Analysis of MoEF’s EAC on River Valley Projects
Introduction Following the implementation of EIA notification of Sept 2006, the Ministry of Environment & forest (MoEF) has constituted different committees for the appraisal of various developmental projects including River Valley & Hydroelectric projects. The committees are called as Expert Appraisal Committees (EAC). The EAC for River Valley & Hydroelectric projects has had 63 meetings till date from the date of constitution of Committee in April 2007 to the latest meeting in Dec 2012. The committee generally recommends for any River Valley projects, at first stage the Terms of Reference (TOR) for the Environment Impact Assessment (EIA) to be carried out for the proposals along with permission for pre construction activities or works related to survey and investigation.
Figure 1: Stage 1 clearance figures across India
Model TOR The MoEF has also put up what the Ministry calls “Model TOR for River Valley and Hydroelectric Projects”, but when you click on the link[1], it opens into a document that is titled, “Model TOR for Hydropower Projects”, it does not even claim to be a model TOR for any other river valley projects. This is a big lacuna, since over 95% of India’s large dams are irrigation projects[2], not hydropower projects. Moreover, substantial proportion of the projects coming before the EAC is irrigation projects, including river linking projects. Not having a Model TOR for such projects is a big gap. This does not mean that the Model TOR given on the MoEF website is adequate or comprehensive. Only to illustrate, the Model TOR does not look into the impacts of the various integral components of the hydropower projects like colonies, roads, mining, blasting etc that the hydropower projects invariably have. Model TOR does not look at the social, environmental, economic or cultural services that a river provides. On downstream impacts, the model TOR says under Impact Prediction, “Downstream impact on water, land & human environment due to drying up of the river in the stretch between dam site and powerhouse site.” This completely negates the impacts that the project would have either on the upstream or in the river downstream from the power site or along the tributaries both upstream and downstream of the projects. Nor does it mean that these grossly inadequate Model TOR is followed by the developers. Even the ministry or the EAC does not bother to check if the EIA submitted to them follows either the specific TOR given to the project or the Model TOR on the MoEF website.
Environment Clearance At the next stage, the EAC considers the projects for the Environment Clearance (EC), at this stage the EIA is supposed to have been conducted as per the approved TOR and the public hearing is also supposed to have been conducted as per the norms set in the EIA notification of Sept 2006. The EIA notification is issued under the Environment Protection Act, 1986. We have tried to analyse the recommendations of the EAC from the minutes of 63 meetings for the period April 2007 to Dec 2012.
The EAC members The reconstituted EAC in April 2007 was headed by Shri P Abraham, former Power Secretary. Over the years, EAC included members like Dr Sanchita Jindal, Dr A R Yousuf, Dr OP Sisodia, Dr Dinesh Kr Alva, Dr. Dulal Goswami, Prof D K Paul, Dr (Mrs) Usha Bhat, Dr Bithin Datta, Dr Pushpam Kumar, Dr. Devendra Pandey (chairman of EAC from Aug 2009 to April 2010, current Chairman took over as chairman during 38th meeting held on June 30, 2010), none of them are members of the EAC for RVP currently. The member representing Central Water Commission in the EAC included R K Khanna, R K Singh, N Mukherjee but has been changing over the years and full list of their names is not available. Shri P Abraham resigned following our letter to the then Union Minister of State for Environment and Forests (Independent Charge) Shri Jairam Ramesh, showing the conflict of interests involved in he being on the board of a number of hydropower companies whose projects came up for clearance before the EAC chaired by him.
The current composition of EAC for RVP is as follows (as per MEF website[3] as on Jan 30, 2013):
S.No. |
Name & Address |
Role in Committee |
1 |
Shri. Rakesh Nath, C-1/29, Bapa Nagar New Delhi-110 003 |
Chairman |
2 |
Dr. B.P Das, 717 Saheed Nagar Bhubaneswar -751007 |
Vice-Chairman |
3 |
Dr .A. K. Bhattacharya, Flat No-805,Pocket-3,Akshardham Apt. sec-19 Dwarka New Delhi-110075 |
Member |
4 |
Chief Engineer(Hydrology), Central Water Commission, Sewa Bhawan, R.K. Puram,New Delhi-110 066 |
Member |
5 |
Dr. Jyoti Kumar Sharma, Professor School of Environment & Natural Resources 14/15, Old Survey road Dehradun-248 001 Uttrakhand |
Member |
6 |
Dr. K.D. Joshi, Principal Scientist and Head Central Inland Fisheries Research Institute Regional Centre Allahabad Uttar Pradesh |
Member |
7 |
Dr. Praveen Mathur, Associate Professor & Head Department of Environmental Science P-5, Professor’s Colony MDS University Campus Ajmer-305 009 Rajasthan |
Member |
8 |
Dr. S Bhowmik, 40 C, Pocket 1, Sector 10, Dwarka, New Delhi |
Member |
9 |
Dr. Surendra kumar Mishra, Department of Water Resources, Development & Management, Indian Institute of Technology, Roorkee – 247667 |
Member |
10 |
Dr. (Mrs.) Maitreyee Choudhary, Professor & Director, Centre for Himalayan Studies, University of North- Bengal, W.B. |
Member |
11 |
Prof. (Dr.) Dhananjai Mohan, Wildlife Institute of India, Dehradun, 248 001 Uttarakhand |
Member |
12 |
Prof. Arun Kumar, Department of Earth Sciences, Manipur University, Imphal, 795003, Manipur. |
Member |
13 |
Prof. S. K. Mazumdar, 242, FF, Sidharth Enclave Ashram Chowk New Delhi-110 014 |
Member |
14 |
Sh. B B Barman, MOEF, Paryavaran Bhavan, New Delhi |
Member Secretary |
In addition to the above, Dr P V Subba Rao (Scientist from MoEF) is listed as EAC member in the minutes of the meetings. Interestingly, he, Dr B P Das and Dr A K Bhattacharya seem to be constant members of the EAC throughout the period under study.
Role of MoEF All the comments about the EAC here apply equally to the Union Ministry of Environment and Forests as two officials of the ministry have always been part of the EAC, including the member secretary of the EAC. In fact MoEF has a greater role in selection of the chairman and members of the EAC, deciding what projects should be put on the agenda, what happens after the EAC recommendations, ensuring that all the required information about the projects on the agenda is available and is in public domain, encouraging EAC to invite to EAC meetings individuals and groups who have written to EAC and MoEF on substantial aspects, and otherwise setting the policies and norms for the EAC and projects. The MoEF performance has been pathetic. Even now it’s not possible to even know the status of the clearances of the projects from the MoEF website, even though it is statutory requirement for MoEF (under EIA notification 2006) to display the clearance letters on its website. In Feb 2012 Central Information Commission (CIC) directed MoEF under the Right to Information Act 2005 to put all the documents submitted by the project developers for clearance, at least ten days before the projects are considered by the EAC. When this was not followed, SANDRP wrote to CIC and CIC issued notice to MoEF. This is still to be followed by MoEF fully. Now some of the documents are put up on the website before the EAC meetings, this is not the case even for the 63rd and 64th meetings of EAC. The EAC, in spite of repeatedly writing to them on this violation of the CIC directions, did not take steps to ensure that CIC directions are fully complied with for the projects that come up before the EAC.
Even though MoEF may be equally if not more responsible for the various violations listed here, that does not reduce the responsibility of the EAC members. Once someone is selected as EAC member, he or she has the duty to ensure basic norms in functioning of the EAC. Evidence presented here shows if the EAC members have succeeded in achieving even basic norms in governance of EAC.
Results and Analysis
The Union Ministry of Environment and Forests’ (MoEF) Expert Appraisal Committee (EAC) on River Valley and Hydroelectric Projects (RVP) has considered a total of 262 hydropower and irrigation projects in close to six years since April 2007 when the new committee was set up to its latest, 63rd meeting in December 2012. It has not rejected any project in this period. Even in case of the two projects that it declined to recommend clearance for the Terms of Reference (TOR) of their Environment Impact Assessment (EIA), it has basically asked the developers to come back with reformulated proposals. It seems the committee is actually an Expert Approval Committee, since it seems to have expertise in approving rather than appraising the projects objectively.
EAC has strong pro project and anti people bias The Committee has shown its strong bias for the projects. Many groups from all over India have sent hundreds of submissions to the EAC over these years. The committee has never called any of the groups for the meetings where the specific projects on which groups have sent submissions. The EAC has never even acknowledged any of such submissions in the minutes of the meetings. In case of some of the recent submissions from SANDRP and others, the chairman of the EAC wrote back saying that this will be discussed in the next meeting, but there has been no mention of such submissions in the minutes of the EAC meetings. The EAC has shown its strong bias against people, environment and all those who represent the interests of the local communities and environment. In February 2012 some of us were invited for a discussion with the EAC, but we saw little impact of our discussions on the functioning of the EAC.
Opposition to Dams on Teesta, many of which are cleared by the EAC Photo: Affected Citizens of Teesta
The table below gives an overview of the situation of TORC (Terms of Reference Clearance) and EC (Environment Clearance) for the projects cleared by the EAC on RVP between April 2007 (when the then newly constituted EAC met for the first time) to its 63rd meeting as in December 2012. The table shows that the EAC has not rejected any of the projects for EC. As against the 211 projects considered by the EAC for TORC, it (only temporarily) rejected TORC for two projects. Hence its rejection rate for TORC is less than 1%. EAC’s rejection rate of environment clearance is nil as it has never rejected any project that has come to it for environment clearance. It seems the EAC for RVP has been basically rubber stamping approval for every project that comes their way. The EAC was expected to do much better than that, as it clear from the reading of EIA notification of Sept 2006, following which the EAC was set up.
Overview of Clearance status across India
Region |
Projects for TORC |
Projects for EC |
Total projects considered |
||||
TORC given |
TORC Rejected |
Projects considered for TORC |
EC given |
EC rejected |
Projects considered for EC |
||
North |
50 |
1 (300 MW) |
57 |
31 |
0 |
34 |
72 |
North East |
70 |
1 (420 MW) |
87 |
17 |
0 |
19 |
99 |
East |
10 |
0 |
13 |
7 |
0 |
8 |
20 |
West |
28 |
0 |
39 |
14 |
0 |
17 |
49 |
South |
7 |
0 |
14 |
6 |
0 |
8 |
22 |
Total |
165 |
2 |
210 |
75 |
0 |
86 |
262 |
Temporary rejections for two TORC Only two projects were rejected TORC. Among these, for the 420 MW Kameng Dam, the EAC rejected the proposal from KSK Ltd, since the submergence area was just 350 m from Pakke Tiger Reserve. The EAC however, said, “The Committee suggested that possibilities of locating a suitable site on Kameng River, upstream of confluence of Bichom & Kameng may be explored.” So the project is likely to come back to EAC. It is surprising, however, that another project in the same basin, namely the 1120 MW Kameng I on Bhareli / Kameng River in East Kameng district in Arunachal Pradesh came before the EAC during its first meeting in April 2007. The minutes of the EAC meeting clearly says about this project, “A part of the submergence area falls under the Pakke Tiger Reserve.” And yet the EAC gave TOR clearance to the project! Inconsistency seems to be the first name of the EAC.
Similarly the 200 MW Bara Bangahal HEP in Kangra district in Himachal Pradesh was accorded TOR clearance in 21st meeting of EAC in Dec 2008, even as the minutes recorded, “The project is located within the wildlife sanctuary.” Similarly the 76 MW Rambara project on Mandakini River in Rudraprayag district in Uttarakhand, just 6 km from Kedarnath, was given TOR approval in the 19th EAC meeting in Oct 2008 even as the minutes noted, “The whole project is located within Kedarnath Musk Deer Sanctuary.”
Thousands of Monks opposing dams in Tawang, Arunachal cleared by the EAC Photo: Seven Sisters Post
Similarly while rejecting the TORC for the 300 MW Purthi HEP in Lahaul and Spiti District in Himachal Pradesh, the EAC said, “The Committee concluded that the project proponent and Govt. of Himachal Pradesh may review and revise the proposal in the light of the above observations for reconsideration.” So it is clear in this case too that the rejection is temporary. In reality, the EAC has rejected none of the projects that came to it for clearance.
Massive hydropower capacity cleared The EAC for RVP basically considers hydropower projects having installed capacity over 50 MW, projects of 25-50 MW going to the state Environment Impact Assessment Authorities and those below or requiring any environment clearance under EIA notification 2006. The table below shows that in less than 6 years, the EAC has recommended TORC for hydropower projects proposed with installed capacity of 49458 MW, which is about 25% more than what India has installed in about 66 years since independence.
Status of clearance for Hydropower Projects
Region |
Capacity for which TORC given, MW |
Capacity for which EC given, MW |
Capacity of projects considered, MW |
North |
12823 |
6843.5 |
18087.5 |
North East |
31541 |
8258 |
46658 |
East |
3434 |
120 |
3684 |
West |
1320 |
– |
1586 |
South |
340 |
863 |
2178 |
Total |
49458 |
16084.5 |
72193.5 |
Figure 2: Zone wise status of Environment Clearance
During the period, the EAC has recommended EC for hydropower capacity of 16084.5 MW, which is about three times the hydro capacity of 5544 MW added during the just concluded 11th five year Plan. EAC has recommended all these clearances without giving any consideration to carrying capacity, cumulative impact assessment, democratic decision making, sustainable development criteria, full and proper social and environment impact assessment or desirability of such capacity addition, including from climate change perspective.
Opposition to 775 MW Luhri Project cleared recently by EAC Photo: Himdhara
Zero rejection for irrigation projects The EAC for RVP considers irrigation projects with Cultivable Command Area (CCA) above 10 000 Ha. In the table below are the region wise details of the TORC and EC recommended by EAC for the Cultivable Command Area figures of the major and medium irrigation projects.
During the period under study (Apr 2007 to Dec 2012), EAC has given TORC for 3.28 million ha of CCA and EC for 1.59 million Ha of CCA. Here we should note that since 1991-92, there has been no addition to the net area irrigated by major and medium irrigation projects at all India level as per Govt of India figures[4]. In light of that fact and considering the overcapacity already built into a number of basins across India already, such clearances by EAC are highly questionable.
Status of clearance for Irrigation Projects
Region |
CCA for which TORC given, L Ha |
CCA for which EC given, L Ha |
CCA of projects considered, L Ha |
North |
2.02 |
3.53 |
6.17 |
North East |
0 |
0 |
4.00 |
East |
11.30 |
1.20 |
12.80 |
West |
8.34 |
4.65 |
13.01 |
South |
7.70 |
6.50 |
22.96 |
Total |
29.36 |
15.88 |
58.94 |
Land requirement Full details of the land required for the projects are never properly assessed by the EIAs. The EAC minutes reflect only indicative figures of land requirement of some of the projects considered by the EAC as mentioned in the EIAs.
Figure 3: Zone wise status of Stage 1 clearances (TORC)
Land required for the projects considered by EAC
Region |
No of projects for which land requirement figures are available |
Land required for the projects in previous column |
North |
62 |
29932.77 Ha |
North East |
72 |
76768.27 Ha |
East |
9 |
16809.24 Ha |
West |
15 |
31858.57 Ha |
South |
13 |
57398.82 Ha |
Total |
171 |
212767.67 Ha |
Following table gives an over view of land requirement for some of the projects as mentioned in the EAC minutes. Based on available figures, the Highest land requirement in a state is for Andhra Pradesh, at 45913.26 ha the second rank state is Arunachal Pradesh with land requirement of 35485.3 Ha. Arunachal being smaller and hilly state and most of the land being required are forested and close to the rivers, the impact in Arunachal Pradesh would be much greater. Based on above information, for the projected land requirement for the 262 projects considered by the EAC during the period under study would come to over 325995 Ha. However, these land requirement figures are gross under estimates and too much need not be read into them.
The flawed functioning of EAC It has not mattered to the EAC that the EIAs of the projects that come to it are shoddy, dishonest, cut and paste jobs. The Committee has not rejected a single EIA, even through evidence was repeatedly presented to the committee about shoddy nature of the EIAs. It has not mattered to the committee that there has been no credible public consultation process and there have been serious anomalies in public hearing processes. The committee did not order fresh public hearings even when evidence was provided to it about serious violations in public hearing processes.
Figure 4: Zone wise figures of TORC and EC given for hydropower installed capacities
Even when the committee asked for fresh studies or significant changes in EIA, it did not ask the project proponent to go back for fresh public hearing. It has not mattered to the committee that EIAs of the projects it cleared did not have full year round ground level surveys, did not have full social impact assessment, did not have downstream impact assessment, did not have options assessment to establish that the proposed project was least cost option, did not have assessment of impacts due to blasting of tens of kilometer long tunnels, did not have proper flora or fauna studies, did not include impact of the project on rivers and the services provided by the river or impact on downstream projects or flood plain use, or had used flawed, false or inconsistent data base.
Figure 5: Zone wise figures of TORC and EC given for irrigated area CCA in lakh Ha
SANDRP had put together a detailed submission[5] and mobilized endorsements of large number of concerned groups and individuals, including over ten eminent scientists on World Fisheries Day on Nov 21, 2012 and sent to EAC, raising issues concerning riverine fisheries in functioning of the EAC and suggesting specific measures to improve the same. The chairman of the EAC wrote back to SANDRP that this will be discussed in the next meeting of EAC, but there was no mention of it in the minutes of the EAC, nor any concrete action taken by the EAC after that. Earlier in November 2012, SANDRP had organized a side event on issues related to riverine biodiversity in India at the Hyderabad Conference of Parties of Convention on Biodiversity. Considering the importance of the issue for the functioning of the EAC, we had invited the members, including the Chairman and member secretary for the side event. No one came.
Figure 6 Overview of State-wise installed capacities of HEPs considered by EAC in North India
No appreciation of Cumulative Impacts It has not mattered to the committee that there has been no Cumulative Impact Assessment (CIA) when large number and bumper to bumper hydropower projects are proposed on number rivers including Bhagirathi, Alaknanda, Mandakini, Sutlej, Ravi, Beas, Chenab, Teesta, Lohit, Tawang, Siang, Subansiri, Narmada, to name only a few. It does not matter to them that there is no flowing river between two projects, it has recommended clearance to Luhri HEP most recently with zero flowing river length with both immediately upstream (Rampur HEP) and immediate downstream (Kol dam) projects.
Figure 7 Basin-wise overview of number of Hydro Projects considered by EAC in North India
Even in few cases that the EAC has asked for CIA, it has asked the CIA to be done by an agency like WAPCOS Ltd that has an abysmally poor track record in doing such studies and it has serious issues of conflict of interests since the agency is also involved in feasibility studies and detailed project reports as part of its business model. But EAC has never understood these concerns. Nor has the EAC really bothered to look at the quality of the CIA. Most significantly, the EAC refused to wait for the CIA report of a basin before considering individual projects in such basins, showing its complete lack of understanding of the importance of CIA.
Section 9 of the Form I (the developer is supposed to apply for stage I clearance with this form duly filled in, as per Para 6 of the notification)) prescribed in Annexure 1 of the EIA notification of Sept 2006 is supposed to be about “Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality”. Section 9.4 under this reads: “Have cumulative effects due to proximity to other existing or planned projects with similar effects”. So even legally the EAC and MoEF are supposed to look at the cumulative impact assessment issues under the EIA notification, both at scoping at appraisal stage, which they are clearly not doing.
Here it may be noted that recommending Environment clearance without first undertaking carrying capacity and cumulative impact assessment is in violation of Supreme Court order in “Karnataka Industrial Areas … vs Sri C. Kenchappa & Ors on 12 May, 2006” which has said:
A. “The pollution created as a consequence of environment must be commensurate with the carrying capacity of our ecosystem. In any case, in view of the precautionary principle, the environmental measures must anticipate, prevent and attack the causes of environmental degradation.”
B. “…the preventive measures have to be taken keeping in view the carrying capacity of the ecosystem operating in the environmental surroundings under consideration.”
C. “The pollution created as a consequence of development must not exceed the carrying capacity of ecosystem.”
Without knowing carrying capacity of a basin it cannot be ascertained if the proposed project is “commensurate with the carrying capacity of our ecosystem”, ecosystem in this context is the river basin.
Figure 8 Overview of Basin-wise installed capacity of HEPs that EAC considered in North India
Figure 9 State wise overview of installed capacity of HEPs considered by EAC in North East India
EAC’s double standards While EAC itself has not rejected any of the proposals that came to it, few, rare environment friendly recommendations that have been made by other committees have also been rejected by the EAC, without any convincing reasons. To illustrate, when the carrying capacity study of the Teesta basin recommended that no projects should be taken upstream of Chungthang in North Sikkim, the EAC in its meeting overturned this decision and decided to consider all such projects. Similarly, the recommendations of the Ganga Basin Cumulative Impact Assessment study by the Wildlife Institute of India, suggesting that at least 24 hydro projects proposed in Ganga basin be dropped and much higher environment flows than those directed by EAC should be mandated, were all rejected by the EAC.
The recommendations of the Western Ghats Ecology Panel headed by Prof Madhav Gadgil were also rejected on grounds such as inadequate studies. Overturning the recommendations of the WG Ecology Panel report, the EAC recommended clearance to the controversial Gundia hydropower project in Western Ghats in Karnataka. If the standards applied by the EAC while rejecting the recommendations of all these committees were to be applied to the EIAs and CIAs based on which the EAC approved the projects, than none of the projects approved by the EAC would merit clearances. But the EAC has very lax standards for its own work, and for the EIAs and CIAs that favour projects, but different ones for the reports that recommend rejection of projects. This contradiction is highlighted here only for illustration of double standards of the EAC and it does not mean that the EAC decisions in rejecting any recommendations of any of these committees have any merits.
Western Ghats Expert Ecology Panel assessing Ecosystems to be affected by Gundia HEP. EAC recommended clearance to this project despite rejection by WGEEP Photo: India Together
It may be noted that the previous chairman (former power secretary Shri P Abraham who chaired EAC till June 2009) had serious conflict of interest issues with he being on board of several power companies whose projects came up before the committee and the current chairman has had no back ground on environment issues. It has not mattered to the committee whether the Environment Management Plans that accompany the EIAs that it clears are implemented or not, or if there is any credible mechanism and legally empowered process in place to ensure its implementation. The EAC has not even shown concern for legal norms that the TOR clearances are valid only for two years. MoEF has recently issued a notification dated Oct 30, 2012[6] that said that project for which the proponents have not come back with the requested additional information for more than six months should be delisted. Luhri project thus should not have been considered by the MoEF from more than one legal point view. MoEF and EAC have yet to follow such notifications of the ministry.
The minutes of many of the EAC meetings make pathetic reading, if read carefully. One can find contradictions, inconsistencies, plain wrong facts being mentioned in the minutes of the EAC meetings[7], which are all approved by the EAC. Even when such errors are pointed out, the EAC has not even bothered to correct the mistakes or review its decisions.
Cleared by EAC, Rejected by others Many of the projects cleared by the EAC have faced serious road blocks for the shoddy appraisal done by the EAC. For example, the then Union Environment Minister himself decided not to clear the Renuka dam project cleared by the EAC. The Rupsiabagar Khasiabara project cleared by the EAC could not get forest clearance, for many reasons, including the fact that the EIA of the project was found to be so shoddy and wrong, that any other committee would have considered this an insult to its work. The Kotlibhel 1B and Kotlibhel 2 projects, cleared by this committee have been rejected clearances by the Forest Advisory Committee, following recommendation of the Wildlife Institute of India.
Figure 10 State wise overview of number of projects considered by EAC in North East India
Athirapally hydropower project in Chalakudy basin in Kerala was recommended Environment Clearance by the EAC for the third time (earlier two clearances were quashed by the Kerala High Court) in May 2007, but the project again came back to the EAC in March 2010, following Kerala High Court directions. Earlier on January 4, 2010, following directions from the then Union Environment Minister of State Shri Jairam Ramesh, Dr S Bhowmik, than director in MoEF, issued show cause notice under Environment Protection Act, 1986, to the developer agency, Kerala State Electricity Board, to show cause in 15 days as to why the environment clearance granted to the project should not be revoked and why the direction of closure of the project not be issued. It is not clear if the MoEF took the next step hinted in the notice. Its strange that the EAC, in which the same Dr Bhowmik was member secretary, did not mention the issuance of this notice in the EAC meetings when the EAC discussed this project between March and July 2010. There is no mention of the MoEF show cause notice in the minutes of the EAC meetings held during the period.
Figure 2 Athirappilly Water Falls at the proposed Athirappilly HEP site Photo: Southernsojourns
Several projects cleared by the EAC stand challenged in the National Green Tribunal, some of them (e.g. Renuka dam) have got a Stay Order. The World Bank too finds the EIAs based on which the EAC cleared the projects so poor that it has asked for fresh EIAs for the projects it wants to fund (e.g. Rampur and Vishnugad Pipalkoti hydropower projects).
Figure 11 Basin wise overview of number of projects considered by EAC in North East India
Climate Change It is well known that the worst impacts of climate change is going to be felt in terms of impacts on water resources. It is also well known that the natural resources like the biodiversity, forests, rivers, wetlands, fertile flood plains and riverine lands are some of the important resources that would help us adapt to the climate change impacts. Hydropower and dams that the EAC considers adversely affect all of these natural resources. It is well established that large sections of people of India who depend on such natural resources are the poorest and most vulnerable to climate change impacts and when the resources that these vulnerable sections depend on are destroyed by the hydropower projects and dams that the EAC appraises, the committee would be expected to consider the climate change context. Consideration of climate change context is thus important from several angles while appraising the river valley projects. It’s also well established now that past is not the best guide while estimating river water flows. Research over the last two decades have also established that reservoirs in a tropical country like India would also be source of methane and CO2 emissions, methane being about 21 times more potent in global warming terms than CO2. In view of all this, one would have expected elaborate discussion of climate change issues in the functioning of the EAC. One would expect the EAC to mandate the EIAs and CIAs to look at these issues comprehensively.
Unfortunately, we are disappointed on every one of these counts. We find little mention of climate change issues in the work of the EAC. In fact the model Terms of Reference for the hydropower projects put up on the MoEF website[8] does not have the word “climate” in it, leave aside “climate change”.
E-flows For Hydroelectric and River valley Projects which dewater and divert rivers entirely or partially and change its natural hydrograph, EAC has now[9] been arbitrarily recommending release of 20% of average lean season flow for lean months, between 20-30% e-flows (short for Environmental flow) for non-lean, non-monsoon months and 30% average monsoon flow for monsoon flows. This standard is entirely arbitrary, without any scientific, ecological or sociological basis, blanket for all rivers from Himalayan to peninsular.
This too has happened not suo motto, but after huge pressure from civil society and various other committees. And when the proponent says it cannot release these inadequate flows, EAC is actually ready to negotiate, which is acceptable between the EAC and the proponents (like in the case of 300 MW Alaknanda HEP by GMR Energy). Like any negotiation in a fish or vegetable market. While taking these decisions, EAC has never recommended that a more holistic and participatory method for assessing e-flows needs to be developed. Or that certain rivers needs to be left undammed. Even when other committees like the Wildlife Institute of India have recommended higher e-flows, the EAC or MoEF has refused to follow such recommendations.
Figure 12 State wise overview of number of Projects considered by EAC in East India
Biodiversity Violating the National Biodiversity Act of 2002, EAC does not ask for Biodiversity Impact Assessment of projects, does not think twice while recommending clearances to projects affecting severely threatened, endemic and endangered biodiversity and RET (Rare Endangered Threatened) species. This has had disastrous impacts for critically endangered fauna like Black Necked Cranes, Red Pandas (780 MW Nyamjangchu HEP), Several endemic species including Gundia Indian Frog (200 MW Gundia HEP), Snow Leopard (Projects in Upper Ganga including 300 MW Alaknanda HEP), Gangetic Dolphin (Upper Ganga and Brahmaputra Projects), Bengal Florican (1750 MW Lower Demwe Project), Fish like Golden Mahseer, Snow Trout (most dams in Himalayas and North East) to name a very few.
Figure 13 Basin wise overview of number of projects considered by EAC in East India
Even while noting in the 56th meeting of EAC, while discussing the 775 MW Luhri HEP on Sutlej river in Himachal Pradesh, that as per the EIA of the project, “However, 21 species are listed in the Red data book of Indian plants”, the EAC does not even bother to enquire about which are these plants and why decide to sacrifice their loss. While discussing Shongtong Karcham hydropower project, the EAC noted in the minutes of the 30th meeting of EAC, “Considering the presence of 51 species of fish in the upper reaches of Sutlej, it is reported (in EIA) that only three species of fish were found in the study area”. But amazingly, the EAC has no qualms in accepting such fundamentally flawed EIA. Two of these species are simply human intervention.
Dibru Saikhowa National Park and its endangered species are thretened by the 1750 MW Lower Demwe Dam on Lohit cleared by EAC Photo: assam Portal
In case of the Rupsiabagar Khasiabara Hydro Power Project in Uttarakhand[10], the EIA report prepared by the WAPCOS to obtain Environment Clearance for the RKHPP reports presence of only 8 bird species. The EAC actually gave clearance to the project without raising any issues of the flawed EIA. The Inspection Report of the Sub-Committee of the Forest Advisory Committee to assess wildlife values and ecological impact of the project, led by Dr Ullas Karanth makes interesting reading.
Figure 14 State wise over view of number of projects considered by EAC in West India
Figure 15 Basin wise overview of number of projects considered by EAC in West India
Figure 16 Basin wise overview of CCA of Irrigation Projects considered by EAC in West India
The Inspection Report noted, “However, as per the existing literature a total of 228 bird species in 30 families and 118 genera, representing more than 45% of the breeding bird diversity of the Western Himalaya and nearly 55% of breeding bird species of the kumaon Himalaya are recorded in the region. Ten species of pheasants are found in the area, including Himalayan monal, and the Koklass pheasant, and several other altitudinal migrants. This assemblage represents 6 out of seven West Himalayan endemics found in Kumaon.” But the EAC did not even note any of these flaws of the EIA and obediently cleared the project. The project currently stands cancelled after the sub committee recommended that the project be rejected forest clearance. All this shows how little significance is of biodiversity for the EAC and MoEF.
Regional and detailed analysis These conclusions are based on analysis of the agenda and minutes of 63 meetings of EAC spread over close to six years from April 2007 to December 2012, done by South Asia Network on Dams, Rivers & People (www.sandrp.in)[11] in light of other related information and experiences. SANDRP has been monitoring the functioning of the EAC over the years, has been writing to the EAC about its concerns and also those of partner organisations about specific projects and general functioning of the EAC. This analysis is based on this experience and we hope it will be useful for all concerned.
In what follows we have given region wise status and analysis of the project wise clearances recommended by the EAC for RVP for the five regions of India, namely: North, North East, East, West and South. The tables for each region give state wise list of projects with some basic features of the projects. An overview of number of projects and their capacities is given in tables that give status wise, state wise and river basin wise figures for the projects that EAC considered in these six years.
Figure 17 State wise Overview of hydropower installed capacities considered by EAC in South India
Figure 18 Overview of Irrigation Projects: Culturable Command Area (CCA) of Projects in South India
In an accompanying document[12], also from SANDRP, we have given more details for each project and date-wise decisions of the EAC for each of the projects on EAC agenda. We are hopeful that these two documents will be helpful in giving clear picture about functioning of the EAC to all concerned.
We should add here that these two documents are only limited to giving a picture about functioning of the Expert Appraisal Committee on River Valley Projects. There are many other equally serious problems plaguing the environmental governance of River Valley Projects in India, they will require separate work.
NORTH INDIA
TOR & Environment Clearance status in North India
Following table gives project wise information about basic features and clearance status for the projects that came to EAC from North Indian states of Jammu and Kashmir, Haryana, Punjab, Himachal Pradesh, Uttar Pradesh, Delhi and Uttarakhand. The maximum no of projects are (34) from Himachal Pradesh among all states, Uttarakhand coming second with 25 projects. Jammu and Kashmir has less no of projects at 11, but the proposed installed capacity of the J&K projects is highest at 7573 MW. The land requirement is also highest in J&K among North India states at over 10170 Ha. Among all regions, the EAC has given the highest number of environment clearances in North India.
SN |
Project |
State |
Basin |
I/H/M |
Ins Cap (MW) |
CCA (Ha) |
TOR |
Meeting date |
Env Clearance |
Meeting date |
Total Area Req (Ha) |
Haryana |
|||||||||||
1 |
Dadupur – Nalvi Irrigation Project |
Haryana |
Yamuna |
I |
– |
92532 |
Approved |
16/05/2007 |
Recommended |
16/06/2009 |
NA |
2 |
Hansi – Butana Link Channel |
Haryana |
Yamuna |
M |
– |
232024 |
– |
|
Waiting |
19/07/2007 |
553.21 |
Himachal Pradesh (HP) |
|||||||||||
3 |
Dhaulasidh HEP |
HP |
Beas |
H |
66 |
– |
Approved |
22/04/2010 |
Recommended |
23/11/2012 |
NA |
4 |
Lambadug HEP |
HP |
Beas |
H |
25 |
– |
– |
|
Recommended |
22/08/2008 |
9.7914 |
5 |
Nakthan HEP |
HP |
Beas |
H |
520 |
– |
Approved |
20/12/2010 |
– |
– |
97.76 |
6 |
SAINJ HEP |
HP |
Beas |
H |
100 |
– |
Approved |
22/06/2007 |
Recommended |
20/03/2009 |
56.763 |
7 |
Thana-Plaun HEP |
HP |
Beas |
H |
141 |
– |
Approved |
7/9/2012 |
– |
– |
497 |
8 |
Triveni Mahadev |
HP |
Beas |
H |
78 |
– |
Approved |
7/9/2012 |
– |
– |
482 |
9 |
Chhatru HEP |
HP |
Chenab |
H |
108 |
– |
Approved |
8/5/2008 |
Waiting |
28/04/2012 |
95.26 |
10 |
Dugar HEP |
HP |
Chenab |
H |
380 |
– |
Approved |
12/10/2012 |
– |
– |
NA |
11 |
Gondhala HEP |
HP |
Chenab |
H |
144 |
– |
Approved |
16/10/2008 |
– |
– |
214 |
12 |
Gyspa HEP |
HP |
Chenab |
H |
300 |
– |
Approved |
26/03/2011 |
– |
– |
1635 |
13 |
Miyar HEP |
HP |
Chenab |
H |
120 |
– |
Approved |
25/09/2010 |
Recommended |
12/11/2011 |
69.94 |
14 |
Purthi |
HP |
Chenab |
H |
300 |
– |
Not approved |
23/11/2012 |
– |
– |
72 |
15 |
Reoli–Dugli HEP |
HP |
Chenab |
H |
420 |
– |
Approved |
26/12/2012 |
– |
– |
182 |
16 |
Sach Khas HEP |
HP |
Chenab |
H |
267 |
– |
Approved |
24/11/2012 |
– |
– |
102.48 |
17 |
Seli HEP |
HP |
Chenab |
H |
400 |
– |
Approved |
19/02/2012 |
Recommended |
1/6/2012 |
292.9654 |
18 |
Telling HEP |
HP |
Chenab |
H |
94 |
– |
Approved |
23/11/2012 |
– |
– |
83 |
19 |
Bajoli Holi |
HP |
Ravi |
H |
180 |
– |
Approved |
16/01/2008 |
Recommended |
21/12/2010 |
85.7 |
20 |
Bara Bangahal HEP |
HP |
Ravi |
H |
200 |
– |
Approved |
16/12/2008 |
– |
– |
53.64 |
21 |
Chanju-I HEP |
HP |
Ravi |
H |
36 |
– |
|
– |
Recommended |
26/02/2011 |
NA |
22 |
Kutehar HEP |
HP |
Ravi |
H |
260 |
– |
Approved |
7/5/2008 |
Recommended |
21/01/2011 |
85.36 |
23 |
Chango-Yangthang HEP |
HP |
Sutlej |
H |
180 |
– |
Approved |
8/9/2012 |
– |
– |
146 |
24 |
Lara Sumta |
HP |
Sutlej |
H |
104 |
– |
Approved |
12/10/2012 |
– |
– |
97.75 |
25 |
Luhri HEP |
HP |
Sutlej |
H |
775 |
– |
Approved |
18/04/2007 |
Recommended |
24/11/2012 |
380 |
26 |
Shongtong-Karcham HEP |
HP |
Sutlej |
H |
402 |
– |
Approved |
16/08/2007 |
Recommended |
18/02/2010 |
79.17 |
27 |
Sumte Kothang |
HP |
Sutlej |
H |
130 |
– |
Approved |
12/10/2012 |
– |
– |
110 |
28 |
Tidong -I |
HP |
Sutlej |
H |
100 |
– |
|
– |
Recommended |
16/08/2007 |
46.66 |
29 |
Tidong -II |
HP |
Sutlej |
H |
60 |
– |
Waiting |
29/07/2009 |
– |
– |
164.53 |
30 |
Yangthang – Khab HEP |
HP |
Sutlej |
H |
261 |
– |
Approved |
16/06/2009 |
– |
– |
1532.6 |
31 |
Chirgaon-Majhgaon HEP |
HP |
Yamuna |
H |
60 |
– |
Approved |
24/11/2012 |
– |
– |
31.58 |
32 |
Dhamwari Sunda HEP |
HP |
Yamuna |
H |
70 |
– |
Approved |
28/07/2009 |
Recommended |
15/07/2011 |
23.3025 |
33 |
Renuka Dam Project |
HP |
Yamuna |
M |
40 |
– |
Approved |
16/08/2007 |
Recommended |
28/07/2009 |
1532.6 |
34 |
Rupin |
HP |
Yamuna |
H |
45 |
– |
Approved |
24/11/2012 |
– |
– |
27 |
Jammu & Kashmir (JK) |
|||||||||||
35 |
Baglihar stage- II HEP |
JK |
Chenab |
H |
450 |
– |
Approved |
22/04/2010 |
Recommended |
8/9/2012 |
NA |
36 |
Bursar HEP |
JK |
Chenab |
H |
1500 |
– |
Approved |
2/6/2012 |
– |
– |
1665 |
37 |
Kirthai HEP |
JK |
Chenab |
H |
250 |
– |
Approved |
8/5/2008 |
– |
– |
290 |
38 |
Kirthai Stage-II HEP |
JK |
Chenab |
H |
990 |
– |
Waiting |
31/03/2012 |
– |
– |
NA |
39 |
Kiru HEP |
JK |
Chenab |
H |
600 |
– |
Approved |
22/08/2008 |
– |
– |
295 |
40 |
Kwar HEP |
JK |
Chenab |
H |
520 |
– |
Approved |
19/02/2010 |
– |
– |
326 |
41 |
Pakal Dul HEP |
JK |
Chenab |
H |
1000 |
– |
|
– |
Recommended |
7/1/2008 |
1163.898 |
42 |
Ratle HEP |
JK |
Chenab |
H |
690 |
– |
Approved |
27/12/2011 |
Recommended |
21/07/2012 |
567.22 |
43 |
Sawalkote HEP |
JK |
Chenab |
H |
1200 |
– |
Approved |
3/6/2011 |
– |
– |
1099 |
44 |
New Ganderbal HEP |
JK |
Jhelum |
M |
93 |
– |
Approved |
8/5/2008 |
Recommended |
26/12/2012 |
63.7 |
45 |
Ujh Multipurpose Project |
JK |
Ravi |
M |
280 |
32000 |
Waiting |
13/11/2010 |
– |
– |
4700 |
Uttarakhand (UA) |
|||||||||||
46 |
Alaknanda Hydro Power Project |
UA |
Alaknanda |
H |
300 |
– |
– |
– |
Recommended |
17/01/2008 |
83.9 |
47 |
Bowala Nand Prayag HEP |
UA |
Alaknanda |
H |
300 |
– |
Approved |
22/08/2008 |
– |
– |
64.069 |
48 |
Devsari HEP |
UA |
Alaknanda |
H |
252 |
– |
Approved |
18/03/2008 |
Recommended |
26/12/2011 |
223.36 |
49 |
Jelam Tamak HEP |
UA |
Alaknanda |
H |
128 |
– |
Approved |
28/04/2012 |
– |
– |
96.27 |
50 |
Kotlibhel 1-B |
UA |
Alaknanda |
H |
320 |
– |
– |
– |
Recommended |
19/07/2007 |
550.619 |
51 |
Kotlibhel-stage II HEP |
UA |
Ganga |
H |
530 |
– |
– |
– |
Recommended |
19/07/2007 |
676.071 |
52 |
Nand Prayag Langasu |
UA |
Alaknanda |
H |
100 |
– |
Approved |
25/09/2010 |
– |
– |
79.8177 |
53 |
Phata Byung HEP |
UA |
Alaknanda |
H |
76 |
– |
– |
– |
Recommended |
17/01/2008 |
22.72 |
54 |
Rambara HEP |
UA |
Alaknanda |
H |
76 |
– |
Waiting |
16/10/2008 |
– |
– |
17.78 |
55 |
Singoli Batwari |
UA |
Alaknanda |
H |
99 |
– |
– |
– |
Recommended |
18/07/2007 |
43 |
56 |
Tamak Lata HEP |
UA |
Alaknanda |
H |
280 |
– |
Waiting |
21/01/2011 |
– |
– |
77.26 |
57 |
Bhilinagana Project |
UA |
Bhialangana |
H |
22.5 |
– |
– |
– |
Recommended |
26/12/2011 |
NA |
58 |
Bogudiyar-Sirkari Bhyol HEP |
UA |
Sarda |
H |
170 |
– |
Approved |
14/05/2009 |
– |
– |
75 |
59 |
Mapang-Bogudiyar HEP |
UA |
Sarda |
H |
200 |
– |
Approved |
14/05/2009 |
– |
– |
70 |
60 |
Rupsiabagar Khasiabara HEP |
UA |
Sarda |
H |
260 |
– |
– |
– |
Recommended |
17/02/2009 |
32 |
61 |
Sirkari Bhyol Rupsiabagar HEP |
UA |
Sarda |
H |
210 |
– |
Approved |
29/07/2009 |
– |
– |
NA |
62 |
Jamrani Dam Multipurpose Project |
UA |
Sarda |
M |
30 |
150302 |
– |
– |
Recommended |
18/02/2010 |
529.57 |
63 |
Arakot Tiuni HEP |
UA |
Yamuna |
H |
81 |
– |
Approved |
21/01/2011 |
– |
– |
38 |
64 |
Hanol -Tiuni HEP |
UA |
Yamuna |
H |
60 |
– |
– |
– |
Recommended |
8/5/2008 |
48.982 |
65 |
Jakhol Sankhri HEP |
UA |
Yamuna |
H |
45 |
– |
Approved |
15/06/2009 |
– |
– |
24 |
66 |
Lakhwar HEP |
UA |
Yamuna |
H |
300 |
– |
Waiting |
12/11/2010 |
– |
– |
NA |
67 |
Mori- Hanol HEP |
UA |
Yamuna |
H |
63 |
– |
Approved |
14/12/2007 |
– |
– |
45 |
68 |
Naitwar Mori HEP |
UA |
Yamuna |
H |
60 |
– |
Approved |
22/06/2007 |
Recommended |
27/12/2011 |
47.05 |
69 |
Tiuni Plasu HEP |
UA |
Yamuna |
H |
66 |
– |
Approved |
17/01/2008 |
– |
– |
NA |
70 |
Vyasi HEP |
UA |
Yamuna |
H |
120 |
– |
– |
– |
Recommended |
16/09/2007 |
135.425 |
Uttar Pradesh (UP) |
|||||||||||
71 |
Badaun Irrigation Scheme |
UP |
Ganga |
I |
– |
53,054 |
Approved |
16/07/2008 |
Recommended |
30/06/2010 |
5053 |
72 |
Arjun Sahayak Pariyojna |
UP |
Yamuna |
I |
– |
57000 |
Approved |
18/03/2008 |
Recommended |
19/08/2009 |
2891 |
Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available
State-wise Overview of Projects in North India
|
Projects |
Ins Cap |
Irrigation |
Drinking water |
Land Req |
Land Req Info available for projects |
State wise Projects |
Nos |
MW |
CCA (Ha) |
MLD |
(Ha) |
Nos |
Total Projects |
72 |
18087.5 |
616912 |
145 |
29932.77 |
62 |
HP |
32 |
6366 |
|
— |
8285.85 |
29 |
UA |
25 |
4148.5 |
150302 |
145 |
2979.89 |
21 |
J&K |
11 |
7573 |
32000 |
— |
10169.82 |
9 |
UP |
2 |
— |
110054 |
— |
7944 |
2 |
Haryana |
2 |
— |
324556 |
— |
533.21 |
1 |
Overview of Status of clearance of projects in North India
TOR & EC Status |
Nos |
MW |
CCA |
MLD |
Land Req |
Land Req Info available for projects |
TOR approved |
50 |
12823 |
202586 |
— |
21005.36 |
44 |
TOR not approved |
1 |
300 |
0 |
— |
72 |
1 |
TOR Waiting |
6 |
1986 |
32000 |
— |
4959.57 |
4 |
TOR approved before this committee |
15 |
2978.5 |
382326 |
145 |
3895.85 |
13 |
Env Cl. Recommended |
31 |
6843.5 |
352888 |
— |
14793.77 |
27 |
Env Cl. Waiting |
3 |
171 |
232024 |
— |
648.47 |
2 |
Env Clearance not Recommended |
0 |
0 |
0 |
0 |
0 |
0 |
Basin-wise overview of projects in North India
Projects on basins |
Nos |
MW |
CCA |
MLD |
Bhilangana (Ganga) |
1 |
22.5 |
— |
— |
Alaknanda (Ganga) |
10 |
1931 |
— |
— |
Sarda (Ganga) |
5 |
870 |
150302 |
145 |
Yamuna (Ganga) |
15 |
1010 |
381556 |
— |
Ramganga (Ganga) |
1 |
0 |
53,054 |
— |
Ganga |
1 |
530 |
— |
— |
Ganga total |
33 |
4363.5 |
— |
— |
Beas |
6 |
930 |
— |
— |
Chenab |
19 |
9733 |
— |
— |
Sutlej |
8 |
2012 |
— |
— |
Ravi |
5 |
956 |
32000 |
— |
Jhelum |
1 |
93 |
— |
— |
From the above tables it is clear that while largest number of projects from North India came from Ganga Basin at 33, the installed capacity of projects proposed in Chenab basin is highest at 9733 MW.
NORTH EAST INDIA
TOR & Environment Clearance status in North-East India
The region comprises of eight states including Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Sikkim, Tripura and Nagaland. The Highest number of projects (99) has come to EAC from the North East region, and the highest number of first stage clearances at 70 have been given by EAC from this region. Within the North East Region, by far the highest number of projects (69) have come to EAC from Arunachal Pradesh. The EAC has the highest approval % in Arunachal Pradesh, every project has been given approval. Only for the 420 MW Kameng HEP of KSK Ltd, the EAC asked the developer to come back with reformulated proposal, rest were all given approval by the EAC. Over 35000 MW of hydropower projects have come to EAC from Arunachal Pradesh alone, by far the highest in the country for any state. Maximum no of projects that came to EAC among all river basins is from Siang basin at 21, though in terms of installed capacity, the highest installed capacity has come from Lohit basin at 10250 MW, among all the sub basins in the region. It was amazing to see the EAC promptly clearing the controversial Tipaimukh project way back in 2008, but the project is yet to get forest clearance and is unlikely to be able to start work in near future.
SN |
Project |
State |
Basin |
I/H/M |
Ins Cap (MW) |
CCA (Ha) |
TOR |
Meeting date |
Env Clearance |
Meeting date |
Land Req (Ha) |
||||
Arunachal Pradesh |
|||||||||||||||
1 |
Amulin HEP |
ARP |
Dibang |
H |
420 |
|
Approved |
30/06/2010 |
|
|
592.46 |
||||
2 |
Dibang |
ARP |
Dibang |
H |
3000 |
|
Approved |
29/07/2009 |
|
|
5827.8 |
||||
3 |
Emini HEP |
ARP |
Dibang |
H |
500 |
|
Approved |
21/08/2010 |
|
|
698 |
||||
4 |
Mihundon HEP |
ARP |
Dibang |
H |
400 |
|
Approved |
3/4/2011 |
|
|
700.42 |
||||
5 |
Sissri HEP |
ARP |
Dibang |
H |
222 |
|
Approved |
20/03/2009 |
|
|
900 |
||||
6 |
Ithun-I |
ARP |
Dibang |
H |
86 |
|
Approved |
26/12/2012 |
|
|
76 |
||||
7 |
Attunil HEP |
ARP |
Dibang |
H |
500 |
|
Approved |
16/11/2009 |
|
|
1021 |
||||
8 |
Emra – II HEP |
ARP |
Dibang |
H |
390 |
|
Waiting |
20/01/2010 |
|
|
1125 |
||||
9 |
Etalin HEP |
ARP |
Dibang |
H |
3097 |
|
Waiting |
26/12/2012 |
|
|
1149.85 |
||||
10 |
Dibbin HEP |
ARP |
Kameng |
H |
130 |
|
— |
|
Recommended |
26/03/2011 |
162 |
||||
11 |
Badao HEP |
ARP |
Kameng |
H |
70 |
|
Approved |
7/10/2010 |
|
|
37.82 |
||||
12 |
Dinchang HEP |
ARP |
Kameng |
H |
360 |
|
Approved |
26/02/2011 |
|
|
82.13 |
||||
13 |
Gongri |
ARP |
Kameng |
H |
144 |
|
Approved |
12/04/2008 |
Recommended |
21/07/2012 |
93 |
||||
14 |
Jameri HEP |
ARP |
Kameng |
H |
50 |
|
Approved |
23/11/2012 |
|
|
130 |
||||
15 |
Khuitam HEP |
ARP |
Kameng |
H |
66 |
|
Approved |
16/10/2008 |
Recommended |
21/12/2010 |
66 |
||||
16 |
Nafra HEP |
ARP |
Kameng |
H |
120 |
|
Approved |
22/08/2008 |
Recommended |
27/12/2011 |
78.45 |
||||
17 |
Pachuk-I HEP |
ARP |
Kameng |
H |
84 |
|
Approved |
27/12/2011 |
|
|
39.2548 |
||||
18 |
Pachuk-II HEP |
ARP |
Kameng |
H |
60 |
|
Approved |
27/12/2011 |
|
|
|
||||
19 |
Para HEP |
ARP |
Kameng |
H |
55 |
|
Approved |
7/10/2010 |
|
|
29.97 |
||||
20 |
Saskang Rong HEP |
ARP |
Kameng |
H |
36 |
|
Approved |
8/5/2008 |
|
|
20 |
||||
21 |
Talong HEP |
ARP |
Kameng |
H |
225 |
|
Approved |
12/10/2012 |
|
|
|
||||
22 |
Kameng Dam HEP |
ARP |
Kameng |
H |
420 |
|
Not accepted |
28/04/2012 |
|
|
3,764 |
||||
23 |
Kameng-I HEP |
ARP |
Bhareli |
H |
1120 |
|
Approved |
18/04/2007 |
|
|
969 |
||||
24 |
Anjaw |
ARP |
Lohit |
H |
280 |
|
Approved |
16/07/2011 |
|
|
359.12 |
||||
25 |
Demwe HEP |
ARP |
Lohit |
H |
3000 |
|
Approved |
19/07/2007 |
|
|
3600 |
||||
26 |
Demwe Lower HEP |
ARP |
Lohit |
H |
1750 |
|
Approved |
17/07/2008 |
Recommended |
16/12/2009 |
1589.97 |
||||
27 |
Demwe upper HEP |
ARP |
Lohit |
H |
1080 |
|
Approved |
26/12/2012 |
|
|
967 |
||||
28 |
Hotong HEP |
ARP |
Lohit |
H |
1250 |
|
Approved |
18/07/2007 |
— |
|
|
||||
29 |
Kalai-I HEP |
ARP |
Lohit |
H |
1450 |
— |
Approved |
18/07/2007 |
|
|
|
||||
30 |
Kalai-II HEP |
ARP |
Lohit |
H |
1200 |
|
Approved |
22/10/2009 |
|
|
830 |
||||
31 |
Tipang HEP |
ARP |
Lohit |
H |
45 |
|
Approved |
20/03/2010 |
|
|
557 |
||||
32 |
Gimliang HEP |
ARP |
Lohit |
H |
99 |
|
Waiting |
12/10/2012 |
|
|
NA |
||||
33 |
Raigam HEP |
ARP |
Lohit |
H |
96 |
|
Waiting |
12/10/2012 |
|
|
NA |
||||
34 |
Dardu HEP |
ARP |
Pare |
H |
60 |
|
Approved |
8/9/2012 |
|
|
82.7 |
||||
35 |
Par HEP |
ARP |
Pare |
H |
60 |
|
Approved |
8/9/2012 |
|
|
28.25 |
||||
36 |
Turu HEP |
ARP |
Pare |
H |
66 |
|
Approved |
8/9/2012 |
|
|
29.49 |
||||
37 |
Tato-II |
ARP |
Siang |
H |
700 |
|
— |
|
Recommended |
21/12/2010 |
371.49 |
||||
38 |
Pauk HEP |
ARP |
Siang |
H |
145 |
|
Approved |
17/09/2011 |
|
|
300 (Combined fig) |
||||
39 |
HEO |
ARP |
Siang |
H |
240 |
|
Approved |
17/09/2011 |
|
|
|||||
40 |
Tato-I |
ARP |
Siang |
H |
186 |
|
Approved |
17/09/2011 |
|
|
|||||
41 |
Hirit HEP |
ARP |
Siang |
H |
28 |
|
Approved |
21/08/2008 |
|
|
120 |
||||
42 |
Hirong HEP |
ARP |
Siang |
H |
800 |
|
Approved |
15/10/2007 |
Waiting |
23/11/2012 |
|
||||
43 |
Kangtanshiri |
ARP |
Siang |
H |
80 |
|
Approved |
8/9/2012 |
|
|
|
||||
44 |
Lower Siang HEP |
ARP |
Siang |
H |
2700 |
|
Approved |
23/11/2012 |
|
|
|
||||
45 |
Lower Yamne St-I |
ARP |
Siang |
H |
88 |
|
Approved |
11/2/2012 |
|
|
128.25 |
||||
46 |
Lower Yamne St- II |
ARP |
Siang |
H |
90 |
|
Approved |
11/2/2012 |
|
|
105.89 |
||||
47 |
Naying HEP |
ARP |
Siang |
H |
1000 |
— |
Approved |
22/06/2007 |
|
|
600 |
||||
48 |
Phangchung HEP |
ARP |
Siang |
H |
36 |
|
Approved |
18/06/2008 |
|
|
25.5 |
||||
49 |
Rapum HEP |
ARP |
Siang |
H |
80 |
|
Approved |
1/6/2012 |
|
|
40 |
||||
50 |
Rego HEP |
ARP |
Siang |
H |
70 |
|
Approved |
16/12/2008 |
|
|
|
||||
51 |
Simang-I HEP |
ARP |
Siang |
H |
67 |
|
Approved |
12/10/2012 |
|
|
|
||||
52 |
Simang-II HEP |
ARP |
Siang |
H |
66 |
|
Approved |
23/03/2010 |
|
|
85 |
||||
53 |
Tagurshit HEP |
ARP |
Siang |
H |
74 |
|
Approved |
31/03/2012 |
|
|
41.7 |
||||
54 |
Yamne -I HEP |
ARP |
Siang |
H |
60 |
|
Approved |
19/09/2008 |
|
|
400 |
||||
55 |
Yamne -II HEP |
ARP |
Siang |
H |
96 |
|
Approved |
23/11/2012 |
|
|
300 |
||||
56 |
Jerong |
ARP |
Siang |
H |
90 |
|
Waiting |
8/9/2012 |
|
|
108.35 |
||||
57 |
Pema Shelphu |
ARP |
Siang |
H |
70 |
|
Waiting |
29/07/2009 |
|
|
63 |
||||
58 |
Nalo HEP |
ARP |
Subansiri |
H |
360 |
|
Approved |
12/11/2011 |
|
|
662.94 |
||||
59 |
Subansiri Middle |
ARP |
Subansiri |
H |
1600 |
|
Approved |
12/10/2012 |
|
|
3180 |
||||
60 |
Subansiri Upper |
ARP |
Subansiri |
H |
2000 |
|
Approved |
22/01/2011 |
|
|
3155 |
||||
61 |
Tawang HEP St-I |
ARP |
Tawang |
H |
600 |
|
— |
— |
Recommended |
21/01/2011 |
305.60 |
||||
62 |
Tawang HEP St-II |
ARP |
Tawang |
H |
800 |
|
— |
— |
Recommended |
21/01/2011 |
452.6 |
||||
63 |
Mago Chu HEP |
ARP |
Tawang |
H |
96 |
|
Approved |
20/01/2010 |
|
|
30 |
||||
64 |
New Melling HEP |
ARP |
Tawang |
H |
96 |
|
Approved |
20/01/2010 |
|
|
|
||||
65 |
Nyamjang Chhu |
ARP |
Tawang |
H |
780 |
|
Approved |
17/01/2008 |
Recommended |
17/09/2011 |
254.55 |
||||
66 |
Nyukcharong Chu |
ARP |
Tawang |
H |
96 |
|
Approved |
20/01/2010 |
|
|
25 |
||||
67 |
Rho HEP |
ARP |
Tawang |
H |
141 |
|
Approved |
7/10/2010 |
|
|
35.39 |
||||
68 |
Tsachu-I Lower |
ARP |
Tawang |
H |
69 |
|
Approved |
21/07/2012 |
|
|
19.5 |
||||
69 |
Tsachu-II Lower |
ARP |
Tawang |
H |
79 |
|
Approved |
21/07/2012 |
|
|
38.89 |
||||
Assam |
|||||||||||||||
70 |
Karbi Langpi Upper St |
Assam |
Kopili |
H |
60 |
|
Waiting |
21/11/2008 |
|
|
|
||||
71 |
Lower Kopili HEP |
Assam |
Kopili |
H |
150 |
|
Waiting |
26/12/2012 |
|
|
1577 |
||||
Manipur |
|||||||||||||||
72 |
Loktak Downstream |
Manipur |
Barak |
H |
66 |
|
— |
|
Recommended |
12/10/2012 |
211.57 |
||||
73 |
Tipaimukh (Multipurpose) |
Manipur |
Barak |
H |
1500 |
|
— |
|
Recommended |
19/09/2008 |
31,950 |
||||
Meghalaya |
|||||||||||||||
74 |
Kynshi Stage- I |
Meghalaya |
Barak |
H |
300 |
|
Approved |
21/12/2010 |
|
|
185 |
||||
75 |
Kynshi Stage- II |
Meghalaya |
Barak |
H |
400 |
|
Waiting |
31/03/2012 |
|
|
4200 |
||||
76 |
Mawhu HEP |
Meghalaya |
Kopili |
H |
120 |
|
Approved |
18/04/2007 |
|
|
65 |
||||
77 |
Nongkohlait HEP |
Meghalaya |
Kopili |
H |
120 |
|
Approved |
14/12/2007 |
|
|
400 |
||||
78 |
Umduna HEP |
Meghalaya |
Kopili |
H |
57 |
|
Approved |
8/5/2008 |
|
|
|
||||
79 |
Umngi HEP |
Meghalaya |
Kopili |
H |
100 |
|
Approved |
14/12/2007 |
|
|
495 |
||||
80 |
Umjaut HEP |
Meghalaya |
Kopili |
H |
69 |
|
Waiting |
8/5/2008 |
|
|
|
||||
81 |
Myntdu HEP |
Meghalaya |
Myntdu |
H |
42[13] |
|
— |
|
Recommended |
17/07/2008 |
|
||||
82 |
Myntdu Leshka Stage -II |
Meghalaya |
Myntdu |
H |
280 |
|
Approved |
23/03/2010 |
|
|
|
||||
Mizoram |
|||||||||||||||
83 |
Kolodyne-II HEP |
Mizoram |
Kolodyne |
H |
460 |
|
Approved |
27/12/2011 |
|
|
720 |
||||
Nagaland |
|||||||||||||||
84 |
Dikhu HEP |
Nagaland |
Dikhu |
H |
186 |
|
Approved |
26/12/2012 |
|
|
|
||||
Sikkim |
|||||||||||||||
85 |
Dickchu HEP |
Sikkim |
Teesta |
H |
96 |
|
— |
|
Recommended |
21/02/2008 |
39.07 |
||||
86 |
Rangit –II |
Sikkim |
Teesta |
H |
66 |
|
— |
|
Recommended |
14/05/2009 |
64.93 |
||||
87 |
Tashiding HEP |
Sikkim |
Teesta |
H |
97 |
|
— |
|
Recommended |
30/06/2010 |
17.854 |
||||
88 |
Ting Ting |
Sikkim |
Teesta |
H |
99 |
|
— |
|
Recommended |
22/01/2011 |
25.4924 |
||||
89 |
Lethang HEP |
Sikkim |
Teesta |
H |
96 |
|
Approved |
20/01/2010 |
|
|
|
||||
90 |
Suntaley Tar |
Sikkim |
Teesta |
H |
40 |
|
Approved |
8/9/2012 |
|
|
39.02 |
||||
91 |
Teesta Stage –I |
Sikkim |
Teesta |
H |
280 |
|
Approved |
18/04/2007 |
|
|
|
||||
92 |
Teesta Stage-II |
Sikkim |
Teesta |
H |
150 |
|
Waiting |
23/11/2012 |
|
|
NA |
||||
93 |
Teesta Stage -III[14] |
Sikkim |
Teesta |
H |
1200 |
|
— |
|
Recommended |
4/8/2006 |
|
||||
94 |
Teesta Stage -IV |
Sikkim |
Teesta |
H |
520 |
|
Approved |
14/05/2009 |
Waiting |
23/11/2012 |
324 |
||||
95 |
Chakung Chu |
Sikkim |
Teesta |
H |
90 |
|
Waiting |
28/04/2012 |
|
|
|
||||
96 |
Lingza HEP |
Sikkim |
Teesta |
H |
120 |
— |
Waiting |
20/09/2007 |
— |
|
|
||||
97 |
Panan HEP |
Sikkim |
Teesta |
H |
300 |
|
Waiting |
31/03/2012 |
|
|
|
||||
98 |
Ralong |
Sikkim |
Teesta |
H |
120 |
|
Waiting |
28/04/2012 |
|
|
|
||||
Multistate |
|||||||||||||||
99 |
Sankosh-Teesta canal |
Multistate |
Sankhosh |
H |
4000 |
400000 |
Waiting |
16/12/2008 |
|
|
|
||||
Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available
State-wise Overview of Projects in North-East India
|
Projects |
Ins Cap |
Irrigation |
Land Req |
Land requirement info available for projects |
State wise Projects |
Nos |
MW |
CCA (Ha) |
(Ha) |
Nos |
Total Projects |
99 |
46658 |
— |
76768.27 |
72 |
ARP |
69 |
35474 |
— |
36454.34 |
56 |
Sikkim |
14 |
3274 |
— |
510.37 |
6 |
Meghalaya |
9 |
1488 |
— |
5345 |
6 |
Manipur |
2 |
1566 |
— |
32161.57 |
2 |
Assam |
2 |
210 |
— |
1577 |
1 |
Nagaland |
1 |
186 |
— |
NA |
0 |
Mizoram |
1 |
460 |
— |
720 |
1 |
Multi state |
1 |
4000 |
400000 |
NA |
0 |
Overview of Status of clearance of projects in North East India
TOR & EC Status |
Nos |
MW |
CCA |
Land Req |
Land Req Info available for projects |
TOR approved |
70 |
31541 |
— |
31180.47 |
55 |
TOR not approved |
1 |
420 |
— |
3764 |
1 |
TOR Waiting |
16 |
9301 |
400000 |
8223.2 |
6 |
TOR approved prior to this EAC |
12 |
4940 |
— |
33600.6 |
10 |
Env Clearance Recommended |
17 |
8256 |
— |
35682.58 |
15 |
Env Clearance Waiting |
2 |
1320 |
— |
324 |
1 |
Env Clearance rejected |
0 |
0 |
0 |
0 |
0 |
Basin-wise overview of projects in North East India
Projects on basins |
Nos |
MW |
CCA |
Lohit |
10 |
10250 |
— |
Siang |
21 |
6766 |
— |
Kameng |
14 |
4060 |
— |
Kopili |
7 |
676 |
— |
Teesta |
14 |
3274 |
— |
Sankhosh |
1 |
4000 |
400000 |
Myntdu |
2 |
406 |
— |
Dikhu |
1 |
186 |
— |
Barak |
4 |
2266 |
— |
Dibang |
9 |
8615 |
— |
Tawang |
9 |
2757 |
— |
Subansiri |
3 |
3960 |
— |
Kolodyne |
1 |
460 |
— |
Pare |
3 |
186 |
— |
EAST INDIA
TOR & Environment Clearance status in East India
The region comprises of Bihar, W Bengal, Jharkhand, Chhattisgarh and Orissa. Among all regions, the least number of projects came to EAC from Eastern region at 20. Interestingly, not one project from Jharkhand has come to the EAC in this period. However, TOR clearance given for the 16.54 lakh CCA in this region is highest among all states and total proposed CCA among all regions is second highest for the Eastern region. This highest contribution for this large CCA from the Eastern region is coming from the proposed Saptakoshi High Dam at 15 lakh Ha (of which 9.76 lakh ha is supposed to be in India), the project also has the highest proposed installed capacity (3000 MW), but that project is supposed to come up in Nepal and there is little likelihood of the project going ahead in near future.
SN |
Project |
State |
Basin |
I/H/M |
Ins Cap (MW) |
CCA (Ha) |
TOR |
Meeting date |
Env Clearance |
Meeting date |
Total Area Req (Ha) |
Bihar (BH) |
|||||||||||
1 |
Dagmara Hydro Power Project |
BH |
Kosi |
H |
130 |
0 |
Approved |
12/10/2012 |
Waiting |
31/03/2012 |
NA |
2 |
Saptkoshi High Dam[15] |
BH |
Kosi |
M |
3000 |
1500000 |
Approved |
18/09/2008 |
– |
– |
NA |
Chhattisgarh (CG) |
|||||||||||
3 |
Arpa Bhaisajhar Barrage project |
CG |
Mahanadi |
I |
– |
25000 |
Approved |
26/12/2012 |
|
|
NA |
4 |
Kelo Major Irrigation Project |
CG |
Mahanadi |
I |
– |
22,800 |
– |
– |
Recommended |
17/07/2008 |
NA |
5 |
Kanhar HEP |
CG |
Son |
H |
50 |
0 |
Waiting |
23/03/2010 |
– |
– |
NA |
Orissa (OR) |
|||||||||||
6 |
Khandohota Medium Irrigation Project |
OR |
Brahmani |
I |
– |
350 |
Approved |
19/06/2008 |
|
|
16.8 |
7 |
Rukura Irrigation Project |
OR |
Brahmani |
I |
– |
5750 |
– |
– |
Recommended |
16/10/2008 |
NA |
8 |
Samakoi Irrigation Project |
OR |
Brahmani |
I |
– |
9990 |
Approved |
20/03/2009 |
– |
– |
1064.43 |
9 |
Brutang Major Irrigation Project |
OR |
Mahanadi |
I |
– |
23,300 |
|
|
Recommended |
7/9/2012 |
NA |
10 |
Jeera Irrigation Project |
OR |
Mahanadi |
I |
– |
4800 |
Approved |
21/08/2010 |
– |
– |
831.5 |
11 |
Ong Dam project |
OR |
Mahanadi |
I |
– |
30000 |
|
|
Recommended |
15/11/2007 |
NA |
12 |
Daha Irrigation Project |
OR |
Rushikulya |
I |
– |
270 |
|
|
Recommended |
16/10/2008 |
NA |
13 |
Sindol 1- Deogaon HEP |
OR |
Mahanadi |
H |
100 |
0 |
Approved |
30/04/2011 |
– |
– |
NA |
West Bengal (WB) |
|||||||||||
14 |
Dwarkeshwar Irrigation Project |
WB |
Hoogly |
I |
– |
38,500 |
– |
– |
Recommended |
17/07/2008 |
NA |
15 |
Siddheswari-Noonbeel Irrigation Project` |
WB |
Hoogly |
I |
– |
29,000 |
Waiting |
21/08/2010 |
– |
– |
NA |
16 |
Subarnarekha Barrage Project |
WB |
Subarnrekha |
I |
– |
114,200 |
Approved |
25/09/2009 |
– |
– |
5,500 |
17 |
Rammam stage-III |
WB |
Teesta |
H |
120 |
0 |
– |
– |
Recommended |
19/09/2007 |
72 |
18 |
Teesta Intermediate HEP |
WB |
Teesta |
H |
144 |
0 |
Approved |
16/06/2009 |
– |
– |
NA |
19 |
Teesta Low Dam-V HEP |
WB |
Teesta |
H |
80 |
– |
Waiting |
13/10/2012 |
– |
– |
157.05 |
20 |
TLDP –I & II HEP |
WB |
Teesta |
H |
60 |
0 |
Approved |
16/06/2009 |
– |
– |
NA |
Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available
State-wise Overview of Projects in East India
|
Projects |
Ins Cap |
Irrigation |
Land Req |
Land Req Info available for projects |
State wise Projects |
Nos |
MW |
CCA (Ha) |
(Ha) |
Nos |
Total Projects |
20 |
3684 |
1279960 |
16809.24 |
9 |
West Bengal |
7 |
404 |
181700 |
5729 |
3 |
Orissa |
8 |
100 |
74460 |
1912.73 |
3 |
Bihar |
2 |
3130 |
976000 |
7,595.35 |
1 |
Chhattisgarh |
3 |
50 |
47,800 |
1572.105 |
2 |
Overview of Status of clearance of projects in East India
TOR & EC Status |
Nos |
MW |
CCA |
Land Req |
Land Req Info available for projects |
TOR approved |
10 |
3434 |
1654340 |
15810.185 |
6 |
TOR not approved |
0 |
0 |
0 |
0 |
0 |
TOR Waiting |
3 |
130 |
29000 |
927.05 |
2 |
TOR approved before this committee |
7 |
120 |
120620 |
72 |
1 |
Env Clearance Recommended |
7 |
120 |
120620 |
72 |
1 |
Env Clerance Waiting |
1 |
130 |
0 |
7595.35 |
1 |
Env Clearance not Recommended |
0 |
0 |
0 |
72 |
1 |
Basin-wise overview of projects in East India
Projects on basins |
Nos |
MW |
CCA |
Teesta |
4 |
404 |
0 |
Mahanadi |
6 |
100 |
105900 |
Brahmani |
3 |
0 |
16090 |
Rushikulya |
1 |
0 |
270 |
Kosi |
2 |
3130 |
1500000 |
Hoogly |
2 |
0 |
67500 |
Subernrekha |
1 |
0 |
114,200 |
Son |
1 |
50 |
0 |
WEST INDIA
TOR & Environment Clearance status in West India
49 projects came to EAC from this region (comprising of states of Gujarat, Maharashtra, Madhya Pradesh, Rajasthan and Goa), most of them were irrigation projects, unlike the situation in North and North East India where most projects that came to EAC during the study period were hydropower projects. Out of these, land availability figures are available only for 14 projects, the least % of the total projects compared to all regions. Land availability figure for none of the 20 projects of MP is mentioned in the EAC minutes. Within the region, highest number of 21 projects came from Maharashtra and close second was Madhya Pradesh. Maharashtra incidentally has the largest number (10) of giant lift irrigation schemes coming for approval before the EAC. Two of the biggest projects came up before the EAC were from Gujarat, the Kalpsar (Gulf of Khambat Development Project) and Par Tapi River Link Project. It was strange to see the EAC clearing the Par Tapi Narmada and the Ken Betwa Phase 1 river link proposals, both for TOR clearance. Both are facing strong opposition. Stranger it is to see the EAC noting in a latter meeting that the MoEF has conveyed to NWDA that the Ken Betwa Phase I link proposal cannot be cleared due to huge submergence it will entail in the Panna Tiger Reserve. Why did the EAC not review its decision regarding the TOR clearance in that case? Parwan irrigation project in Chambal basin in Rajasthan is another project that is facing massive opposition on ground, but the EAC has recommended it for final clearance. Even more shockingly, in its meeting on Nov 20, 2008, EAC opined that the Damanganga Pinjal link (involving several massive dams) does not require any environment clearance since it is a drinking water project. Its clear from these decisions how callous has been the treatment of the EAC to such massive projects.
SN |
Project |
State |
Basin |
I/H/M |
Ins Cap (MW) |
CCA (Ha) |
TOR |
Meeting date |
Env Clearance |
Meeting date |
Total Area Req (Ha) |
Gujarat (GJ) |
|||||||||||
1 |
Gulf of Khambat development project |
GJ |
Multiple |
M |
– |
NA |
Waiting |
25/09/2010 |
– |
– |
– |
Maharashtra (MH) |
|||||||||||
2 |
Ajansara Barrage |
MH |
Godavari |
I |
– |
30004 |
Approved |
18/03/2008 |
– |
– |
NA |
3 |
Dhapewada LIS-II |
MH |
Godavari |
I |
– |
67,506 |
Approved |
22/08/2008 |
Recommended |
21/12/2010 |
NA |
4 |
Upper Penganga Project Stage -II |
MH |
Godavari |
I |
– |
28,600 |
– |
– |
Recommended |
2/6/2011 |
NA |
5 |
Upper Pravara Irrigation Project |
MH |
Godavari |
I |
– |
64260 |
Waiting |
20/09/2007 |
– |
– |
3504 |
6 |
Kanhan River Project |
MH |
Godavari |
M |
– |
– |
Approved |
14/05/2009 |
Recommended |
12/11/2011 |
1434.54 |
7 |
Malshej Ghat Pumped Storage Sch |
MH |
Kalu |
H |
600 |
– |
Approved |
22/08/2008 |
– |
– |
511.06 |
8 |
Ekrukh Lift Irrigation Scheme |
MH |
Krishna |
I |
– |
25,240 |
Approved |
17/07/2010 |
– |
– |
NA |
9 |
Expansion of Krishna – Koyna LIS |
MH |
Krishna |
I |
– |
40219 |
– |
– |
Recommended |
16/06/2009 |
NA |
10 |
Janai Shirsai Lift Irrigation Scheme |
MH |
Krishna |
I |
– |
14080 |
Waiting |
22/08/2008 |
– |
– |
NA |
11 |
Jihe Kathapur Lift Irrigation |
MH |
Krishna |
I |
– |
27500 |
– |
– |
Recommended |
8/5/2008 |
218.46 |
12 |
Krishna Marathwada Irrigation Prjct |
MH |
Krishna |
I |
– |
92141 |
Approved |
16/10/2008 |
– |
– |
2819.7 |
13 |
Purander Lift irrigation |
MH |
Krishna |
I |
– |
21500 |
Approved |
15/11/2007 |
– |
– |
NA |
14 |
Shirapur Lift Irrigation Scheme |
MH |
Krishna |
I |
– |
10,000 |
Waiting |
26/12/2012 |
– |
– |
507.43 |
15 |
Thembu Lift Irrigation Project |
MH |
Krishna |
I |
– |
|
– |
– |
Recommended |
19/07/2007 |
NA |
16 |
Wakurde Lift Irrigation Scheme |
MH |
Krishna |
I |
– |
28,035 |
– |
– |
Recommended |
17/07/2010 |
865 |
17 |
Humbarli Pumped Storage Scheme |
MH |
Krishna |
H |
400 |
– |
Approved |
19/08/2009 |
– |
– |
NA |
18 |
Augmnetation Project at Bhira |
MH |
Krishna |
H |
100 |
– |
Waiting |
19/07/2007 |
– |
– |
NA |
19 |
Bodwad Parisar Sinchan Yojana |
MH |
Tapi |
I |
– |
42,420 |
Approved |
17/02/2009 |
Recommended |
19/02/2012 |
1729.64 |
20 |
Kurha Badoda Islampur Upsa |
MH |
Tapi |
I |
– |
14586 |
Approved |
20/03/2009 |
– |
– |
NA |
21 |
Lower Pedhi irrigation project |
MH |
Tapi |
I |
– |
12230 |
|
|
Recommended |
14/12/2007 |
2532 |
22 |
Lower Tapi LIS |
MH |
Tapi |
I |
– |
54500 |
Approved |
30/06/2010 |
Waiting |
26/12/2012 |
6913.25 |
Madhya Pradesh (MP) |
|||||||||||
23 |
Kundaliya Major Irrigation Project |
MP |
Chambal |
M |
– |
– |
Approved |
27/12/2011 |
– |
– |
NA |
24 |
Mohanpura Major Irrigation Project |
MP |
Chambal |
M |
– |
65000 |
Approved |
17/12/2011 |
– |
– |
NA |
25 |
Punasa Lift Irrigation Scheme |
MP |
Narmada |
I |
– |
35008 |
– |
– |
Recommended |
26/05/2007 |
NA |
26 |
Sip Kolar Medium Irrigation Project |
MP |
Narmada |
I |
– |
6400 |
Approved |
12/10/2012 |
– |
– |
NA |
27 |
Upper Narmada Project |
MP |
Narmada |
I |
– |
21276 |
Approved |
18/04/2007 |
Recommended |
19/08/2009 |
NA |
28 |
Halon Irrigation Project |
MP |
Narmada |
I |
– |
16782 |
– |
– |
Recommended |
16/11/2009 |
NA |
29 |
Integrated Raghavpur, Rosara, Basania with Bargi Multipurpose Prjt |
MP |
Narmada |
i |
– |
|
Waiting |
21/08/2010 |
– |
– |
NA |
30 |
Bauras HEP |
MP |
Narmada |
H |
55 |
– |
Waiting |
17/07/2008 |
– |
– |
NA |
31 |
Handia HEP |
MP |
Narmada |
H |
51 |
– |
Waiting |
15/11/2007 |
– |
– |
NA |
32 |
Hoshangabad HEP |
MP |
Narmada |
H |
60 |
– |
Waiting |
17/07/2008 |
– |
– |
NA |
33 |
Lower Goi irrigation project |
MP |
Narmada |
M |
– |
13760 |
– |
– |
Recommended |
14/12/2007 |
NA |
34 |
Morand & Ganjal Complex Irrigation |
MP |
Narmada |
M |
– |
58,052 |
Approved |
21/07/2012 |
– |
– |
NA |
35 |
Chinki Multipurpose Project |
MP |
Narmada |
M |
– |
73,979 |
Approved |
2/6/2012 |
– |
– |
NA |
36 |
Barrage on Gopad River |
MP |
Son |
WS |
– |
|
Approved |
16/07/2011 |
– |
– |
NA |
37 |
Bansujara Dam Project |
MP |
Yamuna |
I |
– |
49,373 |
Approved |
21/07/2012 |
– |
– |
NA |
38 |
Ghogra Minor Irrigation Project |
MP |
Yamuna |
I |
– |
1650 |
Approved |
21/07/2012 |
– |
– |
NA |
39 |
Lower Orr Project[16] |
MP |
Yamuna |
I |
– |
44791 |
Waiting |
26/12/2012 |
– |
– |
NA |
40 |
Ken-Betwa River Linking Project -I |
MP |
Yamuna |
M |
– |
– |
Approved |
21/12/2010 |
– |
– |
NA |
41 |
Pancham Nagar Multipurpose Prjct |
MP |
Yamuna |
M |
– |
– |
Waiting |
17/09/2011 |
– |
– |
NA |
42 |
Bina Complex IMultipurpose Project |
MP |
Yamuna |
M |
– |
– |
Approved |
8/5/2008 |
Waiting |
11/2/2011 |
NA |
Rajasthan (RJ) |
|||||||||||
43 |
Kalisindh Major irrigation project |
RJ |
Chambal |
I |
– |
22,000 |
Approved |
24/11/2012 |
– |
– |
NA |
44 |
Parwan Major Irrigation-cum-DWS |
RJ |
Chambal |
M |
– |
1,31,400 |
– |
– |
Recommended |
21/12/2010 |
NA |
Multi State |
|||||||||||
45 |
Lendi Major Irrigation Project |
MH/AP |
Godavari |
I |
– |
– |
Approved |
20/09/2007 |
Waiting |
12/11/2011 |
2621.42 |
46 |
Bandra Nala Project |
MH/KN |
Krishna |
H |
– |
– |
Approved |
2/6/2012 |
– |
– |
152 |
47 |
Bhandora Nala Project |
MH/KN |
Krishna |
H |
– |
– |
Approved |
2/6/2012 |
– |
– |
286.08 |
48 |
Pale Parmar Nalla Project |
MH/KN |
Krishna |
H |
320 |
– |
Approved |
2/6/2012 |
– |
– |
203.99 |
49 |
Par-Tapi – Narmada Link Project |
MH/GJ |
Multiple |
M |
– |
188414 |
Approved |
14/05/2009 |
– |
– |
7560 |
Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available, LIS: Lift Irrigation Scheme; DWS: Drinking Water Scheme
State-wise Overview of Projects in West India
|
Projects |
Ins Cap |
Irrigation |
Land Req |
Land Req Info available for projects |
State wise Projects |
Nos |
MW |
CCA (Ha) |
(Ha) |
Nos |
Total |
49 |
1586 |
1300706 |
31858.57 |
15 |
MH |
21 |
1100 |
572821 |
21035.08 |
10 |
GJ |
1 |
— |
— |
NA |
0 |
RJ |
2 |
0 |
153400 |
NA |
0 |
MP |
20 |
166 |
386071 |
NA |
0 |
Multi state |
5 |
320 |
188414 |
10823.49 |
5 |
Overview of Status of clearance of projects in West India
TOR & EC Status |
Nos |
MW |
CCA |
Land Req |
Land Req Info available for projects |
TOR approved |
28 |
1320 |
834041 |
24231.68 |
10 |
TOR not approved |
0 |
0 |
0 |
0 |
0 |
TOR Waiting |
11 |
266 |
133131 |
4011.43 |
2 |
TOR approved before this committee |
10 |
0 |
333534 |
3615.46 |
3 |
Env Cl. Recommended |
14 |
0 |
464736 |
3639.91 |
3 |
Env Cl. Waiting |
3 |
0 |
54500 |
2594.64 |
2 |
Env Clearance not Recommended |
0 |
0 |
0 |
0 |
0 |
Basin-wise overview of projects in West India
Projects on basins |
Nos |
MW |
CCA |
Godavari |
6 |
0 |
190370 |
Krishna |
14 |
1120 |
258715 |
Tapi |
4 |
0 |
123736 |
Kalu |
1 |
600 |
0 |
Chambal |
5 |
0 |
218400 |
Multiple |
2 |
0 |
188414 |
Yamuna |
5 |
0 |
95814 |
Narmada |
11 |
166 |
225257 |
Son |
1 |
0 |
0 |
SOUTH INDIA
TOR & Environment Clearance status in South India
SN |
Project |
State |
Basin |
I/H/M |
Ins Cap (MW) |
CCA (Ha) |
TOR |
Meeting date |
Env Clearance |
Meeting date |
Land Req (Ha) |
Andhra Pradesh (AP) |
|||||||||||
1 |
Pranahitha Chevella Sujala – Srvanthi Project |
AP |
Godavari |
I |
– |
663700 |
Approved |
16/06/2009 |
– |
– |
9810 |
2 |
Diversion from Pranahita to Sripada Sagar |
AP |
Godavari |
I |
– |
548000 |
Waiting |
14/12/2007 |
– |
– |
31424 |
3 |
Lower Penganga Irrigation Project |
AP |
Godavari |
I |
– |
19,233 |
Approved |
26/12/2012 |
– |
– |
509.261 |
4 |
Kanthanapally Sujala Sravanthi |
AP |
Godavari |
H |
280 |
304000 |
Waiting |
26/03/2011 |
– |
– |
4170 |
5 |
Polavaram[17] Multipurpose Project |
AP |
Godavari |
M |
NA |
NA |
|
|
Waiting |
17/02/2009 |
– |
6 |
Dummugundem Nagarjuna Sagar tail pond link canal project |
AP |
Krishna |
I |
– |
NA |
Waiting |
22/01/2011 |
– |
– |
– |
7 |
Modernisation of Krishna Delta sys |
AP |
Krishna |
I |
– |
529000 |
– |
– |
Recommended |
14/05/2009 |
– |
Kerala |
|||||||||||
8 |
Pathrakadavu HEP |
Kerala |
Bharatpuzha |
H |
70 |
|
|
|
Waiting |
16/05/2007 |
|
9 |
Pambar HEP |
Kerala |
Cauvery |
H |
40 |
|
Approved |
16/12/2009 |
|
|
45.034 |
10 |
Athirapally HEP[18] |
Kerala |
Chalakudy |
H |
163 |
|
|
|
Recommended |
16/05/2007 |
|
11 |
Achencovil HEP |
Kerala |
Pamba |
H |
30 |
|
Approved |
21/08/2008 |
|
|
|
Karnataka (KN) |
|||||||||||
12 |
Shivasamudram Seasonal Power |
KN |
Cauvery |
H |
270 |
– |
Approved |
29/07/2009 |
– |
– |
70 |
13 |
Kali Pumped Storage Scheme |
KN |
Kali |
H |
600 |
|
Waiting |
20/03/2009 |
– |
– |
|
14 |
Singtalur Lift Irrigation Project |
KN |
Krishna |
I |
– |
77,198 |
Approved |
26/12/2012 |
– |
– |
3171 |
15 |
Sri Rameshwara Lift Irrigation Sch |
KN |
Krishna |
I |
– |
13800 |
– |
– |
Recommended |
16/06/2009 |
353.7 |
16 |
Upper Bhadra Lift Irrigation Prjct-I |
KN |
Krishna |
I |
– |
107265 |
– |
– |
Recommended |
22/10/2009 |
5245.37 |
17 |
Gundia HEP |
KN |
Netravathi |
H |
200 |
– |
– |
– |
Recommended |
21/07/2012 |
1041.64 |
18 |
Shiggaon Lift Irrigation Scheme |
KN |
Varada |
I |
– |
9900 |
Approved |
21/12/2010 |
– |
– |
775 |
19 |
Dandavathy Reservoir Project |
KN |
Varada |
I |
– |
6,933 |
Waiting |
19/02/2012 |
– |
– |
– |
Tamil Nadu (TN) |
|||||||||||
20 |
Moyar Ultimtae Ph-I |
TN |
Cauvery |
H |
25 |
|
Waiting |
22/08/2008 |
|
|
|
21 |
Kundah PPS |
TN |
Cauvery |
H |
500 |
|
|
|
Recommended |
18/04/2007 |
130.5 |
22 |
Inter-Linking of Tambiraparani, Karumeniyar and Nambiyar Rivers |
TN |
Multiple |
I |
– |
17002 |
Waiting |
12/11/2011 |
– |
– |
653.317 |
Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available
State-wise Overview of Projects in South India
|
Projects |
Ins Cap |
Irrigation |
Land Req |
Land Req Info available for projects |
State wise Projects |
Nos |
MW |
CCA (Ha) |
(Ha) |
Nos |
Total |
22 |
2178 |
2296031 |
57398.82 |
13 |
Kerala |
4 |
303 |
0 |
45.031 |
1 |
TN |
3 |
525 |
17002 |
783.82 |
2 |
KN |
8 |
1070 |
215096 |
10656.71 |
6 |
AP |
7 |
280 |
2063933 |
45913.26 |
4 |
Overview of Status of clearance of projects in South India
TOR & EC Status |
Nos |
MW |
CCA |
Land Req |
Land Req Info available for projects |
TOR approved |
7 |
340 |
770031 |
14380.30 |
6 |
TOR not approved |
0 |
0 |
0 |
0 |
0 |
TOR Waiting |
7 |
905 |
875935 |
36247..32 |
3 |
TOR approved before this committee |
8 |
933 |
650065 |
6771.21 |
4 |
Env Cl. Recommended |
6 |
863 |
650065 |
6771.21 |
4 |
Env Cl. Waiting |
2 |
70 |
0 |
NA |
0 |
Env Clearance not Recommended |
0 |
0 |
0 |
0 |
0 |
Basin-wise overview of projects in South India
Projects on basins |
Nos |
MW |
CCA |
Bharatpuzha |
1 |
70 |
0 |
Cauvery |
4 |
835 |
0 |
Chalakudy |
1 |
163 |
0 |
Godavari |
5 |
280 |
1534933 |
Kali |
1 |
600 |
0 |
Krishna |
5 |
0 |
727263 |
Multiple |
1 |
0 |
17002 |
Netravathi |
1 |
200 |
0 |
Pamba |
1 |
30 |
0 |
Varada |
2 |
0 |
16833 |
[2] See Central Water Commission’s National Register of Large Dams, 2012: http://www.cwc.gov.in/main/webpages/NRLD%20FORMAT%202012.pdf
[4] See for example graph on page12 in this document: https://sandrp.in/wtrsect/Water_Governance_in_India_Himanshu_Thakkar_IWMI_Tata_Meet_December2012.pdf
[7] SANDRP had written to EAC about the glaring errors in the minutes of the 60th and 61st meetings of the EAC, pointing out the errors in capacities, names of places and even names of river in the minutes, but the EAC neither acknowledged the letter or errors, nor bothered to correct them.
[9] EAC has remained on rather steep learning curve on a number of issues, including on Environmental flows. It first questioned the wisdom or need for e-flows, than graduated to recommending 10% of minimum lean season flow, than 15%, later changing to 20% and now it has a little more detailed norms, still far from asking for actual assessment for each river stretch.
[10] See for details: https://sandrp.in/hydropower/Ruspiabagar_Khasiabara_HEP_Ulhas_Karanth_Com_Report_Extracts_Nov2012.pdf
[11] Both the documents authored by Himanshu Thakkar and Bipin Chandra Chaturvedi, Bipin has done the detailed compilation for the two documents. Thanks a due to Parineeta Dandekar (for all the charts in addition to valuable comments, Dr Latha Anantha, Shripad Dharmadhikary and Neeraj Vagholikar for some very useful comments and suggestions.
[13] Clearance sought for adding the third 42 MW unit to the existing 84 MW project.
[14] The project is listed here since it came back before the EAC in Feb 2010 as it had yet to get NBWL clearance.
[15] The TOR clearance was only for the irrigation component in India, the main dam, barrage and headwords will all be in Nepal, which is beyond the jurisdiction of EIA notification 2006 of India.
[16] Part of Ken Beta Link River Link project phase II
[17] The Polavaram project got Environment Clearance in Oct 2005, however, came back to EAC for clearance of the embankments in Orissa and Chhattisgarh as these were not part of the proposal cleared by EAC. The Ministry of Environment and Forests had asked the project authority to get these components cleared and hence the embankment portion came to EAC for clearance. The EAC noted that there has been no public hearings conducted in Orissa and Chhattisgarh as required under EIA notification and asked project authorities to come back to EAC after conducting the public hearings. The project authorities have yet to comply with this requirement and hence the clearance to the project is yet to be recommended by the EAC.
[18] The Athirapally project, following directions by Kerala High Court to KSEB (the MoEF show cause notice of Jan 4, 2010 could also be a factor, but there is no mention of that in the EAC minutes), came back before EAC in March 2010 and was again discussed in April 2010 and July 2010, till when no conclusion could be reached by EAC and EAC had asked for more information and clarifications. There is no mention of the project in any of the subsequent minutes of meetings.