given for Khuga multipurpose project.

Dhansiri irrigation project in Darang district of Assam is another glaring example of mind blowing time and cost overrun. This project was discussed in the 119th meeting on 29th August 2013 for consideration of cost of Rs 567.05 crores. This project started in 1975 and the original cost of the project was Rs 15.83 crores as per the information available in Assam State Irrigation Department website.[10] The same website states that project is supposed to be completed in 2010, 35 years from the time it started.  But in the 119th TAC meeting March 2015 was stated as the new completion target. This implies that the cost of the project has increased by 35.82 times over a period of 40 years but even after that the advisory committee accepts proposal without much scrutiny or enquiry. There was no detailed assessment of the reasons for time and cost overruns (there is no question of delay due to clearances or agitations here) or on whether this project which will take 40 years  just to complete will be viable or not.

Dhansiri irrigation project  command area: Source: India WRIS Wiki
Dhansiri irrigation project command area: Source: India WRIS Wiki

The project proponent stated that due land acquisition and law and order problem the project has not been completed and the TAC seemed to be contended with this. But the minutes of the 119th meeting also showed that major components of the project were in advanced stages of construction with 93% of barrage work, 99% of the canal works and about 83% of works in the distribution system completed. There was no detailed assessment of any of these aspects.

Champamati irrigation project in Chirang district of Bodoland Territorial Area District (BTAD), Assam presents a very unique case. This project started in 1980 with an original cost of 15.32 crores. It was discussed in 103rd meeting of TAC held on 11th March 2010 with a revised cost of 309.22 crores which is clearly a 20 times increase from the original cost. This was 30 years after the project had started and referring to the observation of the Chairman, TAC minutes stated “both physical and financial progress of the work was rather going on a slow pace. He enquired to know whether there was any land acquisition problem persisting or not.”

Map of Champamati irrigation project command area. Source: India WRIS Wiki
Map of Champamati irrigation project command area. Source: India WRIS Wiki

Replying to this, the project authorities had stated that “the delay was mainly due to lack of fund and land acquisition problem. However, the main canals had been completed by about 80% while distribution system completed upto 30% which is likely to be completed in another two years.” But in the list of major/medium schemes in the website of Irrigation department, Govt. of Assam the proposed year of completion of this project has been mentioned as 2009.

But in midst of these tall claims of project completion, what is the present status of this irrigation project cannot be confirmed. There is little information available on this project in the internet and from those it can be clearly said that the project was not completed till the mid of 2013. In a news report titled “Centre worried over Cost overruns in old irrigation projects in NE” published in The Sentinal on 26th August 2013 the delay in construction of Champamati irrigation project was also highlighted. On other hand an earlier report “Irrigation scheme damned by delays” published in the Telegraph on 21st August 2006, had indicated that this project had substantial amount of construction left to be done “Till now, only the sluice gate (headwork) of the Champamati irrigation project has been completed, sources said. Of the 37 regulators, only eight are complete, of the 120 canal falls only 20 are complete, while 72 cross-drainage systems have been completed out of a total of 270. Of the 197 bridges, just 50 are finished. The earthwork of the main canal and the branch canal are also incomplete, with only 97.67 km out of 145.95 km finished.

How much benefit these projects will do to the people of India’s Northeast is the question which may appears in the minds of many after going through this analysis. After such humongous in costs and time overrun, the benefits expected to be derived from these projects, would hardly justify the costs incurred. Similar concerns were raised by the representative of the Planning Commission regarding Dhansiri Irrigation project “the benefit cost ratio of the project was 1.2 and any further escalation in cost would result in the project becoming techno-economic unviable.

Whether these projects can actually deliver what had been promised remains uncertain at best. From the history of Khuga project, it is very clear that the promises are never fulfilled and the benefits never reached the people. In fact the Khuga project is also an example of how the expected benefits of the project never become a reality even after completion of construction. The benefits from irrigation largely remained on paper.

This is the case with the several other irrigation projects in northeast. The case of Loktak Lift Irrigation project in Manipur can be cited here about which the minutes of the 122nd TAC meeting (20th December 2013) stated “Loktak lift irrigation project was commissioned in 1986 with an original command area of 24000 ha and 40000 ha as annual irrigation. Due to scarcity of funds from State Government the normal repair and maintenance could not be taken up and as of now the annual irrigation has reduced to 1800 ha.” This is possibly indicative of how much irrigation benefits have actually been accrued from irrigation projects.

Functioning of TAC Barring the cost and time overrun of these projects, the functioning of TAC also needs to be looked into. The Advisory Committee of MoWR very much works like a rubber stamping committee, clearing everything that comes to it. A reading of the minutes of its meetings reveals that there are hardly any critical questions asked on merits of the projects and for the massive delay and cost escalations that most of the considered projects suffer from. Nor is there any discussion about the performance of the projects. Considering the importance of TAC in India, we believe the committee needs to be more serious in performing its duties. It needs to question the merits and need of a project before clearing and need to do performance evaluation. It should no way become a clearing house for projects. Effective steps need to be taken to ensure that the functioning of this committee becomes more transparent, participatory and accountable. SANDRP has written letters to the concerned authorities in this regard, but we are yet to see an effective change.

Parag Jyoti Saikia (with inputs from Himanshu Thakkar) (meandering1800@gmail.com)

~~~~~~~~~~~~~~~~~~~~~~~~~~~~~

END NOTES:

[1] https://sandrp.wordpress.com/2014/05/03/do-large-dams-deliver-deception-and-delusion-oxford-university-research-says-they-do/
[2] In the 100th TAC meeting along with Khuga and Dolaithabi projects there were four other under construction irrigation projects considered by the committee. Three of these projects were from Tripura and one was from Assam. Due to unavailability of the minutes of 100th meeting in the CWC website, those four projects could not be discussed here.
[3] See news sections of http://www.manipuronline.in/ and http://www.hueiyenlanpao.com/
[4] http://www.hueiyenlanpao.com/headlines/item/7311-khuga-multipurpose-project-a-complete-failure-says-mangi
[5] http://manipuronline.com/features/khuga-dam-boon-bane/2011/03/08
[6] ibid
[7] http://manipuronline.com/headlines/jac-negates-ifc-minister-on-two-counts/2011/03/27
[8] http://kanglaonline.com/2012/10/dolaithabi-barrage-to-be-complete-by-2014/
[9] ibid
[10] http://irrigassam.nic.in/

Interlinking of RIvers · Maharashtra · Uttarakhand

Challenges for the new NDA government in India

National Democratic Alliance (NDA) led by BJP’s Mr. Narendra Modi has been given a mandate to govern India for the next five years. Without going into the political and social facets related to this issue, there are a number of justifiable concerns about this government’s stand on critical issues of water and environment.

While the importance of water and environment sectors for the people, their livelihoods, society and economy is acknowledged, how crucial these sectors are for them is not easily appreciated. For example, environment is important not only for tigers and trees, but also for livelihoods of hundreds of millions of Indians who depend on natural resources. More than 60-65% Indians continue to depend on agriculture and every farm can benefit from better water resource management.

Some of the major challenges plaguing the water and environment sectors in India include: urgent need for an inclusive, democratic and accountable governance, holistic assessment of impacts the very many interventions in the Himalayas (lessons from Uttarakhand flood disaster of June 2013[1]), ecological restoration of Ganga and other rivers, dealing with climate change in a way that protects lives and livelihoods of the vulnerable sections, etc., to name a few.

The leaders of the party forming the new government have already declared their agenda in terms of completion of Sardar Sarovar Project (SSP) on Narmada, pushing interlinking of rivers (ILR), pushing for more dams in the name of irrigation, pushing big hydropower projects in North East India (Mr Modi had said in his campaign that NE is heaven for hydropower projects) and mega industrial initiatives like the Delhi Mumbai Investment Corridor.

This agenda indicates that the importance of water and environment to the vast millions is not understood. Nor is the significance of the challenges to this sector appreciated.  Pushing the above agenda is not only fraught with serious risks in terms of social, environmental, economic and interstate issues, but these projects are not likely to deliver the promise of this party at the elections: Better life, more jobs, more development, fulfillment of  basic needs of the people who do not have access to these at the moment. Pushing this agenda is not likely to deliver stated promises, however blind push for more and bigger projects will compound strife and conflicts.

Let us look at the issues related to the NDA Agenda. These are not incidental issues, but issues inherent to the nature of these centralized, mega projects themselves.

Does ILR have scientific basis? The basic premise of ILR is that certain basins are water surplus and others are water deficit. It is assumed that occurrence of floods in a basin means there is surplus water in the basin and occurrence of drought or water scarcity in other basin means it is water deficit. This premise itself is not scientifically, ecologically and socially robust.

While this is said, there is no attempt at assessing and exhausting the available water options in any basin in India. Twithout this exercise, there can be no scientific basis for declaring a basin surplus or deficit. The ILR advocates seem to ignore the reality that India’s water lifeline is groundwater and the best way to sustain groundwater is through local water systems and recharge. They also seem to ignore the massive social, environmental impacts and constitutional issues. ILR is basically a collection of large number of major irrigation projects (over 84), but proponents of ILR do not seem to realize that in last two decades, there has been no addition to net irrigated area by these projects, in spite of addition of thousands of new projects.[2]

“Sabarmati Model” holds no water for Ganga or other rivers During the elections in Varanasi constituency that elected Mr Modi, the issue of cleaning of Ganga remained prominent. BJP claimed that they will clean up Ganga at Varanasi the way they cleaned up Sabarmati River that flows through Ahmedabad in Gujarat. The trouble with this claim is that Sabarmati has not been cleaned up at all. The water flowing through Sabarmati as it flows through the city of Ahmedabad is actually the water of Narmada River, diverted into Sabarmati. Ahmedabad has no right over this water which was supposed to be meant for Kutch, Saurashtra and North Gujarat. If you go upstream along Sabarmati River from the point where Narmada Main Canal releases water in Sabarmati, you will see the reality of dry Sabarmati River. And if you go down to the Vasna barrage, downstream of Ahmedabad along the Sabarmati, you will see the state of polluted Sabarmati River. This model clearly holds no water either for Ganga or any other river.

River Ministry? There is speculation in media[3] that the new NDA government is going to create a new River Ministry at the centre. The same media report also stated that this ministry will push Inter Linking of Rivers (ILR)! This seems like a proposal for Ministry of River Destruction, since ILR is a recipe for destruction of rivers. If at all the new government is  interested in an act of goodwill towards rivers, it needs to start with understanding what is a river and what are its  various functions along the various stretches during various periods, including the social, ecological, economic, hydrological, geo morphological, biodiversity related, groundwater related and most importantly, livelihoods related functions. This exercise will mean understanding the roles of various arms of the government which affect the river. Some key ministries which affect river profoundly include: Ministry of Water Resources, Ministry of Environment and Forests, Ministry of Power, Ministry of Urban Affairs, Ministry of Rural Development, Ministry of Home Affairs (Disaster Management), Ministry of Agriculture, Department of North East Region, Ministry of Non Conventional Sources of Energy, to name only a few. How is this new proposed Ministry of River Going to coordinate with these ministries? Moreover, according to India’s constitution, Rivers are essentially state subjects and no state is likely to welcome such infringement of centre into what the states see as their domain of responsibility.

Ganga a National Project? There are statements from Mr Amit Shah[4], that the new government will give National status to the Ganga Project. It is not clear what is meant by this. Ganga is already under the Prime-Minister headed National Ganga River Basin Authority, but the Authority, five years after its constitution, has failed to change a single attribute affecting the Ganga. Similarly, Ganga River Basin Management Plan that IIT consortium is working on is already known to be pathetic in its understanding of the river, while pushing for privatization. We do not need another project in the name of Ganga, national or local. If the aim of declaring Ganga as a National Project is to wrest its control from the state, as the media suggests, then it is going to raise a lot of hackles.

What we need is a new approach to river governance, which is based on ecological, and not engineering principles, which is participatory, and not exclusive and which is democratic and not autocratic.

Himalayas & Hydro-onslaught Irrefutable evidence shows that building large number of major hydropower projects in Himalayas is having unprecedented impacts, some are known, many are unknown. The flawed environmental governance around these projects is well known in terms of dishonest EIAs, flawed and compromised appraisals, ineffective (these are consultations just in the namesake, in reality there is no basis for  informed participation) public hearing and non-existent compliance, both at project and cumulative level. One implication of this was felt in terms of the role of such projects in the Uttarakhand flood disaster of June 2013, after which, no political leader from any party spoke about this. It was left to the Supreme Court to order and enquiry into this. The report of this investigation clearly indicates the role of hydropower projects in increasing the proportions of the disaster, and more work on this issue remains to be done. In North East itself, India’s biggest mass based public agitation against dams & hydropower projects has been going on. The anger of people has led to stoppage of the work on 2000 MW Lower Subansiri Hydropower project (largest capacity hydropower project under implementation in India) for 30 months now, after over Rs 5000 crores were irresponsibly spent by NHPC without completing even basic studies. Mindless pushing of more such projects in the region is clearly not a prudent move.

Source: MATU Jansangathan
Source: MATU Jansangathan

BJP manifesto’s promise of expeditious and single window environment clearances is clearly dangerous in this context. What India needs is stronger and not weaker environmental governance. The advocacy[5] to “reduce time and transaction costs for the industry” under the circumstances seems inappropriate particularly from an organisation which was possibly the only environmental organisation represented on the completely flawed EIA registration process at Quality Council of India. The QCI process failed to achieve any improvement in the quality of EIA in almost 4 years of its existence

Sardar Sarovar Dam The new government wants to take the SSP Dam from its current height of 121.92 m to its final design height of 138.68 m. Firstly, there are serious doubts if this height increase is required since it can be shown that Gujarat and Rajasthan can get their share of water from Narmada without this increase in height. Secondly, Gujarat is not even in a position to use more than 20% of the water it already gets from the river at current height of the dam for the purposes for which the project was designed: providing water for the drought affected regions in Kutch, Saurashtra & North Gujarat. On the other hand, urban centres, industrials areas, SEZs, cosmetic river beautification schemes have appropriated a large chunk of SSP waters without legal, democratic sanction or justification. Gujarat really does not have a case for increasing the height of SSP Dam.

Moreover, this will also entail such massive additional submergence, displacement and disruption of lives of tribals and farmers that it is sure to create huge opposition. The just rehabilitation of already affected people is far from complete, in fact, most of the affected population has not been given minimum 2 ha of land required under the Narmada Tribunal award and subsequent accepted policies.

Mr Modi during his tenure of 13 years as Chief Minister of Gujarat failed to complete the canal network of SSP in the drought prone areas in whose name the project has always been justified. It needs to be noted that the agitation against SSP did not stop Gujarat government from going ahead with construction of canal network. It was not for lack of finances that SSP could not complete the canal network. SSP has been getting largest quantum of money from the Government of India’s Accelerated Irrigation Benefits Programme ever since the AIBP scheme started in 1996. This support to SSP from AIBP was clearly wrong since SSP was never the last mile project for which AIBP was meant, but the big dam lobby in Union Water Resources ministry and Gujarat government were hand in glove in this misallocation of AIBP money for SSP. In fact, Mr Modi arm-twisted the Planning Commission in 2011-12 to sanction the escalated costs for SSP even when the issues raised by Planning Commission officers remained unanswered.

Unused Narmada Canal waters flow into Salt pans, not only at a hige cost, but also affecting lievlihoods of  salt pan workers and the ecology Photo: Counterview
Unused Narmada Canal waters flow into Salt pans, not only at a huge cost, but also affecting livelihoods of salt pan workers and the ecology Photo: Counterview

It is the ineptitude of Gujarat Government under Mr Modi that is on show in why it could not complete the canal network on drought prone areas in Gujarat. Mr Modi would do well to remember the reasons for that failure before he considers the mega projects agenda as Prime Minister.

Moreover, on SSP, the issues of completing repairs of the damages the Sardar Sarovar dam structure suffered four years ago & related issue of safety of the dam are yet to be resolved[6] and Gujarat has embarked on building another Garudeshwar Dam in immediate downstream without any impact assessments, participatory democratic process or required sanctions[7]. The legality of the Garudeshwar Dam work stands challenged in the National Green Tribunal by the affected tribals.

MAJOR RISKS FOR NEW GOVERNMENT Some major risks for the new government include: the track record of Gujarat government that Mr Modi headed for the last 13 years; no checks from coalition of parties; poor image, strength, morale and track record of Congress as the chief opposition party; large sections of almost completely subservient media[8] and BJP’s problematic manifesto[9].

Why UPA faced people’s anger The new government also needs to remember why the outgoing ruling coalition of UPA (United Progressive Alliance) lost so badly in spite of some unprecedentedly remarkable, and pro people steps taken by it. Absence of accountable and participatory governance (which also manifested in terms numerous scams) was one of the major reasons as to why there was huge anger in people’s mind about the UPA regime. Another aspect of corruption and high-handedness was apparent in the scandalous way UPA dealt with governance of environmental issues: blatantly changing its environment ministers from bad to worse.

Even if we leave aside the Rajas and Balus of UPA I, the UPA II began on a positive note with appointment of Mr Jairam Ramesh as environment minister. While we had our share of criticism of functioning of Mr Ramesh as environment minister[10], he was possibly the best environment minister India have had.

But under pressure from misguided and misinformed corporate vested interests, Mr Ramesh was removed (kicked upstairs) and Mrs Jayanthi Natarajan was brought in. She did not really help the cause of environment as is apparent, for example, from her answers to the two debates on Ganga river in Parliament (these debates were unprecedented in their own right) as also sanctioning projects rejected by statutory bodies like Forest Advisory Committee.

Strangely, she too was removed to bring in disastrously, Mr Veerappa Moily[11], who also held the Oil and Petroleum ministry. Mr Moily then went about the designated task of green lighting everything, not bothering about governance issues, people’s concerns or environmental consequences. This led to massive anger anger against Moily as well as UPA.[12]

Such arrogant handling of governance of environmental issues that affect the lives and livelihoods of millions of most vulnerable sections of people was bound to be punished[13]. This is clearly another reason behind the anger of people that UPA government faced in the elections.

Playing favorites UPA is also guilty of playing favorites when it came to appointing non governmental persons in environmental decision making. In almost every committee on environmental decision making, including Prime Ministers’ Council on Climate Change, National Tiger Task Force, Coastal Zone Management Committee, National Ganga Authority, Inter Ministerial Group on Ganga, Western Ghats Task Force, QCI process on registration of EIA consultants, 12th Plan working Groups to name only a few, everywhere one could find representatives of only particular organisation. Leaving aside the issue of effectiveness of the role played by representatives from this organisation, such tendencies of playing favorites is bound to raise serious questions. While many people at grassroots may not be aware of this inappropriate action by UPA government, the resultant outcomes of these committee invited various reactions ranging from disbelief, anger and even an uproar, as it happened in case of Kasturirangan Committee on Western Ghats.

While the result of anger of the voters could be seen in decimation of the UPA in the elections, the new NDA government will also do well to remember that even the Vajpayee government was voted out in 2004 for similar reasons. The mindless pursuit of agenda of inter linking of rivers and 50000 MW Hydropower initiatives, disregarding all the concerns and protests of the people across the country, along with the rejection of India Shining campaign were some of the causes for the voting out of the previous NDA regime in 2004.

SOME SPECIFIC TASKS In what follows we have given several examples of specific tasks before the new government. This is not an exhaustive, but only an indicative list.

Ganga Action Plan, Rivers Action Plans, NGBRA, CPCB, SPCBs Mr Modi has said that he would like to give priority to cleaning of Ganga River. Any such effort has any chance of success only if there is an attempt at understanding why our efforts at river pollution for the last 40 years have shown no impact:

Þ    Water Pollution Control Act, 1974 The Water Pollution Control Act led to setting up a huge and powerful bureaucracy including Central and state pollution control boards. 40 years after setting up of  this whole institutional and legal infrastructure, we do not  have a single that this establishment can claim to have cleaned up.

Þ    Ganga Action Plan, 1986 This plan was launched with much fanfare by the then Prime Minister Rajiv Gandhi, but without trying to understand why the water pollution bureaucracy failed.

Þ    National River Conservation Authority 1994 This authority, the only institution in the name or river conservation in India, had Prime Minister of India, no less, its chairman. In ten years of UPA, the Prime Minister of India did not get time for a single meeting of this authority.

Þ    GAP II 2000 The second phase of GAP was launched, again without making any honest attempt at understanding the failure of GAP I.

Þ    NGBRA 2009 In Feb 2009, just before the last parliamentary elections, National Ganga River Basin Authority, again under Prime Minister. As noted earlier, this too has failed to make any impact on the state of Ganga.

What all this shows is that we have tried many things, including legal, institutional, financial, and authoritative, with Prime Minister at the helm, but have achieved no success. This is also true of the previous NDA regime during 1998-2006. If we do not make an honest attempt at understanding the reasons for these failures, there is little hope for success in future.  The efforts at river cleaning has not suffered due to lack of money (over Rs 20 000 crores have been spent on Ganga alone, as per one estimate), for lack of institutions, for lack of political attention, for lack of media attention, for lack of judicial attention, for lack of infrastructure [where infrastructure exists (e.g. Delhi with the highest Sewage Treatment Capacity], there too there is no change in state of river), or technology. One major reason for the failure was the complete disconnect between the people whose lives depend on the river and those who took the decisions or managed the system. In other words, unless you make the river governance more democratic, there is no hope for Ganga or other rivers.

Some basic steps to make governance of rivers democratic could include: Setting up of management committee (with 50% independent members from outside the government) for management of each Sewage Treatment Plant, each freshwater treatment plant, each tributary, each 10 km stretch of river, each water utility, each city (& sub city level where cities have population above 1 lakh). These committees should be legally empowered and the officials should be made responsible to these committees.

Jayanthi Tax In this regard, it would be useful to remember that during the election campaign, Mr Modi had accused Mrs Jayanthi Natarajan for collecting Jayanthi Tax as environment Minister, allegedly for collecting bribes for environment clearances. This was a very serious charge Mr Modi had leveled. Now that he heads the new government at centre, he must institute a credible enquiry into this charge to prove that he was not making just frivolous statements.

Maharashtra Irrigation Scam One state that has given NDA the highest number of seats after Uttar Pradesh is Maharashtra, the NDA coalition got 42 of 48 seats in this state. One of the major reasons for this debacle of UPA was that the UPA here got a very corrupt image, in spite of its Chief Minister having a relatively clean image. This was largely due to the massive Rs 70 000 crores irrigation scam in that state. The NDA partners in Maharashtra also played a role in exposing this corruption, although the top brass of NDA was also allegedly involved in the scandal. To this  corrupt image was added the arrogance shown, for example, by deputy Chief Minister (who resigned on charges of corruption, but came back even without any investigation into the charges) when he first  asked how are people  expecting him to give water from dams – by urinating in the dams? During elections he actually threatened a village that water will be cut off if they do not vote for his party! This combination of corruption and arrogance was sufficient to enrage the voters.

Here again one expects the NDA government at centre to take decisive credible action in exposing the guilty in Maharashtra irrigation scam and brining to book those who are responsible both among the politicians and bureaucrats-engineers. Here, as BJP spokespersons in Maharashtra have been saying, the Madhav Chitale committee has basically done white washing role[14] and hence we need an independent investigation. We hope NDA government at centre will take this up urgently.

Andhra Pradesh Irrigation Scam Similar action is also required in Andhra Pradesh Irrigation scam exposed by the CAG report[15].

AIBP As noted above, the Accelerated Irrigation Benefits Program has majorly failed in achieving any additional net irrigation area by major projects at national level. The CAG has noted in more than one report the failure of AIBP and so has the Planning Commission. The new NDA government could start with instituting a credible independent enquiry into the reasons for failure of this scheme.

Uttarakhand Disaster and role of hydropower projects[16] Following the worst ever disaster faced by the state of Uttarakhand in June 2013, the role played by indiscriminate construction of hydropower projects and other infrastructure needed to be investigated since prime facie they had played significant role in increasing the proportions of disaster. The UPA government did nothing, and it was left to the Supreme Court to ask MoEF to set up an Expert Body for this. In the meantime, SC ordered stay on any more projects. The MoEF along with Central Water Commission and Central Electricity Authority and the Congress’s Uttarakhand state government, have been trying to push more projects in stead of honoring the Apex Court orders. In April 2014, the report of Expert Body lead by Dr Ravi Chopra has been submitted. The new Union government, it is hoped, will take credible steps to implement the recommendations of the Expert Body at the earliest date.

Independent National Environment Monitor It is well known that MoEF as an independent environmental regulator is seriously compromised with shoddy EIAs, flawed appraisal and non existent compliance. This situation has remained unchanged for the last decade and more. The Supreme Court of India, seeing this, had in 2011 ordered that an Independent Environment Regulator needs to be set up at National and state level. The outgoing central government had shown reluctance to do anything in this regard, in spite of repeated Supreme Court orders. The new government has a historical opportunity to indeed set up a truly independent & accountable environment regulator, at the same time increasing the transparency and participation of people in the environmental governance through fresh round of democratic reforms.

Cabinet Committee on Investment One of the flawed legacy of the previous UPA government is the Cabinet Committee on Investment, which has been created to bypass the statutory work of the MoEF. The new Union government would do well to disband this extra legal committee.

Polavaram Project Authority Even as elections were underway, in a most inappropriate decision, the outgoing government set up a Polvaram Project Authority, without even consulting affected states of Orissa and Chhattisgarh. In both these states there is either BJP government or BJP led government. There are also cases going on against this project, including civil suits filed by the governments of Chhattisgarh and Orissa. In the interest of these states and affected tribals, the new Union Government should scrap the Polavaram Project Authority.

Tribals protesting against Polavaram Project Photo:http://www.frontpageindia.com/andra-pradesh/unique-protest-by-tribals-against-polavaram-project/41401
Tribals protesting against Polavaram Project Photo:http://www.frontpageindia.com/andra-pradesh/unique-protest-by-tribals-against-polavaram-project/41401

Mullaperiyar The 119 year old Mullaperiyar dam has already suffered damages in the past and there is no doubt that it has limited life. To overcome the inflexible attitude of Tamil Nadu and respecting the constitutional duty of Kerala government to protect the life and property of people of Kerala, it become the duty of the Union government to initiate process for new a arrangement (e.g. lower the intake level to 50 ft from current 106 ft, as seen promising both by the Empowered Body and Supreme Court in May 2014) and decommissioning of the dam in a time bound manner. The previous Union government completely failed in this and the new government has an opportunity to correct this.

Central Water Commission Central Water Commission is India’s premier technical body on water resources. Water resources development and management has always remained crucial to any country’s water, food, livelihood and environment security. However, for this we need a really independent and credible technical body at the top, on the lines of United States Geological Survey (USGS). USGS, is known to be source of very reliable water resources data world over. However, USGS’s main task is to gather data and put it in public domain. Use of that data for development tasks and such other functions are not the mandate of USGS, there are other bodies for that. Unfortunately in India, CWC tasked with data gathering, sanctioning projects, monitoring and so many other contradictory functions. Moreover, CWC is working more like a big dam lobby, and even the assessment of hydrological data, flood forecasting functioning, water use data and projections, climate change implications, dam safety issues, etc are all getting colored by the lobbying tendency of those who head CWC. This is having a very deleterious effect on the water resources development and management in India.

It is high time that there are reforms in CWC to separate its various contradictory functions and make its functioning transparent, accountable and participatory. The new Union government has a chance to initiate such reforms in CWC and Ministry of Water Resources.

Technical Advisory Committee of CWC The TAC of CWC is a very little known, but powerful body. It sanctions projects worth thousands of crores every year, but its functioning is completely non transparent, unaccountable and it has no independent members. Since the new government has been raising the issue of corruption by UPA during the election campaign, it is hoped that the new government will work to fight corruption and one of the key steps it can do is to make the functioning of TAC transparent, accountable and ensure that at least 50% members of the TAC are non governmental, independent people with track record of having shown independent mind.

Urban Water Sector The social, environmental, economic and carbon footprint of this sector increasing at huge pace, without any success story in sight. The big cities are find it easy to promote construction of big dams rather than go for rain water harvesting, sewage water treatment & recycle, demand side measurement, groundwater recharge, reduction in losses and such other measures. SANDRP report on unjustified dams being pushed in Mumbai highlights this issue. The 12th Plan Working Group report on Urban water issues have several useful recommendations that has remained unimplemented. These need to be urgently implemented.

Climate Change Climate change in the biggest threat that vulnerable sections of Indian people face, as do the vulnerable sections of the rest of the world. This is not only relevant for water and environment sectors that we are discussing here, but for all sectors. As Environmental Groups in Gujarat have noted[17], people of Gujarat do not have good experience of the Modi regime in the state. The record of the 10 year long UPA government is very poor on this issue. We hope the new Union government will do better and begin with identification of the sections of the people who are vulnerable and start working on action plan to address the concerns of such sections, while also reducing the carbon footprint of India through reduction in consumption patterns of richer sections.

Suggestions for positive actions As analysed by Dr. Ashok Gulati (former chairman of Commission for Agricultural Costs and Prices) and Dr. Tushar Shah (International Water Management Institute) separately, the relatively high agricultural growth in Gujarat in first decade of  current millennium was largely due to local water harvesting work that happened in Gujarat through check dams, groundwater recharge etc, largely in non governmental sector. The new government at centre can bring about changes in policies and programs to learn lessons from such success stories to achieve such results all over India.

  • Similarly on the issue or river rejuvenation, management and conservation front as also environmental management front, a decentralized bottom up community driven approach can be taken up.
  • It can encourage people led, scientific and ecological river restoration work.
  • Promote System of Rice Intensification in a major way, it can not only reduce water use, fertiliser use, use of other chemicals, reduce seed requirement, increase farmers’ income, reduce agriculture sector’s carbon footprint and thus help mitigate and also adaptation to changing climate. This is possible in other crops too, as has been demonstrated at farmer level.
  • Encourage measures that can help increase carbon content of the soil, this will also have multiple benefits to farmers, economy and environment.
  • It can strengthen implementation of Forest Rights Act which UPA, despite introducing it, failed to do.
  • It can protect free flowing rivers for their social, ecological, cultural values.
  • It can also engage more effectively with civil society and community groups in a credible manner.
  • A recent SANDRP study “Shrinking and Sinking Deltas: Role of Large Dams” has shown that large dams are playing big  role in sinking of deltas in India. This is not even properly studied. The new government can initiate a scientific study in this regard and ensure that before taking up any new project, this aspect is studied.

Conclusion I started writing this brief note following questions from several media friends, but it has become much longer! So let us come to the conclusion. I am not even sure if the new government is in any mood to listen to such unsolicited suggestions, but let us put it out and hope for the best! I decided to put this out, even as Mr Modi prepares to take office on May 26.

This article tries to show the risks, challenges and some immediate tasks of the new government at the centre. In sum, the new NDA government would do well not to forget the reasons for rejection of NDA in 2004 and UPA now in 2014. Both were guilty of bull dozing ahead with their agendas without listening to the people.  Avoiding that may be the biggest challenge this government faces, besides the specific ones mentioned above.

Himanshu Thakkar[18] (ht.sandrp@gmail.com)

END NOTES:

[1] https://sandrp.wordpress.com/2013/06/23/uttarakhand-floods-disaster-lessons-for-himalayan-states/

[2] https://sandrp.in/irrigation/Failure_of_Big_Irrigation_Projects_and_Rainfed_Agriculture_0510.pdf

[3] http://timesofindia.indiatimes.com/home/lok-sabha-elections-2014/news/Will-an-NDA-government-form-separate-ministry-for-rivers/articleshow/35128448.cms

[4] http://timesofindia.indiatimes.com/home/lok-sabha-elections-2014/news/Modi-plans-to-nurture-Ganga-as-national-project-Amit-Shah-says/articleshow/35082208.cms

[5] http://www.downtoearth.org.in/content/adding-another-national-regulator-will-not-help-environment

[6] https://sandrp.wordpress.com/2014/04/26/why-is-gujarat-neglecting-safety-of-sardar-sarovar-dam/

[7] https://sandrp.wordpress.com/2014/04/18/why-is-this-dam-being-constructed/

[8] https://sandrp.wordpress.com/2014/04/04/why-is-media-missing-the-real-gujarat-story-gujarat-satya-samachar/

[9] https://sandrp.wordpress.com/2014/04/07/election-manifestos-of-bjp-congress-and-aap-comparative-reading-on-environment-and-natural-resource-management/

[10] https://sandrp.in/otherissues/Jairam%20Ramesh%20as%20Environment%20Minister%20-%20An%20Assessment%20July%202011.pdf

[11] https://sandrp.wordpress.com/2013/12/21/veerappa-moily-as-environment-minister-has-the-upa-leadership-learnt-no-lessons-from-aap-experience/ and https://sandrp.wordpress.com/2014/01/03/open-letter-to-upa-leadership-please-remove-mr-moily-from-paryavaran-bhawan/

[12] http://www.greenpeacex.in/petitions/oily-moily-needs-to-go-1

[13] For example, Dakshin Kannada and Mangalore saw a huge socio-political movement against Moily and Congress due to his politically motivated support to Yettinahole Diversion Project.

[14] https://sandrp.wordpress.com/2013/07/08/why-sit-under-dr-chitale-should-be-taken-seriously/ and https://sandrp.wordpress.com/2014/03/03/vijay-pandhares-letter-to-dr-chitale-please-fix-responsibility-of-the-irregularities/

[15] https://sandrp.wordpress.com/2013/07/19/cag-blows-the-lid-off-massive-irrigation-scam-in-andhra-pradesh/

[16] https://sandrp.wordpress.com/2014/04/29/report-of-expert-committee-on-uttarakhand-flood-disaster-role-of-heps-welcome-recommendations/

[17] http://paryavaranmitra.wordpress.com/2014/05/

[18] The numerous suggestions given by Ms Parineeta Dandekar of SANDRP are gratefully acknowledged.

[19] https://sandrp.in/Dams_in_tribal_belt_of_Western_Ghats_for_the_Mumbai_Metropolitan_Region.pdf

[20] https://sandrp.in/Shrinking_and_sinking_delta_major_role_of_Dams_May_2014.pdf

Interlinking of RIvers · Maharashtra · Western Ghats

Interbasin Diversion Dams in Western Ghats: Unknown impacts and uncertain Benefits

ManjarpadaBoxDiscussions on Interlinking of Rivers are gaining momentum as new government takes charge at the centre. It is predicted that the new government will be supportive of ecologically and socially questionable plan of interlinking rivers. In this backdrop, it will be interesting to study the fate of a little known scheme of diverting west flowing water to the Godavari Basin in Maharashtra. While the entire ‘grand’ plan includes many such schemes, we are focusing on one of the biggest interbasin diversion project under this scheme. Manjarpada Phase I project which is on a shared basin between Maharashtra and Gujarat, located in the Dindori Taluka of Nashik District. We also look at the status of about 28 interbasin diversion schemes proposed and under construction in this region, their justifications, benefits as well as impacts.

  1. Manjarpada Phase I under Upper Godavari Irrigation Project

Manjarpada Phase I forms part of the Upper Godavari Irrigation Project under the Water Resources Department, Maharashtra. The original proposal of the Upper Godavari Irrigation Project included Dams like Waghad, Karanjvan, Palkhed and Ozarkhed, which received administrative sanction in 1966. Work was started in 1968. From here on a number of components like Punegaon Dam, Tisgaon Dam, several canals kept getting added to the scheme. However, it remained essentially an intra basin project, there was no inter linking rivers component here.

In 2008 a radically different component was added to Upper Godavari Project. This was the inclusion of 12 diversion weirs on Paar, Taar, Damanganga Basin Rivers that in normal course would flow into Gujarat. These weirs envisaged near the ridge line, transferring waters of these into dams built in the Godavari Basin, via deep canals across the Western Ghats, which will transfer water from west flowing rivers to the east flowing Godavari. According to the White Paper on Irrigation Projects brought out by the Water Resources Department of Maharashtra in December 2012, these diversion weirs and Manjarpada Phase I scheme added an irrigation potential of about 30,000 hectares in the Upper Godavari Projects. The total irrigation potential of the entire Upper Godavari projects is estimated as 74,000 hectares (including 30,000 hectares from Diversion projects), of which potential of 69000 hectares is claimed to be created. This is unbelievable as the Diversion weirs, with a total command of 30,000 hectares, are just about half complete. The White Paper states that about 55% work on Manjarpada project and about 60% work on 11 diversion weirs has been completed.

An interbasin transfer scheme that claims a cumulative irrigation potential of 30,000 hectares will have significant impact on ecosystems, communities and downstream hydrology. But no such studies have been conducted for these projects, there has been no public consultation process and it is not even known if there is any interstate agreement for this transfer. The most striking example is Manjarpada Phase I project which envisages transferring about 500 million cubic feet (Mcft) from the Paar basin into Punegaon dam in the Godavari basin by way of a dam and two significantly big tunnels. Officials of Water Resource Department have stated that the project, submerging 95 hectares of land, also needs Forest Clearance for 65 ha forest land, which has not been granted yet, although work is in an advanced stage! This is clearly illegal as per the Forest Conservation Act (1980).

SANDRP’s visit to Manjarapada Phase I Project When we visited the site of Manjarpada project, we were first struck by the name. The project has nothing to do with Manjarpada village, but is entirely based in Devsale Village of Dindori Taluk. Work on the main dam has been stopped for many months now. The villagers say that this is due to local protests, while the officials claim this is due to paucity of funds.

No impact assessment of the project has taken place. When we visited Devsale village, we were mobbed by villagers who wanted to show us the damages caused by the project for which they have received no compensations. The incessant blasting of the tunnel in the hardrock has resulted in cracks to many homes. More than 250 villagers claim that they have lost water from their shallow wells/ bore wells. More than 50 well owners have submitted a memorandum to the Collector and Zilla Parishad office about drying up of their wells.

M1

Above: Manjarpada Dam wall under construction. Photo: Amit Tillu for SANDRP

The villagers indicate 2 tunnels under construction for the same project, one of which is complete in 1 km length and the other complete in nearly 8 km length, with a huge air vent 20 m wide and over 150 m deep. The depth of the tunnel underground is about 150-300 feet.

m2

Above: Under construction tunnel at Manjarpada Phase I Photo: Amit Tillu for SANDRP

The laborers employed by the subcontractor do not understand Marathi and cannot respond to questions asked by the villagers. Work on the main dam wall has stopped since the last 2 years. Villagers say that blasting and tunneling has severely affected groundwater in the region, which has fallen drastically after tunneling. Blasting has resulted in not only cracks in over 100 homes, it has led to collapse of more than 10 built open wells, turning them into puddles. This was witnessed by us. Displaced families have not been resettled[1] yet.

Corruption involved in the unfeasible Manjarpada Project: Whistle-blower of the Water Resources Department Vijay Pandhare has been highlighting issues about Manjarpada project since a long time, when he was in service as Chief Engineer at Maharashtra Engineering Training Academy. He had pointed serious irregularities about this project in his letters to the Secretary, Maharashtra Water Resource Department, state Chief Minister Prithviraj Chavan as well as separately to Dr. Chitale who was supposed to be investigating the Maharashtra dam scam.

Pandhare talked exclusively with SANDRP on Manjarapada Project, he said: “This project is planned to transfer about 500 million cubic feet of water and is costing about Rs 500 crores and these estimates will increase. It should have costed a fraction of this. The entire process of Manjarapada Phase 1 was driven by the politician and contractor lobby and there was never any space for rational questioning. In addition to Manjarpada Stage I, the department is now also pushing for Manjarpada phase II downstream of this project, which will divert water right into the Tapi Basin. Now the catchment area of Manjarpada Phase I and Phase II actually overlap and the projects are simply unfeasible as there is no water availability as stated in the water availability certificates. This needs to be thoroughly investigated and I had written about this to many authorities, in vain.”

Shri. Pandhare is justified in raising these issues. If we look at the internal note of MID, with SANDRP, it states that in 2008 Manjarapada project was approved Rs. 62.54 Crores. Till December 2013, Rs 122.66 Crores were spent on this project! This has resulted in 30% work on spillway, 80% on connecting tunnel, 100% on open canal, 72% on diversion tunnel.

The last line on the project drops a bomb. It states: “An estimate for Third administrative approval for Upper Godavari Project, which includes the cost of this project at Rs 430.74 crores for Manjarpada project, has been presented before the government for approval.” So within 5 years, cost of the project shot up nearly 6 folds!

M3Above: One of the several open wells collapsed due to balsting for Manjarpada project Photo: Amit Tillu for SANDRP

Pandhare writes in his letter to the Secretary and Chief Minister, the letter that initially shook the water management circles in Maharashtra[2]. “The system that makes cost estimates in WRD is has been nearly killed. So the field officer has been made in-charge of working on estimates. In reality the contractor makes these estimates and they are sanctioned without checking. Otherwise such unfeasible and costly work would not be undertaken… In case of Manjrapada project, the cost estimates, especially tunnel excavation costs have been bloated beyond measure. The benefits are hazy. When Phase I is questionable, unfeasible and hugely costly Manjrpada II is being pushed by political backing. This project has a water availability certificate, when in fact the catchment does not have enough water.” He has specifically requested Dr. Chitale to investigate this project.[3]

When we met the Executive Engineer, MI Projects (Local Sector), for Nashik division, he agreed that there is controversy surrounding Manjarpada Projects, especially related to feasibility and overlap of catchment area, but refused to comment further. He softly added that political interference with water resource department should reduce. In the meantime, Chagan Bhujbal, former MP from Nashik region (he lost in 2014 Parliamentary elections by huge margin of close to 2 lakh votes) has been stating that Manjrapada II will happen at any cost.[4]

One of the official stated that Manjarpada project is the ‘Boss’ of these schemes as it will route water from many schemes in the Paar Basin into the Godavari Basin. Though he later added that the main reason for pushing Manjarpada was that the Punegaon Dam, downstream Manjarpada has not been filling up in monsoon and Manjarpada will aid it. This again underlines Pandhare’s claim that water availability certificates being given for projects in Maharashtra (like Punegaon) are not scientific and driven by other motives!

M4

Above: Villagers at Devsale talking about issues of Manjarpada Project I Photo: Amit Tillu for SANDRP

Incidentally, according to white paper, it’s interesting to see the list of water users downstream of these projects. They include Ranwad sugar factory, K Distillery, Ashokumar Hatcheries, Everest Industries, Seagram Distillery, Shivam chemical, Kadwa Sugar industry, Dinodri MIDC (which is a Wine MIDC in Maharashtra) & have a reservation on 136 MCFt. While Manmad taluka suffered acute water stress in drought in 2012-13, water supply to distilleries and wine industries continued.

This whole episode involving the project, its decision making process, lack of impact assessment and credible techno-economic appraisal and monitoring raises many questions. In the first place, the Manjarpada project highlights the need for thorough participatory processes that should be undertaken before taking up such projects, especially when they involve interbasin transfers.

Maharashtra and Gujarat have signed an MoU to transfer waters from Damanganga River into Vaitarna basin through Bhugad, Khargihill and Pinjal Dams and tunnel systems. The tunnel envisaged between Pinjal and Khargihill stretches over 64 kilometers, more than 5 times the tunnel in Manjarada. It is clear that the impacts of not only the dams, but the tunnel systems will be huge and need investigation.

More than 19 Diversion Projects diverting “unutilized water going waste to the Arabian Sea”

When we met officials at the Minor Irrigation Division (MID), they showed us the map of intricate links planned in the entire Damangagang, Paar, Naar Basin as well as parts of Vaitarna and Ulhas basin to transfer water “flowing unutilized to the Arabian Sea” into the Godavari Basin. It is difficult to imagine that a project of this massive scale, which can transfer nearly 400 MCM from West Flowing basins into the Godavari basin is going on without any project specific impact assessment, cumulative impact assessment, cost benefit studies, environmental appraisal, environment management plan, public consultations, environmental monitoring and based on questionable water availability studies.

The Maharashtra Irrigation Dept GR dated Sept 2005 approved the proposal of diversion schemes near the ridge line to divert water which was “going waste, unutilised into the Arabian Sea” to Godavari Basin in the East. 19 such schemes have received approval from the Hydrology Project (Jal Vgyan Prakalpa) Nashik. Of these 19 schemes, 13 have been included in the second administrative approval of the Upper Godavari Project, but there are in all nearly 28 diversion schemes under consideration. Table in Annexure 1 provides details of the various schemes under this project.

M5

Above: Diversion Weirs at Dindori, with deep canal on the upstream transferring water Photo: Parineeta Dandekar, SANDRP

SANDRP team also visited some of these diversion weirs.

In case of Amboli Diversion Weir, its capacity is supposed to be close to 1 MCM (million cubic meters). It was bone dry in May when SANDRP team visited it. Sagar Marathe, who resides next to the weir states that the weir, now complete, hardly holds any water in it. The reason seems obvious. Just 200-300 mts upstream the dam wall, a high canal embankment runs, which means that the dam has nearly no catchment area! There is no study on the amount of water that is indeed diverted into Kashyapi River here, a tributary of Godavari.

M6

Above: Dam wall and the dry Amoboli Diversion Weir reservoir can be seen on the left, on the right is a tall embankment of an older canal which runs parallel to the dam wall and is much longer. Effectively, the dam has nearly no catchment. Photo: Parineeta Dandekar

In case of Waghera diversion weir, which is supposed to be under construction, the tribal villagers told SANDRP that the mud dam has been existing since the past 20-25 years and the only work going on is digging the canals! But the MID note does not state that the dam is already existing, possibly indicating an irregularity.

These examples are only indicative. They highlight the need for transparent and participatory studies surrounding these projects.

M7

Above: Unlined canal in Dindori, transferring water onto Waghad Dam. Photo: Parineeta Dandekar, SANDRP

Environment laws violated, but MoEF in dark and inactive! Manjarpada Diversion and other diversion dam projects are coming up in violation of the EIA Notification 2006, but MoEF seems to know nothing about it. Manjarpada or other diversion schemes cannot claim exclusion from the environmental appraisal process since it involves huge irrigation, in addition to inter basin transfer, domestic & industrial water supply.

The entire diversion scheme raises big questions about significant impacts, needs of the downstream population, local opposition and finally questionable and unassessed benefits. We hope MoEF will take cognizance of the legal violations and take stringent steps against Maharashtra government. Unfortunately Maharashtra is mired with too many of such examples, in addition to the dam scam.

– Parineeta Dandekar ( parineeta.dandekar@gmail.com), Amit Tillu ( amittillu@gmail.com) with inputs from Himanshu Thakkar ( ht.sandrp@gmail.com)

 ~~~~~~~~~~~~~~~~~~~

Annexure 1

Table 1 Overview of Interbasin diversion projects planned to divert water into the Godavari Basin.

Name Basin Basin in which water is transferred Quantity Remark
Manjarpada Diversion Project Nashik Par Godavari: Punegaon and Karanjvan Dams 17.16 MCM
Golshi Mahaji Flow Diversion Project, Dindori Damanganga origin 10 nallahs to be diverted Waghad Dam, Godavari 0.47 MCMto be transferred Current cost around 32 Crores( 12.97 spent, 21.31 requested)
Nanashi Flow Diversion Project, DindoriNashik Nar-Par. Dam at the origin of Par, from here to Hattipada DW, from there to Karanjvan Dam Karanjvan Dam, Godavari 1 MCM into Godavari 0.55 MCM for local use Initial estimate was 3.04 crores in 2008. Actually 3.81 crores spent, Now application for 17.1 crores made for 3rd administrative approval
4. Golshi 1, Flow Diversion Project, Dindori Dindori Damanganga Basin Waghad Dam 3.11 MCM 1.29 crores in 2008.3.15 crores asked in 3rd administrative approval
5. Hatti pada, Flow Diversion Project, Dindori DindoriNashik Paar Basin Karanjvan dam, Godavari Basin 0.93 mcm to Karanjvan Dam. 0.67 mcm for local use 3.11 crores in 2008, 7.64 crores spent till Dec 2013, now requested: 14.24 crores in 3rd approval
6. Dhondalpada Flow Diversion Project NA Godavari basin 1.73 MCM Consists of5 saddle dams
7. Chaphyacha pada Na Godavari 0.30 MCM
Ranpada Diversion project NA Godavari 0.35 MCM
Payarpada Flow Diversion Canal, Dindori Nashik NA Godavari 2.039 MCM Local opposition to Land aquisition. Hence work not started.
Ambaad Diversion canal. Dindori Nashik 0.40 MCM Local opposition to land acquisition. Work not started
Pimpraj F diversion Project NA Godavari 1.26 MCM
Ambegan F Diversion Prjct NA Godavari 1.40 MCM
Jharlipada F Diversion Prct Waghad Dam, Godavari Basin 1.05 MCM
Chimanpada Flow Diversion Project Dindori Godavari 0.83 MCM for diversion; 0.45 MCM for local use, No technical Sanction yet
Waghera Flow Diversion Scheme, TrimbakNashik Damanganga Basin Godavari ( no dam, u/s of Ganga pur Dam) 1.19 MCM Sanctioned cost in 2007 was 15 crores. 80% work complete, Link cut work under progress
Pegal wadi Flow Diversion Project, Trimbak, Nashik Vaitarna Basin Godavari 0.695 MCM In 2004, 17.92 crores approved
Amboli (Bombiltekpada) Godavari 0.92 MCM 17.92 Cr approved in 2004 (an error?)
Total 34.83 MCM
Schemes which do not have administrative approval, but are included in the Upper Godavari Project by the Godavari Irrigation Development Corp.
Velunje-Amboli Dvrsn Prjct Damanganga Godavari 1.447 MCM 16.07 crores estimated
Kalmuste Diversion project Damanganga Godavari 23.141 MCM by a diversion weir 333 Crores estimated price
3. Kapwadi Diversion Project Ulhas Godavari 7.04 MCM Estimated cost 60.8 Cr
Sub Total 31.62 MCM
Projects with survey permissions and administrative approval
Lift dvrsn prjct 3, Surgana Paar Godavari 94.37 MCM
Lift dvrsn prjct 4, Surgana Paar Godavari 89.12 MCM
Sub Total 183.49 MCM
Water Diversion from Upper Vaitarna Basin to Godavari Basin
Note: GOM approved the scheme to fit doors to the saddle dam of Vaitarna project and transfer water into Godavari. However, Thane Circle of KIDC had acquired 4689 hectares of Upper Vaitarna Project. Eventually, Dam height was reduced and 623 hectares was additional land left which should have been returned to the PAPs. But this was not done. There is a strong opposition of local people to any survey without this return. No has been conducted as yet. 28.50 MCM.
6 Diversion projects for Ahmednagar under very primary planning
Hivra Walvani Diversion Weir Pravara 18.46 MCM 13 hectares forest land
Samrand Diversion weir Pravara 17.98 MCM 6 hectares forest land bot fall in PA. Hydrology Project communicated that the project is not supported by the GOM. CE, KIDC has written in 2012 that there is no water to transfer to the east.
Sub Total 36.44 MCM
Transfer water from Shai and Kalu Basins into Akole between Harishchandragad and Ajoba Mountain into Mula basin
Tolarkhind Tunnel Project 18.08 MCM CE, KIDC has written in 2012 that no surplus water available in Shai & Kalu Basins for dvrsion.
Khirehwarer Tunnel Prject 40.01 MCM
Sadada Tunnel Project 11.13 MCM
Pathar Ghat dvrsn canal pr 7.67 MCM
Diverion from Kalu and Shai Basin 76.89 MCM
TOTAL PLANNED DIVERISON FROM WEST TO EAST in Godavari Basin 391.77 MCM

Source: Minor Irrigation Department, Nashik Division

~~~~~~~~~~~~~~~~~~~

END NOTES:

[1] http://indianexpress.com/article/india/india-others/land-lost-to-irrigation-project-tribal-families-reel-in-poverty/

[2] https://sandrp.in/irrigation/Letter_Maharashtra_Irrigation_Scam_Oct12.pdf

[3] https://sandrp.wordpress.com/2014/03/03/vijay-pandhares-letter-to-dr-chitale-please-fix-responsibility-of-the-irregularities/

[4] http://www.deshdoot.com/news.php/news/4313229

Arunachal Pradesh · Dams

Dibang Project Rejected Forest Clearance for the Second Time

PROJECT UNABLE TO SUBMIT SATISFACTORY PROPOSAL EVEN SIX YEARS AFTER PM LAID FOUNDATION STONE!

In a remarkable decision, the Forest Advisory Committee (FAC) of MoEF has rejected the forest clearance to 3000 MW Dibang multipurpose project for the second time in its meeting held on 29 -30 April 2014. In that meeting FAC considered the Dibang multipurpose project for diversion of massive 4577.84 ha of biodiversity rich forest land which would lead to cutting down of huge 3.24 lac trees.

Continue reading “Dibang Project Rejected Forest Clearance for the Second Time”

Chenab · Jammu and Kashmir

Massive Kwar and Kiru HEPs on Chenab, J and K : Poor quality & cut paste EIAs, flawed public hearing

It seems we do not want to learn any lessons from the massive Uttarakhand disaster of June 2013. Two more huge capacity hydropower projects have been submitted to the Expert Appraisal Committee (EAC) of Ministry of Environment & Forest (MoEF) for grant of Environmental Clearance (EC) with very poor quality Environmental and Social Impact Assessment (EIA) reports.

EIA reports of Kiru Hydro Electric Project (HEP) (660MW) and Kwar HEP (560 MW) proposed in Kishtwar district, Jammu and Kashmir by Chenab Valley Power Projects Ltd. (CVPP) were submitted to the EAC for River for its 74th meeting held on 5-6 May, 2014 for grant of EC. The projects are run-of-river schemes proposed on river Chenab as a part of cascade development of Chenab basin.

Vicinity Map

Vicinity Map (Source Kiru EIA Report)

 Partial map of Hydro Electric Projects on Chenab river basin

Partial Map of Commissioned and Proposed HEPs in Chenab River Basin (Map by SANDRP)

 

Chenab basin may have one of the highest concentrations of hydropower projects among all basins in India[1]. The basin has over 60 HEPs under various stages of planning, construction and commissioning in states of Himachal Pradesh (HP) and Jammu and Kashmir (J&K).

While 49 of these projects are planned or under construction in Chenab in HP, 28 projects of combined generation capacity of 5,800 MW are at an advanced stage of obtaining (Environment Ministry) clearances[2]. State of J&K has 13 projects planned of total capacity 8,623 to 8,923 MW. These consist of at least four operational projects (of total 1563.8 MW), three under construction projects (of 1450.5 MW) and six proposed projects (of 5608.7 MW).

Table 1: Cascade Development of Chenab Basin

Source: EIA report of Kiru & Kwar

Sr. No. Scheme River Capacity
1 Salal (Stage- I & II) Chenab 690 MW
2 Sawalkot Chenab 1856 MW
3 Baglhar (Stage-I & II) Chenab 900 MW
4 Shamnot Chenab 370 MW
5 Ratle Chenab 850 MW
6 Dulhasti Chenab 390 MW
7 Kwar Chenab 560 MW
8 Kiru Chenab 660 MW
9 Kirthai-I Chenab 350 MW
10 Kirthai-II Chenab 990 MW
11 Barinium Chenab 240 MW

Himalayan ecosystem, of which the Chenab river basin is a part, is known to be geologically fragile. Cascade of hydel projects proposed on the river basins of this region would make the region even more vulnerable to extreme and erratic weather events, which will increase in changing climate. This has already been witnessed during Uttarakhand disaster of June 2013. Expert Body (EB) headed by Dr Ravi Chopra recently has officially acknowledged this connection in the report submitted to MoEF[3]. In light of this, a thorough impact assessment of all the proposed hydro power projects in this region is thus of critical importance. Various organizations and experts including SANDRP have repeatedly highlighted the fact that Cumulative Impact Assessment (CIA) of all the proposed, under construction and operational projects and carrying capacity assessment (CCA) of the river basin to see if it can support the massive number of HEPs in safe and sustainable way is one of the first steps before considering clearances to HEPs in this region. Without such a study, considering any hydropower project in the basin will be an invitation to disaster[4].

Even though the MoEF sanctioned TORs for cumulative impact assessments of the HEPs on Chenab in HP in February 2012, this critical task was entrusted to the Directorate of Energy, Government of Himachal Pradesh. This is a clear case of conflict of interest. Further the project specific ECs were delinked from the CIAs[5].

More importantly, no such study has been initiated in Chenab basin in J&K or in the Chenab basin as a whole. State of Jammu and Kashmir is not even considering CIA of HEPs on Chenab in the state as MoEF has not asked for it yet. CIA of the entire Chenab basin including HP and J&K is not being considered, which itself is violating MoEFs Office Memorandum dated May 28 2013. The OM states that all states were to initiate carrying capacity studies within three months from the date of the OM No. J-11013/I/2013-IA-I. Since this has not happened in case of Chanab basin in J&K, considering any more projects in the basin for Environmental clearance will be in violation of the MoEF OM.

On Cumulative Impact Assessment, the OM said, “While, first project in a basin could come up without insisting on cumulative impact study, for all subsequent hydro-power projects in the basin, it should be incumbent on the developer of second/ other project(s) to incorporate all possible and potential impacts of the other project (s) in the basin to get a cumulative impact assessment done.” The EIA of both the projects does not include the cumulative impacts.

MoEF continues to give clearances to individual HEP projects despite of poor quality Project Feasibility Reports (PFRs) and EIA reports submitted for appraisal. Kiru & Kwar EIA reports are a classic example of such poorly conducted EIAs. The EIAs demonstrate several serious issues across various stages from TOR non-compliance, non assessment of impacts, cut and paste job, lack of any references, faulty public hearings, the issued raised at public hearings have not been addressed in EIAs, as statutorily required. SANDRP recently made detailed submissions to EAC highlighting these issues for both the projects. Some highlights below:

Copy paste job while preparing EIA reports Both the reports are prepared by a consortium of RS Envirolink Technologies Pvt. Ltd. (Gurgaon) and Jammu University. Kiru EIA report demonstrates a casual approach towards impact prediction and proposing mitigation measures in EMP. The report also misses out on a number of important aspects of EIA like impact of construction activities on geology, flora fauna, impact of climate change, cumulative impacts of cascade development in Chenab basin etc. While Kiru EIA is inadequate on several fronts it was utterly shocking to discover that Kwar EIA report is a complete replica of the Kiru EIA Report. Entire text, save project specific numbers, remains the same in both reports, to the extent that the Kwar EIA report mentions Kiru instead of Kwar at several places!! The impact prediction for both the cases is so vague and generic that the changes in numbers for project-specific details like proposed installed capacity, submergence of reservoir, FRL, head race tunnels etc. do not reflect at all in the reports!

Brief Project Profiles Kiru H.E. Project and Kwar H.E. Project are run-of-river schemes proposed on river Chenab located in the district Kishtwar of J&K.

Kiru HEP envisages the construction of a 193 m long and 123 m high concrete gravity dam above the river bed across river Chenab at village Kiru with four intake, four pressure shafts, an underground powerhouse of 4 units of 165 MW each. Impoundment will cover an area of 1.03 Km extending 6.5 km upstream of dam. The average river bed level at the dam site is about EL 1394 m corresponding to an FRL of 1515 m, the gross storage of the reservoir is 41.50 Mcum and area under submergence is 1.03 Km.

Proposed dam site for Kiru HEP

Proposed dam site for Kiru HEP(Source Kiru EIA Report)

 Kwar HEP envisages construction of a concrete gravity dam 101 m high from river bed across river Chenab at village Padyarna, four number intakes, four pressure shafts, an underground powerhouse to accommodate 4 units of 140 MW each and two number tail race tunnel. FRL of reservoir is proposed at EI 1385M. Gross storage of the reservoir at FRL is 27.167 Mcum. The reservoir will submerge an area of about 0.8 Sq. Km at FRL.

Proposed dam site for Kwar HEP

Proposed dam site for Kwar HEP (Source Kwar EIA Report)

 TOR non-compliance First and foremost glaring issue about the proposed projects is the non-compliance with the TORs (Terms of Reference) laid down for conducting the EIA. These TORs were granted by MoEF. We have listed here only an indicative list of non compliance below, not an exhaustive one.

Kiru HEP The TOR clearance letter was issued for Kiru project on Sept 9, 2008, the TORs are valid for a period of 3 years, but the project developer never came back for extension of the TOR on expiry of 3 year period and has come now for EC over 5.5 years after the TOR clearance. Thus the TOR clearance is no longer valid for Kiru HEP as per the law. Also originally the TOR clearance for Kiru was given for 600 MW installed capacity. The EIA however has been conducted for 660 MW capacity. No permission was sought by the PP for this increased capacity.

Kwar project has undergone several changes since the grant of TOR on 17 March 2010. Table given below compares some of these changes. First and foremost alteration has been in the proposed total power generation. While the TORs were granted for 520 MW the EIA has been conducted for 560 MW. Number of affected families goes up by 160% and project cost escalates by 29%. The TORs were granted for over four years back and the project authority never got back to EAC/MoEF for renewal of the TOR as other projects do. Thus the TORs granted originally do not remain valid in this case too.

Table 2: Changes in the scope of Kwar project after grant of TOR on 17 March 2010
Sr. No. Parameter Scope at the time of TOR clearance Current scope of the Proposed Project
1 Total power Generation 520MW 560 MW
2 Land requirement 5 Ha Government land 93.66 Ha Government land
3 Power House Units 4 x 130 MW (4 x 140MW)
4 Affected families 35 91
5 Project Cost Rs 3386.11 Cr Rs. 4375.50 Crores at Jan’2012 PL

Casual approach towards impact prediction

 Kwar EIA copy pasted from Kiru EIA report: It is evident that the EIA consultants have done nothing but copy paste job while preparing Kwar EIA report. At certain places Kwar report mentions ‘Kiru’ instead of Kwar. See for example point number 1.7 in Index of Kwar EIA mentions ‘Need of the Kiru HE project’ instead of Kwar and point number 4.4 mentions ‘Basin characteristics of free draining area of Kiru HEP’ (p.3 & p.6 of the document). Page 28 of Kwar EIA states that “The case for forest clearance of Kiru HE Project for diversion of 29.75 ha of forest land has been approved in the 81st meeting of J&K State Forest Advisory Committee (FAC) held on 09.12.2013…”

Other than very project specific figures, the entire text for both the reports is exactly the same. Impact prediction is the heart of an EIA study. However in Kwar EIA report an important chapter like Chapter 8- “Identification, Prediction and Evaluation of Environmental Impacts” is also copy pasted. The text of the chapter is same as that of Chapter 8 from Kiru EIA report save the project specific numbers and their description. The impacts predicted are vague and are conveniently kept the same in both the reports. It is clear that no real field work or application of mind is done. Such an EIA study defeats the basic purpose of conducting an EIA.

Impact of construction activities: The Kiru project involves a reservoir of live storage 10.5 MCM, a concrete dam on height (from river bed) 123.0 M & length 193 M, construction of 4 head race tunnels (of 7 m dia and 165 to 190 m length each) for discharging the water to an underground powerhouse of 4 units of 165 MW each. The project also envisages 33.4 Lakh CuM of construction material required from the project site.

The Kwar project involves construction of 101 m (above river bed)/ 109 m (above deepest foundation) high concrete gravity dam, Underground power house complex of four units of 140 MW each, Two concrete lined 9.5 m internal diameter main tailrace tunnels (having length of 2676 m and 2883 m) amongst several other features like four 5.65 m internal diameter main pressure shafts (each with a length of 108-182 m), etc. The project also envisages 38.36 Lakh CuM of construction material required from the project site.

View of Naigarh Nala Rock Quarry at Kwar Dam site

View of Naigarh Nala Rock Quarry at Kwar Dam site (Source Kwar EIA Report)

 All these activities will have significant impact on the geology and hydrology of the region. However no significant assessment or quantification of these impacts in terms of change in drainage patterns, springs in the project area, increased thereat of landslides, seismic activities has been carried out.

While talking about the impact of construction activities, the only impact of these two EIAs discussed in the chapter is ‘muck generation’. It does not mention impacts of tunneling and blasting involved in construction and also does not talk about its impact on fragile geology and hydrology of Himalayan region at all[6]. While talking about quarrying activities in the same chapter it states only two impacts viz. visual impacts and noise generation[7]. Impacts on landslides have been randomly dismissed stating that the sliding activity may not be significantly induced by project construction activities[8]. The reports trivialize the impacts on migratory fish Mahseer by stating that the upstream migration of this fish from the lower reached of the Chenab River have already been blocked by Salal and Baglihar, Dul Hasti dams. Thus they conclude that impact of this project on this fish species is not expected to be significant[9]. Option for fish ladder and fish lift has been ruled out for both the projects stating that it is not techno-economically feasible at the project site. Development of a hatchery at the project site has been proposed instead. The impact of the project on all the fish available in the river should have been assessed based on baseline assessment of the fisheries in Chenab River, which is not done. Secondly, there is no credible evidence to show that hatchery as a management option is useful or effective.

Left Bank slide for Kiru Project downstream of Ludrari Nala

Left Bank slide for Kiru Project downstream of Ludrari Nala (Source Kiru EIA Report)

 Right Bank slide for Kiru Project about 16 km downstream of Gulab Gargh

Right Bank slide for Kiru Project about 16 km downstream of Gulab Gargh (Source Kiru EIA Report)

 

The southern boundary of the Kishtwar National Park is approximately at an aerial distance of 11 km away from the proposed project, it is claimed, but this needs to be independently assessed. Also, just because it lies outside the boundary of study area which is radius of 10 KM, the EIA does not consider the impacts on this national park at all! EIA reports for both Kiru and Kwar HEPs simply state that the proposed activities shall have no impact on the National park[10].

Biodiversity at Kishwar National Park I

Biodiversity at Kishtwar National Park (Photo: Travel Places[11] & Beauty Spots of India[12])

 Several Important aspects of EIA are missing

No mention of free flowing river stretch: There is no mention of what is the flowing river stretch upstream and downstream of the project. As is clear from the EIA, the elevation difference between FRL of Kiru HEP (1515 m) and TWL of upstream Kirthan II (1526.5 m) is just 11.5 m. The elevation difference between TWL of Kiru HEP (1388 m) and FRL of downstream Kwar HEP (1385 m) is just 3 m. Similarly the elevation difference between TWL of Kwar HEP (1270 m) and FRL of downstream Hasti HEP (1264 m) is just 6 m. However, it is not clear what the flowing river lengths in all these locations are. Unless this length is assessed and is found to be adequate for river to regain its vitality, the project should not be considered and it should be asked to change the parameters.

Environmental Flows: The Kiru EIA report states that significant downstream impacts related to the water quality, fisheries, socio-economic and aquatic biodiversity are not foreseen since toe power house is proposed downstream of the dam and tail water level is EL 1388.52 m, discharge will be less only in a “very small stretch of about 800 m”. This seems to show the ignorance of the EIA consultants about how biodiversity in a flowing, lively river like Chenab survives.

Kwar EIA report states that the water entering the reservoir will be released back to river at a distance of 2.6 KM downstream. The report claims that though there in no human activity in this stretch of 2.6 KM the aquatic life will be definitely affected, as also terrestrial biodiversity, groundwater recharge, use of river and silt flow pattern.

10% of average of lean season discharge has been prescribed to be released through the dam gates as environmental flow for both the projects. This quantity has been calculated as 9.0 cumecs based on discharge data of the river. There is no mention of environmental flows in EMP. Firstly, this is even below the norms being followed by EAC and MoEF (30% in monsoon, 20% in lean season and 25% in rest, each at 90% dependability). Secondly, the amount of E-flow required needs to be arrived at based on actual assessment, but no such assessment has been done.

Impact of peaking generation not assessed: The reports talk about advantage of hydropower in terms of ability to providing peaking power. However, when a project operates as peaking station, there are severe impacts in the downstream and also upstream (rim stability). These impacts have not been assessed, nor is it assessed how the project will perform in the cascade development it is in.

Some other important aspects of impact assessment that report misses out on are:

  • Impact of the project on disaster potential in the project area as well in the downstream due to construction and also operation at various stages, say on landslides, flash floods, etc.
  • Social and Environmental Impacts of construction and operation of the coffer dams and diversion tunnels during construction phase are not included.
  • The reports do not even mention Climate Change.Impact of climate change on the project and impact of the project on the local climate has not been assessed. No mention or attempt has been made about or to assess the impact of green house gas emissions from the project.
  • Impacts on the flood characters of the river due to this dam, what will be the changes and how these will impact downstream areas.
  • Impact of changing silt flows downstream from desilting chamber and from silt flushing in monsoon on the downstream areas not analyzed. A detail account of how the silt from the dam would be flushed out annually and what would be the impact of this in the downstream as well as on the geo morphology, erosion, stability of structures etc was not done.
  • Options Assessment is missing, this is crucial part of the EIA to establish that among all options, including non project option, the given option is the least cost and best option.

Cumulative Impacts not assessed The EIA report gives list of Major hydroelectric projects executed /under execution/ under investigation so far in the basin in J&K which are a part of Cascade Development. Kirthan HE Project (990MW with proposed FRL at 1764 m and TWL at 1526.50m) which is yet to be commissioned is proposed upstream of Kiru (660 MW with FRL at 1515M). Downstream of Kiru is Kwar HE Project (560 MW with FRL at 1385 m and TWL at 1270 m) which is yet to be appraised and Dul Hasti HE Project (390 MW with FRL at 1264 m) which is commissioned.

Impoundment of Chenab at Dul Site

Impoundment of Chenab at Dul Site (Source: Kwar EIA Report)

 Moreover, the EIA does not provide the list of hydropower projects being taken up in Chenab basin in upstream Himachal Pradesh[13]. The cumulative impacts of all such projects will be huge.

The report summarizes cumulative impacts in single sentence: “The increased pressure will include uncontrolled logging, hunting of wildlife, non-timber forest product collection, livestock husbandry, the cultivation in forest areas and forest fires.”[14]

EIA report completely misses out on the detailed analysis of cumulative impacts in terms of

  • Impacts on flora, fauna, carrying capacity, livelihoods
  • Impact of reduction in adaptive capacity of the people and area to disasters in normal circumstance AND with climate change
  • Impacts on springs and drainage pattern
  • Disaster potential of the area
  • Tunneling and blasting
  • Geological disturbance caused
  • Seismic impacts
  • Carrying capacity

Inadequate Dam Break AnalysisThe Dam break analysis does not take into account the cumulative disaster potential including existing and proposed upstream and downstream projects. The EIA report also does not include cumulative disaster management plan.

Improper Public Hearing Public hearing conducted for both the projects were flawed. Excerpts from the speeches made by the officials from J&K State Pollution Control Board (SPCB) and CVPP that are noted in the public hearing report show that what these persons spoke was inappropriate, misleading and intimidating[15]. Also point wise responses to the issues raised by people at the Public Hearing are not provided in the EIA, as statutorily required. Hence even when people ask for Resettlement and Rehabilitation as per latest Act of 2013 (made effective from Jan 1, 2014), the EIA talks about National Resettlement and Rehabilitation Policy of 2007. The public hearing report strangely end for both projects with the officials asking those who are for the projects to raise their hands. There is no formal provision for voting for or against the project. Such public hearing should be declared null and void and fresh public hearing should be conducted.

Poor quality EIA reports that reflect pro hydro bias of the consultant EIA is the most effective tool to ensure environmental compliance in India. Needless to state that it is of critical importance. Casually predicted, unaddressed impacts and copy paste job of the Kiru and Kwar EIA reports once again highlights the poor quality of EIA reports submitted to the ministry for grant of EC. These reports decide fate of the project, of the people and environment surrounding the project site. Such quality of the report is most definitely not acceptable.

Further, an EIA report is an attempt to understand what are the adverse social and environmental impacts of a project and weather the impacts are acceptable, if the project is viable, optimal and desirable. The answer to this exercise can also include the answer that the project is not viable or desirable or acceptable. In view of this, the EIA consultant needs to be completely unbiased and should be ready to even conclude that the project is unacceptable. However, in case of the EIA consultant for the Kiru & Kwar HEP, EIA starts in very 1st chapter with a shockingly unscientific and biased statement: “Hydropower projects are dependable, renewable, economic, environmentally benign sources of energy with ability to stop and start instantaneously.” This statement is factually wrong on many counts (e.g. hydropower project is renewable or dependable or environmentally benign source of energy). It, along with whole para 1.2 also reflects the bias of the EIA consultants RS Envirolink Technologies Pvt Ltd (with Jammu University) and we urge the EAC and MoEF to reject such poor quality and biased EIAs and take other necessary steps to debar such agencies from doing any EIA or environmental studies in future.

CONCLUSION Looking at serious issues above, based on merit of the EIA reports, as well as complete cut-paste jobs, we are hopeful that the MoEF will not recommend EC for these projects. This case also highlights the importance of cumulative impact assessment in an over developed Himalayan basin. When the experience with Uttarakhand flood disaster of June 2013 is fresh, we hope that MoEF will not commit another blunder.

Amruta Pradhan, SANDRP

END NOTES:

 

[1]https://sandrp.wordpress.com/2013/07/01/pm-kick-starts-850-mw-ratle-project-in-jk-without-full-impact-assessment-invitation-to-another-disaster-in-chenab-basin/

[2]https://sandrp.in/hydropower/Dams_on_Chenab_How_many_are_too_many_Dec2012.pdf

[3]https://sandrp.wordpress.com/2014/04/29/report-of-expert-committee-on-uttarakhand-flood-disaster-role-of-heps-welcome-recommendations/

[4] Refer to SANDRP studies on Chenab

https://sandrp.wordpress.com/2013/07/01/pm-kick-starts-850-mw-ratle-project-in-jk-without-full-impact-assessment-invitation-to-another-disaster-in-chenab-basin/

https://sandrp.in/hydropower/Dams_on_Chenab_How_many_are_too_many_Dec2012.pdf

https://sandrp.wordpress.com/2014/05/06/massive-hydropower-capacity-being-developed-by-india-himalayas-cannot-take-this-onslought/

[5]https://sandrp.wordpress.com/2013/07/01/pm-kick-starts-850-mw-ratle-project-in-jk-without-full-impact-assessment-invitation-to-another-disaster-in-chenab-basin/

[6]p.291 of Kiru EIA Report & p.288 of Kwar EIA report

[7]p.293 of Kiru EIA Report & p.289 of Kwar EIA report

[8]p.298 of Kiru EIA Report & p.294 of Kwar EIA report

[9]p.307 of Kiru EIA Report & p.303 of Kwar EIA report

[10]p.221 of Kiru EIA Report & p.223 of Kwar EIA report

[11]http://www.4to40.com/travel/index.asp?p=Kishtwar_National_Park&state=Jammu_and_Kashmir

[12]http://beautyspotsofindia.com/kishtwar-national-park-jammu-kashmir/

[13] See for example: https://sandrp.in/basin_maps/Hydro_%20Electric_Projects_in_Chenab_River_Basin.pdf

[14]P. 306 of Kiru EIA

[15]The Public hearing report of Kiru says that Shri Sajjad Mufti, Regional Director of J&K SPCB said at the public hearing, “Construction of project should not deteriorate the environment….” This is a very strange, untruthful and inappropriate statement from J&K SPCB official. Why should the official be speaking at all at the public hearing and that too make such a statement that would also affect the atmosphere of the public hearing? Similarly the statement of GM of CVPP at the public hearing, “The most viable and cleanest of all (sources of power) is hydro power” was again, wrong, intimidating and inappropriate. The statement of Shri Khursheed Ahmed Butt of CVPP, “forest clearance has already been granted to the proposed project” is incorrect since the proposal for forest clearance for the project has not even come before FAC. Such public hearing should be declared null and void and fresh public hearing should be conducted.

The Public hearing report of Kwar says that the GM of CVPP said at the public hearing, “The best source of power generation is hydro power” was wrong, intimidating and inappropriate. The statement, “forest clearance has already been granted to the proposed project” is incorrect since the proposal for forest clearance for the project has not even come before FAC.

[16] See for details and link to PCA orders: https://sandrp.wordpress.com/2013/12/23/international-court-asks-india-to-release-more-water-and-rejects-plea-to-re-interpret-february-verdict-on-kishanganga/

Assam · brahmaputra · Embankments · Floods

Matmora (Assam) Geo-tube Embankment on Brahmaputra: State Glorifies, but No End to Peoples’ Sufferings after Three Years of Construction

The state of Assam in the northeastern India annually bears the brunt of floods and where embankment construction and repairing seems like permanent affair. Displacement of people living on the banks of rivers due to river bank erosion is another major issue here. The braiding and meandering river Brahmaputra and its tributaries continue to erode the banks rapidly. The Brahmaputra is well known for the rate in which it erodes. Among the places in the path of the river where the brunt of erosion has been felt severely include the following:

–        Rohmoria and Dibrugarh town in Dibrugarh district,
–        Matmora in Dhakukhana subdivsion of Lakhimpur district,
–        Majuli and Nimati Ghat in Jorhat district,
–        Lahorighat in Morigaon district and
–        Palashbari and Gumi in Kamrup district.

Map of areas taken up for erosion protection in Assam (Source– Assam 2011, A Development Perspective, published by Planning and Development Dept., Govt. of Assam)
Map of areas taken up for erosion protection in Assam. Source– Assam 2011, A Development Perspective, published by Planning and Development Dept., Govt. of Assam

SANDRP recently traveled to Matmora and Nimati ghat, two of these areas.

Bearing the Brunt of Erosion Silently Once a large village now only the name Matmora remains. Locals show us towards the middle of the river, to indicate where the village used to be. The rate of erosion is such that the Brahmaputra dyke from Sissikalghar to Tekeliphuta (popularly known as Sissi-Tekeliphuta dyke/embankment) takes the shape of a bow for nearly five kilometers at this place. From 2010, Matmora became very significant in the embankment history of India since country’s first embankment using geo-textile technology was constructed here. This was constructed at the bow shaped eroded line using geotextiles tubes. These tubes were filled up using water and sand from the banks of the river. This five kilometer embankment became a part of the Brahmaputra dyke from Sissikalghar to Tekeliphuta which is 13.9 km long. For the state government and Water Resources Department (WRD) of Assam, Matmora geotube embankment is a story of success of preventing floods and erosion. But what we saw in Matmora presents a different picture.

At Nimati Ghat, the river Brahmaputra is eroding its banks ferociously and people are intimidated by the river. A local person whose village used to be nearly two kilometers from the present bank line, told me, “Nothing can stop Baba Brahmaputra from claiming what he wants”. At Nimati Ghat, the Water Resources Department (WRD) is doing anti erosion work using geo-bags.

Funding for Embankments in Assam The total length of embankments in Assam is 4448 km as stated in a debate in the Legislative Assembly of Assam in 1998. Even though the present length of embankments is not known, it is very clear that the state of Assam continues to construct of newer embankments. In a recent analysis by SANDRP, it was found that the funds continue to increase for construction of embankments in the state. In five years from January 2009 to December 2013, the Advisory Committee in the Union Ministry of Water Resources for consideration of techno-economic viability of Irrigation, Flood Control and Multi-Purpose Project Proposals (TAC in short) had given clearance to projects worth Rs 1762.72 crores. A detailed list of these sanctioned projects can be found in Annexure 1 below.

Matmora Geo-tube embankment after its construction in 2010. Source– Assam 2011, A Development Perspective, published by Planning and Development Dept., Govt. of Assam.
Matmora Geo-tube embankment after its construction in 2010. Source– Assam 2011, A Development Perspective, published by Planning and Development Dept., Govt. of Assam.

Has Geo-tube been helpful for the people   Between January 2009 to December 2013, the Brahmaputra dyke from Sissikalghar to Tekeliphuta, was considered twice by the TAC. The committee in its 95th meeting on 20th January 2009 accepted the project titled “Raising and Strengthening to Brahmaputra dyke from Sissikalghar to Tekeliphuta including closing of breach by retirement and anti-erosion measures (to protect Majuli and Dhakukhana areas against flood devastation by the Brahmaputra, Lakhimpur district, Assam). The estimated cost of this project was Rs 142.42 crore and its project proposal envisaged – (i) Raising and strengthening of embankment for a length of 13.9 km, (ii) Construction of retirement bund with geo-textile tubes of length 5000 m. (iii) Construction of 2700 m long pilot channel.

Geo-tube embankment in Matmora, three years after construction. Photo: SANDRP.
Geo-tube embankment in Matmora, three years after construction. Photo: SANDRP.

Protection work of the same dyke was considered in the 117th meeting held on 21st March 2013 under the proposal for “Protection of Brahmaputra dyke from Sissikalghar to Tekeliphuta at different reaches from Lotasur to Tekeliphuta from the erosion of river Brahmaputra Assam.” The estimated cost of this project was Rs 155.87 crore. According to the minutes of 117th TAC meeting, the scheme envisaged “restoration of existing embankment in a length of 15300m at upstream and downstream of existing geo-tube dyke, Sand filled mattress in a length of 15604 m at river side slope, geo-tube apron length of 7204 m and Reinforced concrete porcupines as pro-siltation device at different reaches to prevent floods and erosion in Dhakukhana Civil sub-division of Lakhimpur district and Majuli sub-division of Jorhat district.” In the same minutes,while referring to the previous project proposal of 95th meeting the minutes stated that, it “was taken up primarily for closure of breach in the existing embankment including raising of embankment around the breach area only. The proposed works in the present scheme were in the same river reach and these would be required to protect the bank from further erosion and provide flood protection.”

This clearly shows that the geo-tube embankment in Matmora cannot be called a success. Government documents which showed that major part of the Brahmaputra dyke from Sissikalghar to Tekeliphuta remained vulnerable even after the construction of the geo-tube embankment. In fact submitting a proposal for the whole Sissi-Tekeliphuta embankment at first and later saying that the money was spent in constructing a smaller part of the embankment also raise questions. The time gap between the two proposals also raises questions. If the whole money from first proposal was to be spent in constructing only a part of the embankment, why was it not stated clearly in the first proposal? In fact, this was not stated in the first proposal and second proposal reflects that the first project failed to achieve the objectives. If the first proposal was indeed only for part of the embankment, why the proposal to strengthen the larger part of the embankment took 5 years to appear before the committee? The latter proposal also did not mention about the breach which swept away a large part of the Sissi-Tekeliphuta embankment from Jonmichuk to Amgiri Tapit under Sissikalghar and Jorkata village panchayat. According to the local people this breach occurred in the morning hours of 25th June 2012. The photo below shows the breach happened at the Jonmichuk end.

The breached area of 2012. This photo is taken from the new embankment and the lake formed at this spot can also be seen. Photo - SANDRP
The breached area of 2012. This photo is taken from the new embankment and the lake formed at this spot can also be seen. Photo – SANDRP

Jonminchuk area is nearly 15 km upstream of the geotube embankment in Matmora and part of the Sissi-Tekeliphuta embankment. A new embankment of nearly four kilometer long is being constructed at this place but the remnants of the old embankment still exist. The embankment was breached for nearly 3 kms and the water which entered the fields during that time could no longer go out and a large lake has been formed at this place, see the photo. It was surprising to see people living in the patches of the old embankment.

In the downstream, right from the point where the geo-tube embankment ends, the condition of the Sissi-Tekeliphuta embankment is pathetic. There were cracks in the embankment and water seepage has almost shattered the embankment. The embankment was in need of urgent repairs.

Condition of the Sissi-Tekelphuta embankment at the end point of the geo-tube embankment towards the village side. Photo - SANDRP
Condition of the Sissi-Tekelphuta embankment at the end point of the geo-tube embankment towards the village side. Photo – SANDRP
Sissi-Tekelphuta embankment at the same spot mentioned above towards the river side.  Photo - SANDRP
Sissi-Tekelphuta embankment at the same spot mentioned above towards the river side. Photo – SANDRP

Besides, one does not have to travel far to find erosion in the downstream of the geo-tube embankment. After travelling, less than three kilometers from the end point of the geo-tube embankment, rapid erosion was observed at the place where the Matmora and Tekeliphuta ghats join, due to low water level. This joint ghat is more than a kilometer from the toe line of Sissi-Tekeliphuta embankment but seeing the rapidity of the erosion the locals opine that the river would reach the toe of the embankment within this monsoon. It was difficult to believe that the river can erode so fast, until a young man pointed towards a black line in the middle of the river and said that that area which now seemed to be char/sand bar used to be his village three years back. He with his family now live beside the embankment. In this ghat we also witnessed that spurs constructed from the embankment inside the river, mainly to divert the flow of water, have been eroded as well.

The Spur has also been eroded. Photo - SANDRP
The Spur has also been eroded. Photo – SANDRP
Erosion at Matmora-Tekeliphuta Ghat. Photo - SANDRP
Erosion at Matmora-Tekeliphuta Ghat. Photo – SANDRP

It is also important to note that protection of Majuli from floods was one of the main aims of the geo-tube embankment project, but there were reports of devastating floods affecting Majuli in 2012 & 2013.

After geo-tube comes geo bags With the construction of geo-tube embankments being hailed as a success by the state government, construction of embankments using geo-bags followed. Geo-bags are smaller than geo-tubes and come at a cheaper cost. Embankments on many rivers were constructed using geo-bags which were also used for erosion protection. But effectiveness of the geo-bags as protective measure to flood and erosion, still remains disputed. A news report titled “ADB, river engineers differ on geo-bags” published in Assam Tribune on 9th September 2010 reported about the difference of opinion among the water resource engineers of Assam and powerful lobby of the Asian Development Bank (ADB) for the use of geo-bags to resist Brahmaputra erosion in Palasbari-Gumi and Dibrugarh. Referring to the engineers the news report stated “They have alleged that the ADB provided 23,000 geo-bags for an experiment. They were dumped in the month of September 2009 at a 150-metre-long selected erosion-prone reach at Gumi for testing their efficacy. But, a diving observation made in the month of December 2009, suggested that the bags were not launched uniformly in a single layer as it was claimed. They were found lying in a haphazard manner in staggered heaps with gaps in between and the total distance they covered was only about 8 metres, against the claimed and required 35 metres…..The ADB then carried out another diving observation at Gumi in May last (2010) and found no bag at the site. The State WRD did not get any feedback from the ADB on this issue.”

Work of piling up the geo-bags is going on in Nimati Ghat. Photo - SANDRP
Work of piling up the geo-bags is going on in Nimati Ghat. Photo – SANDRP
Status of the geo-bags put last year. Photo - SANDRP
Status of the geo-bags put last year. Photo – SANDRP
The spot where not a single Geo-bag was seen.  Photo - SANDRP
The spot where not a single Geo-bag was seen. Photo – SANDRP

Nimati Ghat was the other place which SANDRP visited to find out the effectiveness of geo-bags. The work of piling up the geo-bags for erosion protection was going on when SANDRP visited the area in the second week of April 2014. The bags which were used previously for the same purpose were seen to be mostly lying in water in shattered condition. Locals told us that majority of the bags are now under water. In the eroded bank line, these geo-bags were lying without any order and in a way suggesting how the river has dealt or to say played with these jumbo bags. In this bank line, there was a stretch of nearly five meters where the river has eroded more than the other parts. At this stretch none of the geo-bags were to be seen.

There were also contradictions regarding when the present erosion protection work at Nimati ghat had started. Some of the shopkeepers of the ghat said that the work of putting up geo-bags started in February 2014. But according to the contractor in charge of the work, the work started in November 2013. Construction or repairing of embankment just few months before the advent of monsoons is one of the constant criticisms, leveled against the Water Resources department of the state and in Nimati too we heard the same complaint.

Is Geo-tube really a ‘permanent solution’ to floods? In the present discourse of floods in Assam this has become a very significant question. The local people have been fed with various information about geo-tube and most of which are wrong. The life of embankment constructed using geo-tube is of 100 years, we were told by the locals when we travelled to the upstream areas of Matmora geo-tube. This is absolutely not true. In fact, for Prof Chandan Mahanta of IIT Guwahati the scouring[1] done by the river Brahmaputra will be the major cause of concern for geo-tube embankments in the long run.

The geo-tube embankment has already faced threat of scouring right after its construction in the monsoons of 2011. It was on the morning of 14th July, 2011 when two of the apron tubes at the tail of the embankment, were launched due to increase force of water. The apron tubes were laid at the toe of the geo-tube embankment and with the increased force of water scoured at the bottom by the embankment toe line. WRD engineers flung into action and immediate repairing work was taken up at the site. According to WRD engineers this had happened because the trees which were  left outside the  embankment  had  obstructed  and  increased  the  force  of  water and they were immediately cut down. Concrete porcupines were also thrown into the water. Asomiya Pratidin, a regional newspaper reported this on that day but thereafter no report on this could be found. The incident was almost forgotten. When we visited the geo-tube embankment, it was observed that along the toe-line of the embankment a scour line runs for substantial length of the embankment. This clearly shows that scouring by the river has increased in this area. The news report published in Assam Tribune [2]also points out a significant problem associated with geo-bags – “The lobby is mounting pressure for use of geo-bags in the form of bank revetment. Bank revetment is generally not adopted in Brahmaputra because of many reasons. Most important of them is – it produces a permanent deep channel along the existing riverbank.”

On the issue of lobbying behind geo-tube, an interesting perspective was provided by activist-researcher Keshoba Krishna Chatradhara who coordinates ‘Peoples’ Movement for Subansiri and Brahmaputra Valley (PMSBV)’. He opines that the construction of geo-tube embankment in Matmora was an experiment, done to see whether such embankments can withstand the flood and erosion of Brahmaputra. The reason for choosing Matmora first and not other severe erosion affected places like Dibrugarh or Rohmoria, was because even if the embankment fails it won’t be as significant loss for the state compared to those places. Dibrugarh is one of the most important towns of upper Assam with a glorious history whereas Rohmoria became important for the state when Oil India Limited found oil deposits in Khagorijan[3]. Infact several local people and activists also opined that the Sissi-Tekeliphuta embankment which is on the north bank of the river was cut several times, to save the areas in the upstream south bank, mainly the Dibrugarh town. They said that in the past, before the geo-tube embankment came, whenever there was any news of water rising in Dibrugarh, there would soon be a breach in Sissi-tekeliphuta embankment. In fact considering these breaches in the larger Sissi-tekeliphuta embankment, Mr. Chatradhara opined that even if the geo-tube embankment survives the flood, erosion and breaches in future, it might become a small island in midst of a submerged land as there will surely be breaches in the rest of the Sissi-Tekeliphuta embankment.

ADB loan for Geo-textile Embankments in Assam After the construction of the geo-tube embankment at Matmora, the state government is leaving no stone unturned to make it sound like a glorious success. But it is surprising to know that, even before the Matmora embankment was commissioned in December 2010, the state government have filed proposal for two more embankment project where geo-textile would be used for construction and got it cleared. The two subprojects of Assam Integrated Flood River Bank Erosion Risk Management Project (AIFRERM) in Dibrugarh and Palashbari were cleared in the 106th meeting of TAC held on 16th September 2010. It is important to note that for the total AIFRERM project ADB is giving a loan of $56.9 million. The cost of Dibrugarh and Palashbari subprojects are Rs 61.33 crore and Rs 129.49 crore respectively. But these investments have been cleared without even doing a post-construction impact assessment of Matmora geo-textile embankment. The Palashbari subproject also included erosion protection for Gumi area through the use of geo-bags but the Assam Tribune report quoted above already mentioned about how geo-bags scheme has failed in that area.

It is important to note here that, the first geo-tube embankment has been constructed only three years back and it would be premature to give any verdict of success, on the contrary there are many signs of failure. But the state government of Assam and the Assam Water Resources department are claiming it as success without really any credible basis and than have used that self certification to go on building more embankments using geo-textile and in several occasions these plans have failed. They first should have done a detailed impact assessment of the embankment at Matmora before going on building more embankments of the same nature.

It seems the Assam government, ADB and CWC are pushing these projects to deflect attention from the failure of embankments in flood management. Such attempts won’t succeed, but it is possibly a ploy to prolong the use of embankments as a flood management technique.

Parag Jyoti Saikia (meandering1800@gmail.com)

Annexure 1

Flood and Erosion Projects approved for Assam – 2009 to 2013

TAC meeting no & date Project Appr. year River/ Basin L of Emba. (m) Original (revised) Cost-CrRs Benefitting area (Ha) Decision
95th -20.01.2009 Protection of Sialmari Area from the erosion of Brahmputra 2002 Brahmaputra NA 14.29 (25.73) NA Accepted
Protection of Bhojaikhati, Doligaon and Ulubari area from the erosion 2002 Brahmaputra NA 14.52 (27.92) NA Accepted
Raising & strengthening Brahmputra Dyke from from Sissikalghar to Tekeliphuta including closing of breach by retirement and anti erosion measures New Brahmaputra NA 142.42 NA Accepted
96th -16.02.2009 Flood protection of Majuli Island from Flood and Erosion Ph-II & III New Brahmaputra NA 115.03 NA Accepted
Restoration of Dibang & Lohit rivers to their original courses at Dholla Hattiguli New Brahmaputra NA 23.32 (53.11) NA Accepted partly & suggested that proposal of coffer dam, pilot channel, etc. to be put up for expert opinion
101st -30.11.2009 Raising and strengthening to Puthimari embankment New Brahmaputra NA 30.23 15000 Accepted
Anti Erosion measures to protect Brahmputra Dyke on left bank New Brahmaputra NA 27.97 5000 Accepted
Protection of Gakhirkhitee & adjoining areas from erosion New Brahmaputra NA 19.06 20,000 Accepted
102 -28.1.’10 Emergent measures for protection of Rohmoria in Dibrugarh District New Brahmaputra NA 59.91 18,000 Accepted
106th -16.09.2010 Raising and strengthening of tributary dyke along both banks of Kopili River New Kopilli/ Brahmputra NA 110.72 NA Accepted
Assam Integrated Flood River Bank Erosion Risk Management Project New Brahmaputra NA 61.33 NA Accepted
Assam Integrated Flood River Bank Erosion Risk Management Project New Brahmaputra NA 129.49 NA Accepted
110th – 20.07.2011 Protection of Majuli from Flood and Erosion Ph II & III 2011 Brahmaputra 115.03 Accepted
Restoration fo rivers Dibang & Lohit to their original courses at Dholla Hatighuli 2011 Brahmaputra 54.43 Accepted
111th – 17.08.2011 Protection of Biswanath Panpur including areas of upstream Silamari and Far downstream Bhumuraguri to Borgaon against erosion New Brahmaputra 167.09 Accepted
117 – 21.3.’13 Protecion of Sissi-Tekeliphuta dyke from erosion – Lotasur to Tekeliphuta New Brahmaputra 153000 m 155.87 153000 m Accepted
118th – 30.07.2013 Flood management of Dikrong along with river training works on both banks embankment New Dikrong/Brahmaputra 105.96 Accepted
Flood management of Ranganadi along with river training works on both bank embankments New Ranganadi/Brahmaputra 361.42 Accepted

[1] Scour can be termed as a specific form of the more general term erosion. In case of geo-tube embankments Scour is the removal of sediment from the bottom of the geo-tubes. Scour, caused by swiftly moving water, can scoop out scour holes, compromising the integrity of a structure.

[2] ADB, river engineers differ on geo-bags – http://www.assamtribune.com/scripts/detailsnew.asp?id=jun2410/at08

[3] See ‘Rohmoria’s Challenge: Natural Disasters, Popular Protests and State Apathy’ published in Economic and Political Weekly, Vol XLVI NO 2, Janurary 8, 2011.

Himalayas · Hydropower · Hydropower Performance

Massive Hydropower capacity being developed by India: Himalayas cannot take this onslaught

At least 49 large[1] hydropower projects are under construction in India today, with a cumulative capacity of 15006 MW[2]. As per the latest bulletin from Central Electricity Authority[3], “Status of Hydro Electric Projects under Execution for 12th Plan & beyond (Excluding projects above[4] 25 MW)” dated March 31, 2014, 35 of these projects (9934 MW) are expected to be commissioned in 12th Five Year Plan[5] and remaining 14 with installed capacity of 5072 MW would provide benefit beyond 12th Plan.

Considering that 1534 MW capacity has already been added in first two years of ongoing 12th Five Year Plan (during 2012-13 and 2013-14), CEA projections means that India hopes to add massive 11468 MW capacity during the current five year plan. This will be higher than capacity added in any other five year plan and 254% of the capacity addition during the last, 11th Five Year Plan (2007-12) when India added 4514 MW. The graph below shows how steeply our hydropower installed capacity is going up over the last 25 years.

 

Rapidly Increasing installed capacity of Large Hydropower Projects in India
Rapidly Increasing installed capacity of Large Hydropower Projects in India

The proponent of even more accelerated hydro capacity addition misleadingly talk about the need for having 40% of installed grid capacity as hydro.

In line with this, the CEA came out with plans to add 65000 MW in 13th Five Year Plan (2017-2022: 30 000 MW) and 14th Five Year Plan (2022-2027: 35 000 MW). (see http://www.energylineindia.com/ of May 6, 2014)

There is no science behind this  advocacy. It is basically a suggestion possibly based on the general assumption that peaking demand is 40% higher than base-load demand. Hence if we have 40% installed capacity from hydro in the grid, this can take care of total demand optimally. However, this is based on assumption that hydro capacity is indeed used for peaking. This assumption is completely wrong in India, with no agency monitoring or even reporting how much of the hydro generation currently provide peaking power. Without such optimum use of current hydro capacity, where is the case for 60:40 grid capacity ratio for hydro? It goes without saying that when hydro projects are used for peaking power, there are additional social and  environmental impacts in the downstream and upstream. These need to assessed and those who suffer are compensated.

On similar lines, one can answer the advocacy for claim that hydro is clean, green, renewable and cheap source of power or that  run of the river or small hydropower projects are more environmentally benign. However, this blog is not attempting to answer all such fallacies here, it needs a separate blog.

While this is happening, the Expert Appraisal Committee of Union Ministry of Environment and Forests on River Valley Projects has been clearing projects at break a neck speed with almost zero rejection rate. Between April 2007 and Dec 2013, this committee recommended environment clearance to 18030.5 MW capacity, most of which has not entered the implementation stage. Moreover, this committee has recommended 1st Environment clearance (what is technically called Terms of Reference Clearance) for a capacity of unimaginable 57702 MW in the same period. This is indicative of the onslaught of hydropower projects which we are likely to see in the coming years.

Figure 1 TORs (First Stage EC) and EC recommended by EAC between April 2007 - December 2013
Figure 1 TORs (First Stage EC) and EC recommended by EAC between April 2007 – December 2013

 Table: Sector-wise & plan-wise number of & capacity of under construction HEPs

Sector

During 12th FYP

After 12th Plan

Total

No of Projects Installed capacity, MW No of Projects Installed capacity, MW No of Projects Installed capacity, MW
Central

11[6]

5312 3 2615 14

7927

State

12

1506 3 736 15

2242

Pvt

12

3116 8 1721 20

4837

Total

35

9934 14 5072 49

15006

Among the three sectors, the largest number of under construction projects (20) are from private sector. However, among all sectors of under construction projects, central sector projects have the highest installed capacity (7927 or 53% of under construction capacity of 15006 MW).

Figure 2 Sectorwise ownership of under-construction HEPs in Numbers
Figure 2 Sectorwise ownership of under-construction HEPs in Numbers

Vulnerable Himalayas are the target In the second table the state-wise and sector-wise break of numbers and capacity of under construction HEPs has been given. Himachal Pradesh has the highest number and highest installed capacity projects among all states. That state also has the highest installed capacity (8139 MW or over a fifth of operating HEP capacity at national level) of large operating hydropower projects. Sikkim, however, has the highest number and capacity of private sector hydropower projects under construction. In fact, half of the total national-level private sector projects which are under construction are in that tiny state. Their installed capacity is more than half the installed capacity of all the private sector hydropower projects under construction at national level. Ironically, the state also has the highest biodiversity in the country.

Figure 3 Installed Capacity of under construction HEPs, sector-wise ownership, in MW
Figure 3 Installed Capacity of under construction HEPs, sector-wise ownership, in MW

Himachal Pradesh and Uttarakhand also have 5 and 3 private sector HEPs under construction respectively. The 5 Himalayan states of Jammu & Kashmir (J&K), Himachal Pradesh, Uttarakhand, Sikkim and Arunachal Pradesh between them have 38 of the 49 under construction hydropower projects with total capacity of 13550 MW or over 90% of under construction capacity. In addition, the projects of Mizoram, Meghalaya, W Bengal (Teesta L Dam IV) and Punjab (Shahpur Kandi on Ravi River) are also in Himalayan zone.

Table: State-wise & sector-wise number and capacity of under-construction HEPs

State

Central Sector

State Sector Private Sector

Total

No of projects Installed Capacity, MW No of projects Installed Capacity, MW No of projects Installed Capacity, MW No of projects Installed Capacity, MW
J&K

1

330 1 450 1 850 3

1630

Himachal P

4

2532 6 956 5 460 15

3948

Uttarakhand

4

2135 3 505 7

2640

Sikkim

10 2622 10

2622

Arunachal P

3

2710 3

2710

Mizoram

1

60 1

60

Meghalaya

1 40 1

40

W Bengal

1

160 1

160

Punjab

1 206 1

206

Madhya Pr

1 400 1

400

Maharashtra

1 80 1

80

Andhra Pr

3 410 3

410

Kerala

2 100 2

100

Total

14

7927 15 2242 20 4837 49

15006

 

Figure 4 State-wise and sector-wise number of HEPs under construction
Figure 4 State-wise and sector-wise number of HEPs under construction
Figure 5 State-wise installed capacity of under construciotn HEPs
Figure 5 State-wise installed capacity of under construciotn HEPs

Diminishing Returns This blind rush for hydropower projects (which have serious and irreversible impacts on social and ecological systems) is difficult to understand and justify considering their poor generation performance, rising costs and availability of better options. To illustrate, in the graph below we can see how power generation per unit (MW) installed capacity has been steadily reducing over the last two decades. From 1993-94 to the latest year of 2013-14, there has been a huge drop of 16.5%.

Diminishing power generation from India's Hydropower Projects over the last two decades
Diminishing power generation from India’s Hydropower Projects over the last two decades

Yawning gap between promised and actual generation of Hydro Projects Another way to look at performance of hydropower projects would be to compare the projected (as promised in Techno Economic Clearance) and actual generation (both at 90% dependability) of electricity by HEPs. This assessment shows that about 89% of India’s operating hydropower projects are generating at below the promised levels. Shockingly, half of under performing projects are generating at below 50% of promised generation levels.

How much Peaking Power are we generating? A third way to assess the hydropower generation is in terms of peaking power, a USP[7] of hydropower projects. However, no figures are available as to how much of the generation from hydropower projects are happening during peaking hours. No agency in India is even monitoring this or reporting this: including CEA, Central or State Electricity Regulatory Authority, National, Regional or State Load Dispatch Centers, Union or state Power Ministries or individual operators. In short, there is no case for justifying more hydro in the name of providing peaking power if we are neither monitoring nor optimizing hydropower generation during peaking hours. One expected CEA to do this job, but it seems they are busy lobbying for hydropower projects rather than functioning as India’s premier Technical Power sector agency.

Invitation to disaster? The consequences of such massive capacity addition are and will continue to be disastrous for the rivers, forests, biodiversity and people. The Uttarakhand disaster of June 2013 has shown the vulnerability of hydropower projects in Himalayas, as well as their impacts. The disaster and independent reports[8] also show how the construction and operation of these projects have contributed to compounding the proportion of the disaster. Climate Change is accentuating this situation and will continue to do so with increasing intensity as per the IPCC reports.

Role  of HEPs in Uttarakhand disaster: CEA and CWC in denial mode This analysis of under construction hydropower projects as reported in the latest CEA bulletin shows that Himalayas is the target for overwhelming majority of hydropower projects being taken up India (& neighbouring countries like Bhutan, Nepal, Pakistan and Tibet). The Uttarakhand disaster showed how hydropower projects are increasing the existing vulnerabilities and disaster potential of the Himalayan region in times of natural calamities. An independent committee appointed by MoEF following Supreme Court orders of Aug 13, 2013 pointed out the role of hydropower projects in Uttarakhad disaster of June 2013.

It should be highlighted here that multiple hydropower projects should invite cumulative impact assessment. As Supreme Court order of Aug 13, 2013 highlighted, such cumulative impact assessment need to be done in a credible way and not the way AHEC of IITR did for the Bhagirathi-Alaknanda basin.

Strangely, instead of accepting this reality and taking this into account in decision making processes, Central Water Commission and Central Electricity Authority are in a denial mode! They collectively submitted a completely unscientific and unfounded report to Union Environment & Forests Ministry, advocating for hydropower projects rather than assessing their role in disaster, which was the mandate given by Supreme Court of India to MoEF. The CEA is clearly jeopardizing whatever credibility it has in joining hands with CWC. It would be better for both the agencies to accept and wake up to these realities.

Else, such onslaught of hydropower projects on Himalayas is likely to be an invitation to further disasters all across the Himalayas. All our decision makers and all others concerned need to take note of this urgently.

Himanshu Thakkar (ht.sandrp@gmail.com)

END NOTES:

[1] Defined as those projects having installed capacity above 25 MW

[2] In reality, there are many other large HEPs under construction, but his figure is based on CEA.

[3] http://cea.nic.in/reports/proj_mon/status_he_execution.pdf, CEA has been pretty irregular in putting up these bulletins, after Nov 2013, the next bulletin was available only now.

[4] In reality, this should be “below”, we have italicized the word since the error is in the original.

[5] Ending on March 31, 2017

[6] CEA projects that out of 2000 MW installed capacity of Lower Subansiri HEP in Arunachal Pradesh, 1000 MW will be commissioned in 12th Plan and the rest of 1000 MW thereafter.

[7] Unique Selling Proposition

[8] https://sandrp.wordpress.com/2014/04/29/report-of-expert-committee-on-uttarakhand-flood-disaster-role-of-heps-welcome-recommendations/

Madhya Pradesh · Narmada

Why is This Dam being constructed? Is this not an example of Big Dam Fundamentalism?

Imagine that a state government wants to build a Big Dam, with height of 31.75 m on a Big River. The River has already seen a large number of dams, agitations, controversies and legal disputes.

This dam is going to cost several hundred crores of rupees, just the initial civil works’ cost is Rs 299.43 Crores[1] out of approved construction cost (alone) of Rs 438.18 Crores[2].

But this dam will not provide any irrigation. Not supply any water to anyone. Will not do any flood control. Will not be a net generator of power. In short it can claim none of the benefits that a standard dam project claims.

And yet it will have fairly serious impacts. Hundreds of hectares of fertile, useful land will be destroyed. River itself and biodiversity of the river will be destroyed. In the downstream too there will be huge adverse impacts. Hundreds of tribal families will be adversely affected. Almost all of them have been affected by an upstream dam project. The government has refused to answer any of their concerns. The people are already agitated and have declared their opposition[3],[4] and have also legally challenged the project.

However, we do not know full social or environmental impacts of the dam, since such an impact assessment has never been done. The work on this project according to the government started in Feb 2013. Any such dam project would require impact assessment, management plan, public hearings, environmental appraisal, clearance, monitoring and compliance mechanism. But this one had none of it and does not want to do any of it! It does not have even a Rehabilitation Plan. Not even one on paper, as most such plans are.

Majority of the purported benefits of the project are supposed to legally go to another state, but that state has said it does not want the dam, nor does it want to share costs or benefits. And still the state government has started work on the dam.

We are used to telling a lot of bad dam stories. But this one seems to be a unique one.

Why does the state government want to build this dam? What are the benefits and for whom? Why is the Union Environment Ministry allowing such an illegal dam? Is this not dam fundamentalism?

Ok, enough of mystery. Let us understand what this project is about.

Garudeshwar Dam This story is about Garudeshwar dam[5] on Narmada River in Bharuch district in Gujarat. With height of 31.75 m, it is a major dam, since any dam above 15 m height is considered big dam by national and international definitions. The Garudeshwar Dam will create a huge 12 km long reservoir.

Ongoing work at Garudeshwar Dam site. Photo: SANDRP
Ongoing work at Garudeshwar Dam site. Photo: SANDRP
Sardar Sarovar Dam in the upstream of Garudeshwar dam. Photo - SANDRP
Sardar Sarovar Dam in the upstream of Garudeshwar dam. Photo – SANDRP
Map of Garudeshwar dam  affected area. It also shows the Sardar Sarovar on right side.  Photo: SANDRP
Map of Garudeshwar dam affected area. It also shows the Sardar Sarovar on right side. Photo: SANDRP

It is proposed just downstream from the most controversial Sardar Sarovar Dam Project (SSP). The SSP is being constructed under the Narmada Water Disputes Tribunal Award of 1979. The Garudeshwar Dam is proposed as part of the power component of the SSP, to act as downstream storage when the 1200 MW River Bed Power House (RBPH) of SSP will act in a Pump Storage Supply (PSS) mode. This means that Garudeshwar Dam’s basic function is to store the water released from RBPH during peak hour power generation. This water stored in the Garudeshwar dam is then to be pumped back to the SSP reservoir during off peak hours. Pumping the water back to the reservoir typically takes about 20% more power. This is in comparison with the power generated when a unit of water was released from the upstream dam (SSP in this case) during generation mode. It means that Garudeshwar Dam will be net consumer of electricity. This kind of project could have economic viability when there is additional tariff for power available during peak hours, which is not the case today. In absence of such valuation, such projects are not even economically viable.

According to the NWDT award, Madhya Pradesh gets majority, or 57% share in the power benefits (and costs) from SSP, Maharashtra gets 27% and Gujarat 16%.

Another objective of the Garudeshwar Dam[6] is to create a reservoir surrounding Statue of Unity, being propagated as the world’s highest statue on a small island 3 km downstream of the SSP Dam.

None of the required Statutory clearances obtained The minutes of the 80th meeting of SSCAC (Sardar Sarovar Construction Advisory Committee, the statutory interstate body to coordinate construction of SSP, it is chaired by Secretary, Union Ministry of Water Resources and includes senior officials of Gujarat, Madhya Pradesh, Maharashtra and Rajasthan, in addition to Narmada Control Authority) held in March 2013 notes on the issue of Garudeshwar Dam, “The work to be taken up by GOG in compliance of all statutory clearances. The committee accordingly directed GOG to take further follow up actions.” It was no secret to SSCAC that GOG had taken no clearances, how could then SSCAC wash its hands off with such a statement?

As per Supreme Court Order of Oct 2000 (Narmada Bachao Andolan vs Union of India and Others), as also earlier statutory orders under NWDT, the sanction of Rehabilitation Sub Group and Environment Sub Group of Narmada Control Authority is to be obtained prior to every stage of work related to SSP. No such sanction has been obtained by these authorities. In fact, as per letter written by Shekhar Singh, a member of ESG of NCA on March 24, 2013, there has not even been impact assessment of the Garudeshwar Dam, which is necessary before ESG can consider clearing the work on Garudeshwar work:

“Garudeshwar weir, to be built 12 km downstream of the SSP dam with a live storage capacity of 32.9 Million Cubic Meters is a component of the Sardar Sarovar Project, as was envisaged by the Narmada Water Disputes Tribunal Award of 1979. However, as far as I recollect, the environmental and social impacts of construction and operation of Garudeshwar weir (GW) have never been brought before the ESG of NCA. In my estimation, the construction and operation of the GW will have significant social and environmental impacts, since it will entail a reservoir of about 12 km in length and unknown width and submergence area. The weir will have the potential of affecting the fisheries in the immediately surrounding areas and also of affecting the downstream river and its biodiversity, and other related aspects. This is especially because the weir will control the flow of water and silt downstream. However, I do not know whether there has been a comprehensive assessment of the environmental and social impacts of the GW and its contribution to the cumulative impact of all the projects and activities in the area. And if there has been, I do not believe that this has been put up to the ESG for its approval.”

River Narmada from Indravarna village which will be affected due to  construction of Garudeshwar dam. The map on the ground speaks volumes about locked between two dams and a river in reality.
River Narmada from Indravarna village which will be affected due to construction of Garudeshwar dam. This image speaks volumes about Narmada, the river in reality and the river locked between two dams as there in the map. Photo: SANDRP

Similarly, since it is a work under SSP, the R&R policy of SSP is suppose to apply to the people affected by the Garudeshwar Dam. This also means that a R&R Plan have to be prepared and consent of the affected people taken and R&R completed a year before the construction work, which too has not been done, nor a sanction of RSG of NCA taken.

The reservoir upstream of the Sardar Sarovar Dam has been declared eco sensitive zone and protected area. The Garudeshwar Dam will create a reservoir that will be affecting the river close to the SSP Dam and thus will be within the eco sensitive zone and legally, such a work requires clearance from National Board of Wildlife, but such a clearance has not been taken.

Since Garudeshwar Dam is proposed in tribal area, consent of the gram sabhas is also legally required. No such consents have been taken.

Thus, the work that has been going on is completely illegal.

State benefiting the most, questions need for the Garudeshwar Dam Official documents obtained by SANDRP under RTI Act shows that GoMP has repeatedly shown their disagreement with the need for Garudeshwar Dam. Here are a few instances from official records. Strangely, in spite of this clear disagreement from a majority beneficiary state, the decision to go ahead with the project was taken by Gujarat and endorsed by SSCAC. The other statutory bodies like the Narmada Control Authority and its Environment Sub Group and Rehabilitation Sub Group were not even consulted.

  • June 2011 The minutes of the 101st meeting of the PSC of SSCAC held in June 2011 noted, “Summing up the discussion the Chairman observed that the extent of disagreement is now so acute that the very need of Garudeshwar Weir is being questioned.”
  • July 2011 The events thereafter moved rapidly. Following a request letter of GOG on July 21st, 2011, Secretary to Union Water Resources Ministry (also chairman of SSCAC and NCA) called a meeting of participating states on 25th July, 2011. At this meeting, Madhya Pradesh continued its disagreement with the need for the Garudeshwar weir, as recorded in the minutes of the meeting[7], providing reasons of their opposition: “The representative from Govt of MP also informed the stand of their government on the construction of the said weir mentioning that State of Madhya Pradesh will become surplus in power by the year 2014 and as such, Madhya Pradesh may not like to avail such a costly peak power. According to their calculations, the tariff for peak power may be more than Rs 6 per unit. In view of this, State of Madhya Pradesh is not in the favour of the proposal of the Garudeshwar Weir requiring the sharing of the cost of construction and the energy required for reversible operations.”
  • The response of the Secretary (MoWR) was strange[8], “GOMP to review their stand of surrendering their share of peak hour power generation by reversible operation on RBPH machines and confirm about the same for further course of action.”
  • The fact that GOG and Union Govt (even as opposite parties were ruling the state and the centre, showing amazing collusion of pro dam fundamentalism) were so much hand in glove that the secretary, brushing aside the objections of the majority beneficiary state of MP, decided to push unwanted dam down the unwilling state’s throat: “Secretary (MOWR) while concluding the meeting, stated that the construction of Garudeshwar Weir needs to be taken up urgently & completed expeditiously…”.
  • March 2012 The Government of Madhya Pradesh (GoMP) pointed out in their letter dated 21.03.2012 to SSCAC[9]), “there is no mention about Garudeshwar Weir in the NWDT Award”.
  • The GoMP also made it clear in this letter that GoMP does not concur with the proposal in view of “the change in power tariff scenario”.
  • Aug 2012: The 104th meeting of PSC of SSCAC records on this agenda Item no 104-5, “The representative of GOMP conveyed that, at this stage, they don’t agree with above decision and a note of dissent in this regard will be sent soon.”

So the state that was supposed to get 57% benefits and also pay same proportion of costs, has refused to concur with the scheme.

Status of work According to the Agenda notes for the 81st meeting of SSCAC held on March 28, 2014, till Dec 2013, 6.88% of excavation was the only physical progress on the Garudeshwar weir. Financial Progress achieved was even less, at 3.19%.

Some recent Developments:

  • Oct 2013 The affected people and eminent Gujarat citizens write to MoEF and GOG[10] to immediately stop illegal work on Garudeshwar Dam. Affected people and their leaders were put under house arrest when Chief Minister and former Deputy PM L K Advani came to the Kevadia Colony to lay foundation stone for the proposed Statue of Unity.
  • Jan 3, 2014 Gujarat Government[11] is considering use of force to suppress the movement against the illegal work on Garudeshwar Dam.
  • Jan 27, 2014 Tribal women of 70 villages to be affected by the Garudeshwar dam go to the site of ongoing work and ask the contractor to stop the work as it is illegal, without necessary clearances, impact assessments and consents.

    Women leading the protest against Garudeshwar Dam. Photo: http://www.counterview.net/
    Women leading the protest against Garudeshwar Dam. Photo: http://www.counterview.net/
  • Jan 31, 2014 National Green Tribunal order (Lakhan Musafir & Anr Vs. Sardar Sarovar Narmada Nigam Ltd and others – Application 10/2013 WZ): “We deem it proper to grant three (3) weeks time to Respondent No.1 to file reply affidavit and make it clear that in the meanwhile if any work done, it will be subject to final outcome of the present Application, without claiming any right of equity arising out of execution of construction work and without pleadings in advance of any ‘fait Accompli’.
  • Feb 25, 2014 NGT order: “Learned Additional Advocate General, seeks time to file comprehensive reply affidavit, as regards the nature of project in question. He submits that filing of such affidavit requires co-ordination of various departments and Agencies, which will take certain time. He, therefore, seeks reasonable time to complete the exercise of preparing reply affidavit. He undertakes to maintain directions as regards keeping of equity, in the light of earlier order dated 31st January, 2014.” The application next comes up for hearing on May 9, 2014.
  • April 1, 2014 People of 70 villages affected by Garudeshwar Dam hold protest demonstration in Vadodara.
  • April 14, 2014 Blasting at Garudeshwar village for the dam leads to rock fall on people, endangering lives of children and also shaking of houses.
A milestone on the way to Sardar Sarovar, with the dam in the background. Photo: SANDRP
A milestone on the way to Sardar Sarovar, with the dam in the background. Photo: SANDRP

Conclusion It is clear that Garudeshwar Dam does not have any justification, any impact assessment study, any required statutory clearances, any consents from affected Gram Sabhas and or even from the state which is supposed to get majority of the questionable claimed benefits. This dam seems like a symbol of Gujarat Government’s dam fundamentalism.

The reason as to why the Union Ministry of Environment and Forests is not taking action against this illegal work or why the Union Water Resources Ministry is supporting the work or why the political opposition in Gujarat is silent on this dam is still a mystery. However, under the current circumstances, the project must be stopped immediately. We hope NGT takes this step urgently. It is high time that political parties fighting elections in the area and Gujarat take a stand on this dam immediately.

Himanshu Thakkar (ht.sandrp@gmail.com)

END NOTES:
_________________________________

[1] “The letter of acceptance-cum-work order for the construction of Garudeshwar Weir across river Narmada near village Garudeshwar has been issued to agency M/s Rithwik Project Pvt Ltd, Hyderabad by SSNNL, Gandhinagar vide letter No. CPC/ Garudeshwar Weir/ 2011/657-P-II dated 04.05.2012”, as per Minutes of 104th meeting of PSC of SSCAC held on Aug 23, 2012.

[2] Minutes of 104th meeting of Permanent Standing Committee of SSCAC held on Aug 23, 2012, obtained by SANDRP under RTI.

[3] That the officials knew about the opposition is clear from the Gujarat Samachar clipping of Oct 22, 2012, carrying warning from affected people that if their issues are not settled, the work on the dam will be stopped. This clipping was included in the agenda notes for the 80th meeting of SSCAC held on March 25, 2013.

[4] The minutes of the 105th meeting of the PSC of SSCAC held in Feb 2013 noted on the issue of Garudeshwar dam, “The representative of GOG informed that work is delayed due to objection of the local peoples for giving better R&R package”.

[5] Calling is weir is clearly an attempt to mislead everyone, giving an impression that is a low dam, which it is not.

[6] http://archive.indianexpress.com/news/garudeshwar-weir-could-pave-way-for-sardar-statue/776013/

[7] Annexure 79.2(C).5 with the Agenda for 79th meeting of SSCAC held in Feb 2012

[8] Agenda of the 79th meeting of SSCAC held in Feb 2012.

[9] Obtained by SANDRP under RTI Act.

[10] http://www.business-standard.com/article/pti-stories/tribal-body-demands-scrapping-of-garudeshwar-weir-113102901241_1.html

[11] http://www.counterview.net/2014/01/government-now-considering-to-use-force.html

Maharashtra

El Nino and Maharashtra: Lets dig the Well before we are thirsty

2012-13 was described by the Maharashtra government as the worst drought in the state since 1972. Weather scientists are predicting that conditions are fast developing that seems like a repeat of 2012. The Reserve Bank of India has already warned the states about the possibility of El Nino and be ready for the worse. Maharashtra could take several steps to be ready for this developing situation, including using its available water storage in reservoirs around the state prudently.

Yes, it’s that time of the year again when we need to be alert to weather predictions and reservoir storages. Especially for Maharashtra. At this time last year, following poor 2012 monsoon, many of the bigger reservoirs were at 0% live storage for months (Ujani, Jayakwadi, several projects in Marathwada, etc). A satisfactory monsoon 2013 and some small contribution from the ill-fated hailstorms has resulted in better status of Maharashtra reservoirs storages at this point in time.

However, Maharashtra (like the country) needs to be extra cautious with using the available resources. Several institutes and bodies like Skymet, Buraeu of Meteorology, Australia, National Weather Service USA, etc. are predicting a strong possibility of El Nino effect this year, which generally results in poor monsoons.  Sky met is specifically saying that this year may be a repeat of 2012 poor monsoons. The report also states that Vidarbha, Marathwada and Central Maharashtra, could face monsoon deficit.[1] Bureau of Meteorology, Australia has issued notice stating a 70% or more chance of El Nino this year. They state “Although the El Niño–Southern Oscillation (ENSO) is currently neutral, surface and sub-surface ocean temperatures have warmed considerably in recent weeks, consistent with a state of rapid transition. International climate models surveyed by the Bureau indicate continued warming of the central Pacific Ocean in coming months. Most models predict sea surface temperatures will reach El Niño thresholds during the coming season.”[2] A similar prediction has been made by US agency National Oceanic and Atmospheric Administration’s Climate Prediction Centre.[3] While some weather scientists are saying that we should not panic and wait for IMD’s (India Meteorological Department) official forecast on April 25 and the next one in June, however, it would certainly be useful to be careful from now onwards.[4]

According to the latest Central Water Commission (CWC) Reservoir bulletin of 090414 regarding water levels in 85 selected major reservoirs in India, the 12 major reservoirs of Maharashtra have a combined storage of 4.471 BCM (Billion Cubic Meters) which is still good 38.73% of live storage capacity of 11.544 BCM.  This is down from 6.522 BCM (over 50%) on Feb 6, 2014. It is not clear where this huge 2 BCM water has been used up in these two months.

However, Maharashtra is indeed lucky to have this 4.471 BCM water in 12 major reservoirs[5] at this time. We need to use this prudently in view of the forecast that situation similar to what prevailed in 2012 when Maharashtra experienced bad drought could get repeated in coming monsoon. Government needs to take advance steps to ensure that storage capacity is not frittered away and there is less land under water intensive sugarcane and such other crops. Media, civil society and independent observers need to be vigilant in this regard to ensure that mistakes of 2012 are not repeated and available resources are used wisely.

In terms of wise water management and effective use of available reservoir storage, waiting for June IMD forecast will be much too late. It will be wiser if water management is cautious starting from now. At this time, already some regions are facing water scarcity.

Maharashtra farmers are already in dire states due to 2012 drought followed by hailstorms and the disastrous impacts of extreme weather events in 2014. Another drought possibility is bad news, but impacts can be reduced with wise planning and prudent advance steps. Maharashtra Water Resources Department Website[6] provides further details about storage position. Let us look at basin-wise water storage position.

Godavari Basin

Marathwada: In Marathwada, the overall live storage is 31% on 17th April 2014, including Major, Medium and Minor storages. However, this gives a misleading picture as many dams with better storages (like Vishnupuri) are placed at the end of the basin.

Dams like Manjra, Lower Terna and Seena Kolegao are already at 0 live storage, while Jayakwadi is at 15% (It was at 0%, along with six other dams of Marathwada even before this time last year).

In the upstream of Godavari Basin, Kadwa sub basin is showing severe water scarcity already. The region consists of premier onion and grape growing belt of Maharashtra, as well as wine processing centre. The chronically drought affected town of Manmad lies here and last year, it received water after 51 days in March from the upstream Palkhed Dam.[7] Surprisingly, Palkhed is currently at 5% Live Storage, when this time last year it was at 19% live storage. Water releases from Palkhed were extremely contentious last year. This year with even lesser storage, things may flare up again and wise water management, curb on non-essential uses (in dry period) like wine industry, preventing siphoning water from canals for cash crops, etc., needs to be observed to avoid stress in coming two months or more. Kadwa Dam shows a dipping live storage at 2%, while Nilwande Dam in downstream Ahmednagar shows just 3% against 7% last year.

Vidarbha shows a better picture at 58% live storage, Lowest being Bagh Kalisarar inn Bhandar at zero live storage. Now this project, though in heavy rainfall region of Bhandara has been at 0 live storage since January for the past 6 years! Either the information about the project is incorrect, or the dam has serious issues which need urgent attention.

Krishna-Bhima Basin

Ujani which was at 110% LS earlier this year after many years because of the monsoon in 2013 is now showing LS of 22% on April 17.[8] Two irrigation rotations have been released from the dam. It was reported that last rotation was used up largely by sugarcane,[9] leaving little for other crops. Ujani was at sub-zero storage (-39%) at this time last year. According to that standard, it has a good storage now, which should be used very cautiously. Solapur has added several new sugar factories this year, in addition to the 28 factories and the area under sugarcane has increased tremendously because of good rainfall.[10] Keeping the possibility of a weak monsoon in 2014, water to sugarcane must be controlled and curtailed, else we will see a repeat of 2013, only on a larger scale.

1920 MW Koyana Hydropower Project: Surprisingly in Koyana, the reservoir level this year is worse off than last year at the same time, which is not the case for any other Maharashtra reservoir in CWC bulletin. While this year it is at 30%, last year it was at 47% as on April 9.

Falling Groundwater tables: Recent GSDA report[11] has warned that groundwater levels in more than 2700 villages in Maharashtra has fallen below 1 meter than the average levels in the past 5 years. This is definitely alarming as groundwater is the water lifeline of rural Maharashtra. Out of the 2700 villages, levels in nearly 1200 villages have fallen below two or even three meters (for 497 villages).

Sugarcane: Area under sugarcane has increased in Maharashtra following good rains in 2013. This cane will demand more water in its lifecycle in farm and also for crushing. Agricultural Minister of India too did not find it appropriate to curb the wide spread plantation of sugarcane in drought prone areas even when national and global sugar prices were falling.It is estimated that current year may see more than 10,00,000 hectares of sugarcane which will demand water.The government has not even taken its own promise of enforcing drip to sugarcane.

There seem to be turbulent times ahead and it will be advisable if water management in Maharashtra tightens up to respond to upcoming challenges. The fact that there is useful water storage in some reservoirs and that warning is available in advance could be blessings if necessary steps are taken.

Parineeta Dandekar, parineeta.dandekar@gmail.com

Himanshu Thakkar, ht.sandrp@gmail.com

 

 

END NOTES:

 

[1] http://www.skymet.net/

[2] http://www.bom.gov.au/climate/enso/

[3] http://www.cpc.ncep.noaa.gov/products/expert_assessment/sdo_discussion.html

[4] http://www.downtoearth.org.in/content/el-nino-may-disrupt-monsoons

[5] These 12 reservoir include: Jayakwadi, Ujani, Koyna, Khadakwasla, Isapur, Mula, Yeldari, Girna, Upper Vaitarna, Upper Tapi, Pench and Upper Wardha.

[6] http://mahawrd.org/default.htm

[7] http://www.thehindu.com/todays-paper/tp-national/tp-newdelhi/a-drop-in-the-bucket/article4560869.ece

[8] http://www.agrowon.com/Agrowon/20140415/5237052667319190169.htm

[9] http://www.agrowon.com/Agrowon/20140415/5237052667319190169.htm

[10] https://sandrp.in/Sugarcane_and_Drought_in_Solapur_june2013.pdf

[11] http://www.esakal.com/esakal/20140416/4977647275092496415.htm

Climate Change · Maharashtra

Maharashtra State Action Plan on Climate change: Farmers Suffer, State and consultant TERI unaffected

Even as rural areas in otherwise-drought hit Maharashtra (as also in neighbouring areas of Karnataka, Madhya Pradesh and Chhattisgarh) are trying to cope with the immense damages due to untimely rain and hailstorms in Feb-March 2014, the IPCC Assessment Report 5 by Working Group II warns that extreme weather events may increase in their frequency. This was also supported by the IPCC Special Report on Extreme Events in 2012.

Sr NoEventDate
1NAPCC made publicJune 30, 2008
2Mah state council on CC formed by a GRSept 2008
3Work awarded to TERI “to assess Climate Change Vulnerability and Adaptation Strategies for Maharashtra State and to prepare a Climate Change Adaptation Action Plan for the State” at the cost of Rs 98 lakhs; to include six case studiesAug 20, 2009
4Maharashtra govt order regarding TERI (6 members in addition to Dr Pachauri and Dr Leeana Srivastava as advisors) given above task, along with Met office, Hadley Centre, UK (2 members) and formation of state coordination committee for this under the chairmanship of Chief SecretaryNov 26, 2009
5Dept of Environment conducted decision makers workshop CC adaptation and mitigationFeb 24-25, 2011
6State advisory committee on CC created with chief minister as chairJuly 8, 2011
7First meeting of State advisory committee on CCFeb 2013
8Meeting (latest) held on draft climate change action plan with Chief Secy in chairOct 7, 2013
9Mah Env department gives RTI response to SANDRP: “The final action plan on climate change is not yet submitted by TERI to Govt of Maharashtra”Apr 2, 2014

Back to back in two years, Maharashtra faced a drought (in 2012-13), touted to be worst in past 40 years, to a hail and rain event which broke records of past hundred years (and perhaps even more) several times over. Studies are pointing out that the coastal region and the traditionally drought-affected part of Marathwada and Vidarbha is specifically vulnerable to climate change.

Drought 2013. Photo: Mint
Drought 2013. Photo: Mint

It is also highlighted by the IPCC reports, experienced painfully by Maharashtra that: “Risks are unevenly distributed and are generally greater for disadvantaged people and communities in countries at all levels of development.”

So how prepared is Maharashtra to face, adapt to and mitigate the challenges put forth?

Information obtained by SANDRP under RTI underlines the fact that respective governments have given no priority, time or importance to consider climate change or its impacts on societies and ecosystems.

The Maharashtra State Council on Climate change was formed in Sept 2008 by a GR, its Chairperson was the then Chief Minister and included ministers from Agriculture, Water resources, Industries, etc. This Council awarded work related to State Action Plan on Climate Change to TERI on 20th Aug 2009 and TERI was supposed to complete this Study in two years,  that is by Aug 2011.

More than four and a half years latter, TERI has still not completed the report on State Action Plan on Climate change and Government of Maharashtra does not seem too bothered by it.

The process by which TERI was given the task of doing the SAPCC also seems inappropriate. The process is described in Maharashtra government order of Nov 16, 2009, where there is no mention of any competitive bidding. The order says that Dr RK Pachauri of TERI was  asked to make a presentation on climate change in Maharashtra, based on which it was decided to give the task of preparing the SAPCC to TERI and Met Office, UK at the cost of Rs 98 lakhs. This is clearly inappropriate process.

It’s been 5 years since the National Action Plan on Climate Change (NAPCC) was made public in June 2008. NAPCC itself was formulated in non-transparent, non-participatory way by Prime Minister’s Council on Climate Change.  Several States have submitted and are working towards their Action Plans.

In Feb 2011, Chief Minister Prithviraj Chavan announced Advisory committee on Climate change similar to PM’s council on CC. However, the Government Resolution for the State Council on CC came only on 8th July 2011. Some its  current 19  members include Chief Minister (chair), Deputy Chief Minister,  Ministers of Environment, Agriculture, Water resources, Rural Development, Chief Secretary, Secy-Environment, etc. Some Expert members include Sunita Narain, Jamshed Godrej, Anu Agha, Dr. R.K. Pachauri, Dr. R. A. Mashelkar, Dr. Anil Kakodkar and Ajay Mathur from Bureau of Energy Efficiency.

The Terms of Reference of the Committee indicate the following duties:

(a) To evaluate the study being done by TERI in the State and recommend strategies. (Emphasis added)

(b) Provide an oversight to the State Government in the drafting an action plan to combat climate change;

(c) To ensure a co-ordinated response to all issues relating to climate change.

This council was to meet “at least twice a year to review situation on CC and adaptation strategy” as per the GR. It has met just once in last 33 months.

After giving contract to TERI in 2009, announcing State Council on CC in 2011, the first and only meeting of the State Council on Climate Change happened only in Feb 2013! Minutes of the meeting claim that final report from TERI is expected in March 2013. However, there was no discussion on this important report or even a discussion to hasten the formulation and implementation of this report. Strangely, TERI and MET Office UK had already published a note on the Action Plan in 2012[1] itself, when the State Action Plan is still not final even today!

There is also issue of conflict of interest here: when TERI is given the task of preparing Maharashtra SAPCC, how can Dr. Pachauri, who heads TERI be on the State Council to oversee the preparation of SAPCC? Secondly, Dr. Pachauri is a member of PM’s Council on Climate Change, which recommends state action plans and then his own organisation, TERI is awarded the work to prepare the action plan for Maharashtra. Is not there a conflict of interest here?

Moreover, Sunita Narain and Dr. Pachauri are also members of PM’s Council on Climate Change and having seen the performance of PMCCC in bringing out business as usual NAPCC in non-transparent, non-participatory way. The state government should have appointed independent members who have knowledge of the state.

The minutes of the first meeting of the state council seem to suggest that the meeting had rather unfocused discussions. The meeting had interesting conclusion: “All the members Council were of the opinion that the implementation of the existing schemes/ plans need to be focused on climate change adaptation strategies and did not encourage going in for further studies.” In spite of such a clear conclusion, we see neither the state action plan in place, nor adaptation of the existing schemes/ plans with the climate change implications in Maharashtra. In fact, Sunita Narian was also member of the Kasturirangan committee on Western Ghats, but we see no effective reflection of climate change concerns in the conclusions of the Kasturirangan committee.

The Chief Minister said in conclusion, “Providing income support to farmers was of utmost importance to the Government. A special “Climate Change Cell” would be established in the state to focus on climate change issues”. There is no evidence of functioning of any such cell, more than a year after that meeting.

There have been some meetings of High Powered Committee on climate changed, headed by Chief Secretary, the latest meeting happed on Oct 7, 2013.

The minutes of the Oct 2013 meeting notes, “The officers of the disaster management department were attending the meeting for the first time, which according to the Chief Secretary was not very useful given that they do not have any background in the subject area as well as the previous discussions.” Considering how important is the role of disaster management in climate change context, this callousness of disaster management department seems disturbing. The minutes also noted the need for additional Rs 40 lakhs to get run off (hydrology) data.

The minutes of the meeting ends with this conclusion: “Chief Secretary instructed TERI, to finish the consultations with respective departments for validations of data and finalise the recommendations within a month time, post which the presentation could be made before the cabinet.” However, that was in Oct 2013, but even in April 2014, there is no sign of the State Action Plan on Climate Change, an exercise that has dragged on for over 4 and half years now.

While all this has been going on without any conclusion, action plan or implementation of any necessary actions, the millions of the vulnerable people of the state are suffering and more than 20 farmers have committed suicide in the face of inconsolable loss.

The State Action Plan on Climate change is not a magic wand that will cure all ills. It is, however, one of the indicators of the seriousness and intent of our administration in tackling the real and grave challenges. Right now, there seems to be no seriousness and no intent.

 Parineeta Dandekar (parineeta.dandekar@gmail.com),
Himanshu Thakkar (ht.sandrp@gmail.com)

END NOTES:

[1] http://www.metoffice.gov.uk/media/pdf/c/a/GOM_brochure_for_web.pdf

2. https://sandrp.wordpress.com/2014/03/11/maharashtra-farmers-face-impacts-of-hailstorms-and-states-inaction-plan-on-climate-change/

3. https://sandrp.wordpress.com/2014/04/03/dams-are-not-climate-friendly-readings-from-ipcc-wg-ii-report/

4. VERY TRAGIC story of how hailstorms have hit poor farmers in Marathawada in Maharashtra: http://www.livemint.com/Specials/jkcra6zQqMShlFJjzmvXeN/Death-and-despair-in-hailstormhit-Marathwada.html