Dams

The Expert ‘Approval’ Committee has zero rejection in six years

 

Analysis of MoEF’s EAC on River Valley ProjectsImage

 

 

Introduction Following the implementation of EIA notification of Sept 2006, the Ministry of Environment & forest (MoEF) has constituted different committees for the appraisal of various developmental projects including River Valley & Hydroelectric projects. The committees are called as Expert Appraisal Committees (EAC). The EAC for River Valley & Hydroelectric projects has had 63 meetings till date from the date of constitution of Committee in April 2007 to the latest meeting in Dec 2012. The committee generally recommends for any River Valley projects, at first stage the Terms of Reference (TOR) for the Environment Impact Assessment (EIA) to be carried out for the proposals along with permission for pre construction activities or works related to survey and investigation.

 

Figure 1: Stage 1 clearance figures across India

 

Model TOR The MoEF has also put up what the Ministry calls “Model TOR for River Valley and Hydroelectric Projects”, but when you click on the link[1], it opens into a document that is titled, “Model TOR for Hydropower Projects”, it does not even claim to be a model TOR for any other river valley projects. This is a big lacuna, since over 95% of India’s large dams are irrigation projects[2], not hydropower projects. Moreover, substantial proportion of the projects coming before the EAC is irrigation projects, including river linking projects. Not having a Model TOR for such projects is a big gap. This does not mean that the Model TOR given on the MoEF website is adequate or comprehensive. Only to illustrate, the Model TOR does not look into the impacts of the various integral components of the hydropower projects like colonies, roads, mining, blasting etc that the hydropower projects invariably have. Model TOR does not look at the social, environmental, economic or cultural services that a river provides. On downstream impacts, the model TOR says under Impact Prediction, “Downstream impact on water, land & human environment due to drying up of the river in the stretch between dam site and powerhouse site.” This completely negates the impacts that the project would have either on the upstream or in the river downstream from the power site or along the tributaries both upstream and downstream of the projects. Nor does it mean that these grossly inadequate Model TOR is followed by the developers. Even the ministry or the EAC does not bother to check if the EIA submitted to them follows either the specific TOR given to the project or the Model TOR on the MoEF website.

 

Environment Clearance At the next stage, the EAC considers the projects for the Environment Clearance (EC), at this stage the EIA is supposed to have been conducted as per the approved TOR and the public hearing is also supposed to have been conducted as per the norms set in the EIA notification of Sept 2006. The EIA notification is issued under the Environment Protection Act, 1986. We have tried to analyse the recommendations of the EAC from the minutes of 63 meetings for the period April 2007 to Dec 2012.


The EAC members The reconstituted EAC in April 2007 was headed by Shri P Abraham, former Power Secretary. Over the years, EAC included members like Dr Sanchita Jindal, Dr A R Yousuf, Dr OP Sisodia, Dr Dinesh Kr Alva, Dr. Dulal Goswami, Prof D K Paul, Dr (Mrs) Usha Bhat, Dr Bithin Datta, Dr Pushpam Kumar, Dr. Devendra Pandey (chairman of EAC from Aug 2009 to April 2010, current Chairman took over as chairman during 38th meeting held on June 30, 2010), none of them are members of the EAC for RVP currently. The member representing Central Water Commission in the EAC included R K Khanna, R K Singh, N Mukherjee but has been changing over the years and full list of their names is not available. Shri P Abraham resigned following our letter to the then Union Minister of State for Environment and Forests (Independent Charge) Shri Jairam Ramesh, showing the conflict of interests involved in he being on the board of a number of hydropower companies whose projects came up for clearance before the EAC chaired by him.

 

The current composition of EAC for RVP is as follows (as per MEF website[3] as on Jan 30, 2013):

 

S.No.

Name & Address

Role in Committee

1

Shri. Rakesh Nath, C-1/29, Bapa Nagar New Delhi-110 003

Chairman

2

Dr. B.P Das, 717 Saheed Nagar Bhubaneswar -751007

Vice-Chairman

3

Dr .A. K. Bhattacharya, Flat No-805,Pocket-3,Akshardham Apt. sec-19 Dwarka New Delhi-110075

Member

4

Chief Engineer(Hydrology), Central Water Commission, Sewa Bhawan, R.K. Puram,New Delhi-110 066

Member

5

Dr. Jyoti Kumar Sharma, Professor School of Environment & Natural Resources 14/15, Old Survey road Dehradun-248 001 Uttrakhand

Member

6

Dr. K.D. Joshi, Principal Scientist and Head Central Inland Fisheries Research Institute Regional Centre Allahabad Uttar Pradesh

Member

7

Dr. Praveen Mathur, Associate Professor & Head Department of Environmental Science P-5, Professor’s Colony MDS University Campus Ajmer-305 009 Rajasthan

Member

8

Dr. S Bhowmik, 40 C, Pocket 1, Sector 10, Dwarka, New Delhi

Member

9

Dr. Surendra kumar Mishra, Department of Water Resources, Development & Management, Indian Institute of Technology, Roorkee – 247667

Member

10

Dr. (Mrs.) Maitreyee Choudhary, Professor & Director, Centre for Himalayan Studies, University of North- Bengal, W.B.

Member

11

Prof. (Dr.) Dhananjai Mohan, Wildlife Institute of India, Dehradun, 248 001 Uttarakhand

Member

12

Prof. Arun Kumar, Department of Earth Sciences, Manipur University, Imphal, 795003, Manipur.

Member

13

Prof. S. K. Mazumdar, 242, FF, Sidharth Enclave Ashram Chowk New Delhi-110 014

Member

14

Sh. B B Barman, MOEF, Paryavaran Bhavan, New Delhi

Member Secretary

 

In addition to the above, Dr P V Subba Rao (Scientist from MoEF) is listed as EAC member in the minutes of the meetings. Interestingly, he, Dr B P Das and Dr A K Bhattacharya seem to be constant members of the EAC throughout the period under study.

 


Role of MoEF All the comments about the EAC here apply equally to the Union Ministry of Environment and Forests as two officials of the ministry have always been part of the EAC, including the member secretary of the EAC. In fact MoEF has a greater role in selection of the chairman and members of the EAC, deciding what projects should be put on the agenda, what happens after the EAC recommendations, ensuring that all the required information about the projects on the agenda is available and is in public domain, encouraging EAC to invite to EAC meetings individuals and groups who have written to EAC and MoEF on substantial aspects, and otherwise setting the policies and norms for the EAC and projects. The MoEF performance has been pathetic. Even now it’s not possible to even know the status of the clearances of the projects from the MoEF website, even though it is statutory requirement for MoEF (under EIA notification 2006) to display the clearance letters on its website. In Feb 2012 Central Information Commission (CIC) directed MoEF under the Right to Information Act 2005 to put all the documents submitted by the project developers for clearance, at least ten days before the projects are considered by the EAC. When this was not followed, SANDRP wrote to CIC and CIC issued notice to MoEF. This is still to be followed by MoEF fully. Now some of the documents are put up on the website before the EAC meetings, this is not the case even for the 63rd and 64th meetings of EAC. The EAC, in spite of repeatedly writing to them on this violation of the CIC directions, did not take steps to ensure that CIC directions are fully complied with for the projects that come up before the EAC.

 

Even though MoEF may be equally if not more responsible for the various violations listed here, that does not reduce the responsibility of the EAC members. Once someone is selected as EAC member, he or she has the duty to ensure basic norms in functioning of the EAC. Evidence presented here shows if the EAC members have succeeded in achieving even basic norms in governance of EAC.

 

Results and Analysis

 

The Union Ministry of Environment and Forests’ (MoEF) Expert Appraisal Committee (EAC) on River Valley and Hydroelectric Projects (RVP) has considered a total of 262 hydropower and irrigation projects in close to six years since April 2007 when the new committee was set up to its latest, 63rd meeting in December 2012. It has not rejected any project in this period. Even in case of the two projects that it declined to recommend clearance for the Terms of Reference (TOR) of their Environment Impact Assessment (EIA), it has basically asked the developers to come back with reformulated proposals. It seems the committee is actually an Expert Approval Committee, since it seems to have expertise in approving rather than appraising the projects objectively.

 

EAC has strong pro project and anti people bias The Committee has shown its strong bias for the projects. Many groups from all over India have sent hundreds of submissions to the EAC over these years. The committee has never called any of the groups for the meetings where the specific projects on which groups have sent submissions. The EAC has never even acknowledged any of such submissions in the minutes of the meetings. In case of some of the recent submissions from SANDRP and others, the chairman of the EAC wrote back saying that this will be discussed in the next meeting, but there has been no mention of such submissions in the minutes of the EAC meetings. The EAC has shown its strong bias against people, environment and all those who represent the interests of the local communities and environment. In February 2012 some of us were invited for a discussion with the EAC, but we saw little impact of our discussions on the functioning of the EAC.

 

 Opposition to Dams on Teesta, many of which are cleared by the EAC Photo: Affected Citizens of Teesta

 

The table below gives an overview of the situation of TORC (Terms of Reference Clearance) and EC (Environment Clearance) for the projects cleared by the EAC on RVP between April 2007 (when the then newly constituted EAC met for the first time) to its 63rd meeting as in December 2012. The table shows that the EAC has not rejected any of the projects for EC. As against the 211 projects considered by the EAC for TORC, it (only temporarily) rejected TORC for two projects. Hence its rejection rate for TORC is less than 1%. EAC’s rejection rate of environment clearance is nil as it has never rejected any project that has come to it for environment clearance. It seems the EAC for RVP has been basically rubber stamping approval for every project that comes their way. The EAC was expected to do much better than that, as it clear from the reading of EIA notification of Sept 2006, following which the EAC was set up.

 

 

Overview of Clearance status across India

 

Region

Projects for TORC

Projects for EC

Total projects considered

TORC given

TORC Rejected

Projects considered for TORC

EC given

EC rejected

Projects considered for EC

North

50

1 (300 MW)

57

31

0

34

72

North East

70

1 (420 MW)

87

17

0

19

99

East

10

0

13

7

0

8

20

West

28

0

39

14

0

17

49

South

7

0

14

6

0

8

22

Total

165

2

210

75

0

86

262

 

Temporary rejections for two TORC Only two projects were rejected TORC. Among these, for the 420 MW Kameng Dam, the EAC rejected the proposal from KSK Ltd, since the submergence area was just 350 m from Pakke Tiger Reserve. The EAC however, said, “The Committee suggested that possibilities of locating a suitable site on Kameng River, upstream of confluence of Bichom & Kameng may be explored.” So the project is likely to come back to EAC. It is surprising, however, that another project in the same basin, namely the 1120 MW Kameng I on Bhareli / Kameng River in East Kameng district in Arunachal Pradesh came before the EAC during its first meeting in April 2007. The minutes of the EAC meeting clearly says about this project, “A part of the submergence area falls under the Pakke Tiger Reserve.” And yet the EAC gave TOR clearance to the project! Inconsistency seems to be the first name of the EAC.

 

Similarly the 200 MW Bara Bangahal HEP in Kangra district in Himachal Pradesh was accorded TOR clearance in 21st meeting of EAC in Dec 2008, even as the minutes recorded, “The project is located within the wildlife sanctuary.” Similarly the 76 MW Rambara project on Mandakini River in Rudraprayag district in Uttarakhand, just 6 km from Kedarnath, was given TOR approval in the 19th EAC meeting in Oct 2008 even as the minutes noted, “The whole project is located within Kedarnath Musk Deer Sanctuary.”

 

Thousands of Monks opposing dams in Tawang, Arunachal cleared by the EAC Photo: Seven Sisters Post

 

Similarly while rejecting the TORC for the 300 MW Purthi HEP in Lahaul and Spiti District in Himachal Pradesh, the EAC said, “The Committee concluded that the project proponent and Govt. of Himachal Pradesh may review and revise the proposal in the light of the above observations for reconsideration.” So it is clear in this case too that the rejection is temporary. In reality, the EAC has rejected none of the projects that came to it for clearance.

 

Massive hydropower capacity cleared The EAC for RVP basically considers hydropower projects having installed capacity over 50 MW, projects of 25-50 MW going to the state Environment Impact Assessment Authorities and those below or requiring any environment clearance under EIA notification 2006. The table below shows that in less than 6 years, the EAC has recommended TORC for hydropower projects proposed with installed capacity of 49458 MW, which is about 25% more than what India has installed in about 66 years since independence.

 

 

Status of clearance for Hydropower Projects

 

Region

Capacity for which TORC given, MW

Capacity for which EC given, MW

Capacity of projects considered, MW

North

12823

6843.5

18087.5

North East

31541

8258

46658

East

3434

120

3684

West

1320

1586

South

340

863

2178

Total

49458

16084.5

72193.5

 

Figure 2: Zone wise status of Environment Clearance

 

During the period, the EAC has recommended EC for hydropower capacity of 16084.5 MW, which is about three times the hydro capacity of 5544 MW added during the just concluded 11th five year Plan. EAC has recommended all these clearances without giving any consideration to carrying capacity, cumulative impact assessment, democratic decision making, sustainable development criteria, full and proper social and environment impact assessment or desirability of such capacity addition, including from climate change perspective.

 

Opposition to 775 MW Luhri Project cleared recently by EAC Photo: Himdhara

 

Zero rejection for irrigation projects The EAC for RVP considers irrigation projects with Cultivable Command Area (CCA) above 10 000 Ha. In the table below are the region wise details of the TORC and EC recommended by EAC for the Cultivable Command Area figures of the major and medium irrigation projects.

 

During the period under study (Apr 2007 to Dec 2012), EAC has given TORC for 3.28 million ha of CCA and EC for 1.59 million Ha of CCA. Here we should note that since 1991-92, there has been no addition to the net area irrigated by major and medium irrigation projects at all India level as per Govt of India figures[4]. In light of that fact and considering the overcapacity already built into a number of basins across India already, such clearances by EAC are highly questionable.

 

Status of clearance for Irrigation Projects

 

Region

CCA for which TORC given, L Ha

CCA for which EC given, L Ha

CCA of projects considered, L Ha

North

2.02

3.53

6.17

North East

0

0

4.00

East

11.30

1.20

12.80

West

8.34

4.65

13.01

South

7.70

6.50

22.96

Total

29.36

15.88

58.94

 

Land requirement Full details of the land required for the projects are never properly assessed by the EIAs. The EAC minutes reflect only indicative figures of land requirement of some of the projects considered by the EAC as mentioned in the EIAs.

 

Figure 3: Zone wise status of Stage 1 clearances (TORC)

 

Land required for the projects considered by EAC

 

Region

No of projects for which land requirement figures are available

Land required for the projects in previous column

North

62

29932.77 Ha

North East

72

76768.27 Ha

East

9

16809.24 Ha

West

15

31858.57 Ha

South

13

57398.82 Ha

Total

171

212767.67 Ha

 

Following table gives an over view of land requirement for some of the projects as mentioned in the EAC minutes. Based on available figures, the Highest land requirement in a state is for Andhra Pradesh, at 45913.26 ha the second rank state is Arunachal Pradesh with land requirement of 35485.3 Ha. Arunachal being smaller and hilly state and most of the land being required are forested and close to the rivers, the impact in Arunachal Pradesh would be much greater. Based on above information, for the projected land requirement for the 262 projects considered by the EAC during the period under study would come to over 325995 Ha. However, these land requirement figures are gross under estimates and too much need not be read into them.

 

The flawed functioning of EAC It has not mattered to the EAC that the EIAs of the projects that come to it are shoddy, dishonest, cut and paste jobs. The Committee has not rejected a single EIA, even through evidence was repeatedly presented to the committee about shoddy nature of the EIAs. It has not mattered to the committee that there has been no credible public consultation process and there have been serious anomalies in public hearing processes. The committee did not order fresh public hearings even when evidence was provided to it about serious violations in public hearing processes.

 

Figure 4: Zone wise figures of TORC and EC given for hydropower installed capacities

 

Even when the committee asked for fresh studies or significant changes in EIA, it did not ask the project proponent to go back for fresh public hearing. It has not mattered to the committee that EIAs of the projects it cleared did not have full year round ground level surveys, did not have full social impact assessment, did not have downstream impact assessment, did not have options assessment to establish that the proposed project was least cost option, did not have assessment of impacts due to blasting of tens of kilometer long tunnels, did not have proper flora or fauna studies, did not include impact of the project on rivers and the services provided by the river or impact on downstream projects or flood plain use, or had used flawed, false or inconsistent data base.

 

 

Figure 5: Zone wise figures of TORC and EC given for irrigated area CCA in lakh Ha

 

SANDRP had put together a detailed submission[5] and mobilized endorsements of large number of concerned groups and individuals, including over ten eminent scientists on World Fisheries Day on Nov 21, 2012 and sent to EAC, raising issues concerning riverine fisheries in functioning of the EAC and suggesting specific measures to improve the same. The chairman of the EAC wrote back to SANDRP that this will be discussed in the next meeting of EAC, but there was no mention of it in the minutes of the EAC, nor any concrete action taken by the EAC after that. Earlier in November 2012, SANDRP had organized a side event on issues related to riverine biodiversity in India at the Hyderabad Conference of Parties of Convention on Biodiversity. Considering the importance of the issue for the functioning of the EAC, we had invited the members, including the Chairman and member secretary for the side event. No one came.

 

 Figure 6 Overview of State-wise installed capacities of HEPs considered by EAC in North India

 

No appreciation of Cumulative Impacts It has not mattered to the committee that there has been no Cumulative Impact Assessment (CIA) when  large number and bumper to bumper hydropower projects are proposed on number rivers including Bhagirathi, Alaknanda, Mandakini, Sutlej, Ravi, Beas, Chenab, Teesta, Lohit, Tawang, Siang, Subansiri, Narmada, to name only a few. It does not matter to them that there is no flowing river between two projects, it has recommended clearance to Luhri HEP most recently with zero flowing river length with both immediately upstream (Rampur HEP) and immediate downstream (Kol dam) projects.

 

 

Figure 7 Basin-wise overview of number of Hydro Projects considered by EAC in North India

 

Even in few cases that the EAC has asked for CIA, it has asked the CIA to be done by an agency like WAPCOS Ltd that has an abysmally poor track record in doing such studies and it has serious issues of conflict of interests since the agency is also involved in feasibility studies and detailed project reports as part of its business model. But EAC has never understood these concerns. Nor has the EAC really bothered to look at the quality of the CIA. Most significantly, the EAC refused to wait for the CIA report of a basin before considering individual projects in such basins, showing its complete lack of understanding of the importance of CIA.

 

Section 9 of the Form I (the developer is supposed to apply for stage I clearance with this form duly filled in, as per Para 6 of the notification)) prescribed in Annexure 1 of the EIA notification of Sept 2006 is supposed to be about “Factors which should be considered (such as consequential development) which could lead to environmental effects or the potential for cumulative impacts with other existing or planned activities in the locality”. Section 9.4 under this reads: “Have cumulative effects due to proximity to other existing or planned projects with similar effects”. So even legally the EAC and MoEF are supposed to look at the cumulative impact assessment issues under the EIA notification, both at scoping at appraisal stage, which they are clearly not doing.

 

Here it may be noted that recommending Environment clearance without first undertaking carrying capacity and cumulative impact assessment is in violation of Supreme Court order in “Karnataka Industrial Areas … vs Sri C. Kenchappa & Ors on 12 May, 2006” which has said:

A. “The pollution created as a consequence of environment must be commensurate with the carrying capacity of our ecosystem. In any case, in view of the precautionary principle, the environmental measures must anticipate, prevent and attack the causes of environmental degradation.”

B. “…the preventive measures have to be taken keeping in view the carrying capacity of the ecosystem operating in the environmental surroundings under consideration.”

C. “The pollution created as a consequence of development must not exceed the carrying capacity of ecosystem.”

 

Without knowing carrying capacity of a basin it cannot be ascertained if the proposed project is “commensurate with the carrying capacity of our ecosystem”, ecosystem in this context is the river basin.

 

 

Figure 8 Overview of Basin-wise installed capacity of HEPs that EAC considered in North India

 

 

Figure 9 State wise overview of installed capacity of HEPs considered by EAC in North East India

 

EAC’s double standards While EAC itself has not rejected any of the proposals that came to it, few, rare environment friendly recommendations that have been made by other committees have also been rejected by the EAC, without any convincing reasons. To illustrate, when the carrying capacity study of the Teesta basin recommended that no projects should be taken upstream of Chungthang in North Sikkim, the EAC in its meeting overturned this decision and decided to consider all such projects. Similarly, the recommendations of the Ganga Basin Cumulative Impact Assessment study by the Wildlife Institute of India, suggesting that at least 24 hydro projects proposed in Ganga basin be dropped and much higher environment flows than those directed by EAC should be mandated, were all rejected by the EAC.

 

The recommendations of the Western Ghats Ecology Panel headed by Prof Madhav Gadgil were also rejected on grounds such as inadequate studies. Overturning the recommendations of the WG Ecology Panel report, the EAC recommended clearance to the controversial Gundia hydropower project in Western Ghats in Karnataka. If the standards applied by the EAC while rejecting the recommendations of all these committees were to be applied to the EIAs and CIAs based on which the EAC approved the projects, than none of the projects approved by the EAC would merit clearances. But the EAC has very lax standards for its own work, and for the EIAs and CIAs that favour projects, but different ones for the reports that recommend rejection of projects. This contradiction is highlighted here only for illustration of double standards of the EAC and it does not mean that the EAC decisions in rejecting any recommendations of any of these committees have any merits.

 

Western Ghats Expert Ecology Panel assessing Ecosystems to be affected by Gundia HEP. EAC recommended clearance to this project despite rejection by WGEEP Photo: India Together

 

It may be noted that the previous chairman (former power secretary Shri P Abraham who chaired EAC till June 2009) had serious conflict of interest issues with he being on board of several power companies whose projects came up before the committee and the current chairman has had no back ground on environment issues. It has not mattered to the committee whether the Environment Management Plans that accompany the EIAs that it clears are implemented or not, or if there is any credible mechanism and legally empowered process in place to ensure its implementation. The EAC has not even shown concern for legal norms that the TOR clearances are valid only for two years. MoEF has recently issued a notification dated Oct 30, 2012[6] that said that project for which the proponents have not come back with the requested additional information for more than six months should be delisted. Luhri project thus should not have been considered by the MoEF from more than one legal point view. MoEF and EAC have yet to follow such notifications of the ministry.

 

The minutes of many of the EAC meetings make pathetic reading, if read carefully. One can find contradictions, inconsistencies, plain wrong facts being mentioned in the minutes of the EAC meetings[7], which are all approved by the EAC. Even when such errors are pointed out, the EAC has not even bothered to correct the mistakes or review its decisions.

 

Cleared by EAC, Rejected by others Many of the projects cleared by the EAC have faced serious road blocks for the shoddy appraisal done by the EAC. For example, the then Union Environment Minister himself decided not to clear the Renuka dam project cleared by the EAC. The Rupsiabagar Khasiabara project cleared by the EAC could not get forest clearance, for many reasons, including the fact that the EIA of the project was found to be so shoddy and wrong, that any other committee would have considered this an insult to its work. The Kotlibhel 1B and Kotlibhel 2 projects, cleared by this committee have been rejected clearances by the Forest Advisory Committee, following recommendation of the Wildlife Institute of India.

 

Figure 10 State wise overview of number of projects considered by EAC in North East India

 

Athirapally hydropower project in Chalakudy basin in Kerala was recommended Environment Clearance by the EAC for the third time (earlier two clearances were quashed by the Kerala High Court) in May 2007, but the project again came back to the EAC in March 2010, following Kerala High Court directions. Earlier on January 4, 2010, following directions from the then Union Environment Minister of State Shri Jairam Ramesh, Dr S Bhowmik, than director in MoEF, issued show cause notice under Environment Protection Act, 1986, to the developer agency, Kerala State Electricity Board, to show cause in 15 days as to why the environment clearance granted to the project should not be revoked and why the direction of closure of the project not be issued. It is not clear if the MoEF took the next step hinted in the notice. Its strange that the EAC, in which the same Dr Bhowmik was member secretary, did not mention the issuance of this notice in the EAC meetings when the EAC discussed this project between March and July 2010. There is no mention of the MoEF show cause notice in the minutes of the EAC meetings held during the period.

 

Figure 2 Athirappilly Water Falls at the proposed Athirappilly HEP site Photo: Southernsojourns

 

Several projects cleared by the EAC stand challenged in the National Green Tribunal, some of them (e.g. Renuka dam) have got a Stay Order. The World Bank too finds the EIAs based on which the EAC cleared the projects so poor that it has asked for fresh EIAs for the projects it wants to fund (e.g. Rampur and Vishnugad Pipalkoti hydropower projects).

 

 

Figure 11 Basin wise overview of number of projects considered by EAC in North East India

 

Climate Change It is well known that the worst impacts of climate change is going to be felt in terms of impacts on water resources. It is also well known that the natural resources like the biodiversity, forests, rivers, wetlands, fertile flood plains and riverine lands are some of the important resources that would help us adapt to the climate change impacts. Hydropower and dams that the EAC considers adversely affect all of these natural resources. It is well established that large sections of people of India who depend on such natural resources are the poorest and most vulnerable to climate change impacts and when the resources that these vulnerable sections depend on are destroyed by the hydropower projects and dams that the EAC appraises, the committee would be expected to consider the climate change context. Consideration of climate change context is thus important from several angles while appraising the river valley projects. It’s also well established now that past is not the best guide while estimating river water flows. Research over the last two decades have also established that reservoirs in a tropical country like India would also be source of methane and CO2 emissions, methane being about 21 times more potent in global warming terms than CO2. In view of all this, one would have expected elaborate discussion of climate change issues in the functioning of the EAC. One would expect the EAC to mandate the EIAs and CIAs to look at these issues comprehensively.

 

Unfortunately, we are disappointed on every one of these counts. We find little mention of climate change issues in the work of the EAC. In fact the model Terms of Reference for the hydropower projects put up on the MoEF website[8] does not have the word “climate” in it, leave aside “climate change”.

 

E-flows For Hydroelectric and River valley Projects which dewater and divert rivers entirely or partially and change its natural hydrograph, EAC has now[9] been arbitrarily recommending release of 20% of average lean season flow for lean months, between 20-30% e-flows (short for Environmental flow) for non-lean, non-monsoon months and 30% average monsoon flow for monsoon flows. This standard is entirely arbitrary, without any scientific, ecological or sociological basis, blanket for all rivers from Himalayan to peninsular.

 

This too has happened not suo motto, but after huge pressure from civil society and various other committees. And when the proponent says it cannot release these inadequate flows, EAC is actually ready to negotiate, which is acceptable between the EAC and the proponents (like in the case of 300 MW Alaknanda HEP by GMR Energy). Like any negotiation in a fish or vegetable market. While taking these decisions, EAC has never recommended that a more holistic and participatory method for assessing e-flows needs to be developed. Or that certain rivers needs to be left undammed. Even when other committees like the Wildlife Institute of India have recommended higher e-flows, the EAC or MoEF has refused to follow such recommendations.

 

Figure 12 State wise overview of number of Projects considered by EAC in East India

 

Biodiversity Violating the National Biodiversity Act of 2002, EAC does not ask for Biodiversity Impact Assessment of projects, does not think twice while recommending clearances to projects affecting severely threatened, endemic and endangered biodiversity and RET (Rare Endangered Threatened) species. This has had disastrous impacts for critically endangered fauna like Black Necked Cranes, Red Pandas (780 MW Nyamjangchu HEP), Several endemic species including Gundia Indian Frog (200 MW Gundia HEP), Snow Leopard (Projects in Upper Ganga including 300 MW Alaknanda HEP), Gangetic Dolphin (Upper Ganga and Brahmaputra Projects), Bengal Florican (1750 MW Lower Demwe Project), Fish like Golden Mahseer, Snow Trout (most dams in Himalayas and North East) to name a very few.

 

Figure 13 Basin wise overview of number of projects considered by EAC in East India

 

Even while noting in the 56th meeting of EAC, while discussing the 775 MW Luhri HEP on Sutlej river in Himachal Pradesh, that as per the EIA of the project, “However, 21 species are listed in the Red data book of Indian plants”, the EAC does not even bother to enquire about which are these plants and why decide to sacrifice their loss. While discussing Shongtong Karcham hydropower project, the EAC noted in the minutes of the 30th meeting of EAC, “Considering the presence of 51 species of fish in the upper reaches of Sutlej, it is reported (in EIA) that only three species of fish were found in the study area”. But amazingly, the EAC has no qualms in accepting such fundamentally flawed EIA. Two of these species are simply human intervention.

 

Dibru Saikhowa National Park and its endangered species are thretened by the 1750 MW Lower Demwe Dam on Lohit cleared by EAC Photo: assam Portal

In case of the Rupsiabagar Khasiabara Hydro Power Project in Uttarakhand[10], the EIA report prepared by the WAPCOS to obtain Environment Clearance for the RKHPP reports presence of  only 8 bird species. The EAC actually gave clearance to the project without raising any issues of the flawed EIA. The Inspection Report of the Sub-Committee of the Forest Advisory Committee to assess wildlife values and ecological impact of the project, led by Dr Ullas Karanth makes interesting reading.

 

 

Figure 14 State wise over view of number of projects considered by EAC in West India

 

 

Figure 15 Basin wise overview of number of projects considered by EAC in West India

 

 

Figure 16 Basin wise overview of CCA of Irrigation Projects considered by EAC in West India

 

The Inspection Report noted, “However, as per the existing literature a total of 228 bird species in 30 families and 118 genera, representing more than 45% of the breeding bird diversity of the Western Himalaya and nearly 55% of breeding bird species of the kumaon  Himalaya are recorded in the region. Ten species of pheasants are found in the area, including Himalayan monal, and the Koklass pheasant, and several other altitudinal migrants. This assemblage represents 6 out of seven West Himalayan endemics found in Kumaon.” But the EAC did not even note any of these flaws of the EIA and obediently cleared the project. The project currently stands cancelled after the sub committee recommended that the project be rejected forest clearance. All this shows how little significance is of biodiversity for the EAC and MoEF.

 

Regional and detailed analysis These conclusions are based on analysis of the agenda and minutes of 63 meetings of EAC spread over close to six years from April 2007 to December 2012, done by South Asia Network on Dams, Rivers & People (www.sandrp.in)[11] in light of other related information and experiences. SANDRP has been monitoring the functioning of the EAC over the years, has been writing to the EAC about its concerns and also those of partner organisations about specific projects and general functioning of the EAC. This analysis is based on this experience and we hope it will be useful for all concerned.

 

In what follows we have given region wise status and analysis of the project wise clearances recommended by the EAC for RVP for the five regions of India, namely: North, North East, East, West and South. The tables for each region give state wise list of projects with some basic features of the projects. An overview of number of projects and their capacities is given in tables that give status wise, state wise and river basin wise figures for the projects that EAC considered in these six years.

 

Figure 17 State wise Overview of hydropower installed capacities considered by EAC in South India

 

 

Figure 18 Overview of Irrigation Projects: Culturable Command Area (CCA) of Projects in South India

 

In an accompanying document[12], also from SANDRP, we have given more details for each project and date-wise decisions of the EAC for each of the projects on EAC agenda. We are hopeful that these two documents will be helpful in giving clear picture about functioning of the EAC to all concerned.

 

We should add here that these two documents are only limited to giving a picture about functioning of the Expert Appraisal Committee on River Valley Projects. There are many other equally serious problems plaguing the environmental governance of River Valley Projects in India, they will require separate work.  

 

NORTH INDIA

TOR & Environment Clearance status in North India

 

Following table gives project wise information about basic features and clearance status for the projects that came to EAC from North Indian states of Jammu and Kashmir, Haryana, Punjab, Himachal Pradesh, Uttar Pradesh, Delhi and Uttarakhand. The maximum no of projects are (34) from Himachal Pradesh among all states, Uttarakhand coming second with 25 projects. Jammu and Kashmir has less no of projects at 11, but the proposed installed capacity of the J&K projects is highest at 7573 MW. The land requirement is also highest in J&K among North India states at over 10170 Ha. Among all regions, the EAC has given the highest number of environment clearances in North India.

 

SN

Project

State

Basin

I/H/M

Ins Cap (MW)

CCA (Ha)

TOR

Meeting date

Env Clearance

Meeting date

Total Area Req (Ha)

Haryana

1

Dadupur – Nalvi Irrigation Project

Haryana

Yamuna

I

92532

Approved

16/05/2007

Recommended

16/06/2009

NA

2

Hansi – Butana Link Channel

Haryana

Yamuna

M

232024

 

Waiting

19/07/2007

553.21

Himachal Pradesh (HP)

3

Dhaulasidh HEP

HP

Beas

H

66

Approved

22/04/2010

Recommended

23/11/2012

NA

4

Lambadug HEP

HP

Beas

H

25

 

Recommended

22/08/2008

9.7914

5

Nakthan HEP

HP

Beas

H

520

Approved

20/12/2010

97.76

6

SAINJ HEP

HP

Beas

H

100

Approved

22/06/2007

Recommended

20/03/2009

56.763

7

Thana-Plaun HEP

HP

Beas

H

141

Approved

7/9/2012

497

8

Triveni Mahadev

HP

Beas

H

78

Approved

7/9/2012

482

9

Chhatru HEP

HP

Chenab

H

108

Approved

8/5/2008

Waiting

28/04/2012

95.26

10

Dugar HEP

HP

Chenab

H

380

Approved

12/10/2012

NA

11

Gondhala HEP

HP

Chenab

H

144

Approved

16/10/2008

214

12

Gyspa HEP

HP

Chenab

H

300

Approved

26/03/2011

1635

13

Miyar HEP

HP

Chenab

H

120

Approved

25/09/2010

Recommended

12/11/2011

69.94

14

Purthi

HP

Chenab

H

300

Not approved

23/11/2012

72

15

Reoli–Dugli HEP

HP

Chenab

H

420

Approved

26/12/2012

182

16

Sach Khas HEP

HP

Chenab

H

267

Approved

24/11/2012

102.48

17

Seli HEP

HP

Chenab

H

400

Approved

19/02/2012

Recommended

1/6/2012

292.9654

18

Telling HEP

HP

Chenab

H

94

Approved

23/11/2012

83

19

Bajoli Holi

HP

Ravi

H

180

Approved

16/01/2008

Recommended

21/12/2010

85.7

20

Bara Bangahal HEP

HP

Ravi

H

200

Approved

16/12/2008

53.64

21

Chanju-I HEP

HP

Ravi

H

36

 

Recommended

26/02/2011

NA

22

Kutehar HEP

HP

Ravi

H

260

Approved

7/5/2008

Recommended

21/01/2011

85.36

23

Chango-Yangthang HEP

HP

Sutlej

H

180

Approved

8/9/2012

146

24

Lara Sumta

HP

Sutlej

H

104

Approved

12/10/2012

97.75

25

Luhri HEP

HP

Sutlej

H

775

Approved

18/04/2007

Recommended

24/11/2012

380

26

Shongtong-Karcham HEP

HP

Sutlej

H

402

Approved

16/08/2007

Recommended

18/02/2010

79.17

27

Sumte Kothang

HP

Sutlej

H

130

Approved

12/10/2012

110

28

Tidong -I

HP

Sutlej

H

100

 

Recommended

16/08/2007

46.66

29

Tidong -II

HP

Sutlej

H

60

Waiting

29/07/2009

164.53

30

Yangthang – Khab HEP

HP

Sutlej

H

261

Approved

16/06/2009

1532.6

31

Chirgaon-Majhgaon HEP

HP

Yamuna

H

60

Approved

24/11/2012

31.58

32

Dhamwari Sunda HEP

HP

Yamuna

H

70

Approved

28/07/2009

Recommended

15/07/2011

23.3025

33

Renuka Dam Project

HP

Yamuna

M

40

Approved

16/08/2007

Recommended

28/07/2009

1532.6

34

Rupin

HP

Yamuna

H

45

Approved

24/11/2012

27

Jammu & Kashmir (JK)

35

Baglihar stage- II HEP

JK

Chenab

H

450

Approved

22/04/2010

Recommended

8/9/2012

NA

36

Bursar HEP

JK

Chenab

H

1500

Approved

2/6/2012

1665

37

Kirthai HEP

JK

Chenab

H

250

Approved

8/5/2008

290

38

Kirthai Stage-II HEP

JK

Chenab

H

990

Waiting

31/03/2012

NA

39

Kiru HEP

JK

Chenab

H

600

Approved

22/08/2008

295

40

Kwar HEP

JK

Chenab

H

520

Approved

19/02/2010

326

41

Pakal Dul  HEP

JK

Chenab

H

1000

 

Recommended

7/1/2008

1163.898

42

Ratle HEP

JK

Chenab

H

690

Approved

27/12/2011

Recommended

21/07/2012

567.22

43

Sawalkote HEP

JK

Chenab

H

1200

Approved

3/6/2011

1099

44

New Ganderbal HEP

JK

Jhelum

M

93

Approved

8/5/2008

Recommended

26/12/2012

63.7

45

Ujh Multipurpose Project

JK

Ravi

M

280

32000

Waiting

13/11/2010

4700

Uttarakhand (UA)

46

Alaknanda Hydro Power Project

UA

Alaknanda

H

300

Recommended

17/01/2008

83.9

47

Bowala Nand Prayag HEP

UA

Alaknanda

H

300

Approved

22/08/2008

64.069

48

Devsari HEP

UA

Alaknanda

H

252

Approved

18/03/2008

Recommended

26/12/2011

223.36

49

Jelam Tamak HEP

UA

Alaknanda

H

128

Approved

28/04/2012

96.27

50

Kotlibhel 1-B

UA

Alaknanda

H

320

Recommended

19/07/2007

550.619

51

Kotlibhel-stage II HEP

UA

Ganga

H

530

Recommended

19/07/2007

676.071

52

Nand Prayag Langasu

UA

Alaknanda

H

100

Approved

25/09/2010

79.8177

53

Phata Byung HEP

UA

Alaknanda

H

76

Recommended

17/01/2008

22.72

54

Rambara HEP

UA

Alaknanda

H

76

Waiting

16/10/2008

17.78

55

Singoli Batwari

UA

Alaknanda

H

99

Recommended

18/07/2007

43

56

Tamak Lata HEP

UA

Alaknanda

H

280

Waiting

21/01/2011

77.26

57

Bhilinagana Project

UA

Bhialangana

H

22.5

Recommended

26/12/2011

NA

58

Bogudiyar-Sirkari Bhyol HEP

UA

Sarda

H

170

Approved

14/05/2009

75

59

Mapang-Bogudiyar HEP

UA

Sarda

H

200

Approved

14/05/2009

70

60

Rupsiabagar Khasiabara HEP

UA

Sarda

H

260

Recommended

17/02/2009

32

61

Sirkari Bhyol Rupsiabagar HEP

UA

Sarda

H

210

Approved

29/07/2009

NA

62

Jamrani Dam Multipurpose Project

UA

Sarda

M

30

150302

Recommended

18/02/2010

529.57

63

Arakot Tiuni HEP

UA

Yamuna

H

81

Approved

21/01/2011

38

64

Hanol -Tiuni HEP

UA

Yamuna

H

60

Recommended

8/5/2008

48.982

65

Jakhol Sankhri HEP

UA

Yamuna

H

45

Approved

15/06/2009

24

66

Lakhwar HEP

UA

Yamuna

H

300

Waiting

12/11/2010

NA

67

Mori- Hanol HEP

UA

Yamuna

H

63

Approved

14/12/2007

45

68

Naitwar Mori HEP

UA

Yamuna

H

60

Approved

22/06/2007

Recommended

27/12/2011

47.05

69

Tiuni Plasu  HEP

UA

Yamuna

H

66

Approved

17/01/2008

 NA

70

Vyasi HEP

UA

Yamuna

H

120

Recommended

16/09/2007

135.425

Uttar Pradesh (UP)

71

Badaun Irrigation Scheme

UP

Ganga

I

53,054

Approved

16/07/2008

Recommended

30/06/2010

5053

72

Arjun Sahayak Pariyojna

UP

Yamuna

I

57000

Approved

18/03/2008

Recommended

19/08/2009

2891

Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available

 

 

State-wise Overview of Projects in North India

 

 

Projects

Ins Cap

Irrigation

Drinking water

Land Req

Land Req Info available for projects

State wise Projects

Nos

MW

CCA (Ha)

MLD

(Ha)

Nos

Total Projects

72

18087.5

616912

145

29932.77

62

HP

32

6366

 

8285.85

29

UA

25

4148.5

150302

145

2979.89

21

J&K

11

7573

32000

10169.82

9

UP

2

110054

7944

2

Haryana

2

324556

533.21

1

 

Overview of Status of clearance of projects in North India

 

TOR & EC Status

Nos

MW

CCA

MLD

Land Req

Land Req Info available for projects

TOR approved

50

12823

202586

21005.36

44

TOR not approved

1

300

0

72

1

TOR Waiting

6

1986

32000

4959.57

4

TOR approved before this committee

15

2978.5

382326

145

3895.85

13

Env Cl. Recommended

31

6843.5

352888

14793.77

27

Env Cl. Waiting

3

171

232024

648.47

2

Env Clearance not Recommended

0

0

0

0

0

0

 

Basin-wise overview of projects in North India

 

Projects on basins

Nos

MW

CCA

MLD

Bhilangana (Ganga)

1

22.5

Alaknanda (Ganga)

10

1931

Sarda (Ganga)

5

870

150302

145

Yamuna (Ganga)

15

1010

381556

Ramganga (Ganga)

1

0

53,054

Ganga

1

530

Ganga total

33

4363.5

Beas

6

930

Chenab

19

9733

Sutlej

8

2012

Ravi

5

956

32000

Jhelum

1

93

 

From the above tables it is clear that while largest number of projects from North India came from Ganga Basin at 33, the installed capacity of projects proposed in Chenab basin is highest at 9733 MW.

 

 NORTH EAST INDIA

TOR & Environment Clearance status in North-East India

 

The region comprises of eight states including Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Sikkim, Tripura and Nagaland. The Highest number of projects (99) has come to EAC from the North East region, and the highest number of first stage clearances at 70 have been given by EAC from this region. Within the North East Region, by far the highest number of projects (69) have come to EAC from Arunachal Pradesh. The EAC has the highest approval % in Arunachal Pradesh, every project has been given approval. Only for the 420 MW Kameng HEP of KSK Ltd, the EAC asked the developer to come back with reformulated proposal, rest were all given approval by the EAC. Over 35000 MW of hydropower projects have come to EAC from Arunachal Pradesh alone, by far the highest in the country for any state. Maximum no of projects that came to EAC among all river basins is from Siang basin at 21, though in terms of installed capacity, the highest installed capacity has come from Lohit basin at 10250 MW, among all the sub basins in the region. It was amazing to see the EAC promptly clearing the controversial Tipaimukh project way back in 2008, but the project is yet to get forest clearance and is unlikely to be able to start work in near future.

 

SN

Project

State

Basin

I/H/M

Ins Cap (MW)

CCA (Ha)

TOR

Meeting date

Env Clearance

Meeting date

Land Req (Ha)

Arunachal Pradesh

1

Amulin HEP

ARP

Dibang

H

420

 

Approved

30/06/2010

 

 

592.46

2

Dibang

ARP

Dibang

H

3000

 

Approved

29/07/2009

 

 

5827.8

3

Emini HEP

ARP

Dibang

H

500

 

Approved

21/08/2010

 

 

698

4

Mihundon HEP

ARP

Dibang

H

400

 

Approved

3/4/2011

 

 

700.42

5

Sissri HEP

ARP

Dibang

H

222

 

Approved

20/03/2009

 

 

900

6

Ithun-I

ARP

Dibang

H

86

 

Approved

26/12/2012

 

 

76

7

Attunil HEP

ARP

Dibang

H

500

 

Approved

16/11/2009

 

 

1021

8

Emra – II HEP

ARP

Dibang

H

390

 

Waiting

20/01/2010

 

 

1125

9

Etalin HEP

ARP

Dibang

H

3097

 

Waiting

26/12/2012

 

 

1149.85

10

Dibbin HEP

ARP

Kameng

H

130

 

 

Recommended

26/03/2011

162

11

Badao HEP

ARP

Kameng

H

70

 

Approved

7/10/2010

 

 

37.82

12

Dinchang HEP

ARP

Kameng

H

360

 

Approved

26/02/2011

 

 

82.13

13

Gongri

ARP

Kameng

H

144

 

Approved

12/04/2008

Recommended

21/07/2012

93

14

Jameri HEP

ARP

Kameng

H

50

 

Approved

23/11/2012

 

 

130

15

Khuitam HEP

ARP

Kameng

H

66

 

Approved

16/10/2008

Recommended

21/12/2010

66

16

Nafra HEP

ARP

Kameng

H

120

 

Approved

22/08/2008

Recommended

27/12/2011

78.45

17

Pachuk-I HEP

ARP

Kameng

H

84

 

Approved

27/12/2011

 

 

39.2548

18

Pachuk-II HEP

ARP

Kameng

H

60

 

Approved

27/12/2011

 

 

 

19

Para HEP

ARP

Kameng

H

55

 

Approved

7/10/2010

 

 

29.97

20

Saskang Rong HEP

ARP

Kameng

H

36

 

Approved

8/5/2008

 

 

20

21

Talong HEP

ARP

Kameng

H

225

 

Approved

12/10/2012

 

 

 

22

Kameng Dam HEP

ARP

Kameng

H

420

 

Not accepted

28/04/2012

 

 

3,764

23

Kameng-I HEP

ARP

Bhareli

H

1120

 

Approved

18/04/2007

 

 

969

24

Anjaw

ARP

Lohit

H

280

 

Approved

16/07/2011

 

 

359.12

25

Demwe HEP

ARP

Lohit

H

3000

 

Approved

19/07/2007

 

 

3600

26

Demwe Lower HEP

ARP

Lohit

H

1750

 

Approved

17/07/2008

Recommended

16/12/2009

1589.97

27

Demwe upper HEP

ARP

Lohit

H

1080

 

Approved

26/12/2012

 

 

967

28

Hotong HEP

ARP

Lohit

H

1250

 

Approved

18/07/2007

 

 

29

Kalai-I HEP

ARP

Lohit

H

1450

Approved

18/07/2007

 

 

 

30

Kalai-II HEP

ARP

Lohit

H

1200

 

Approved

22/10/2009

 

 

830

31

Tipang HEP

ARP

Lohit

H

45

 

Approved

20/03/2010

 

 

557

32

Gimliang HEP

ARP

Lohit

H

99

 

Waiting

12/10/2012

 

 

NA

33

Raigam HEP

ARP

Lohit

H

96

 

Waiting

12/10/2012

 

 

NA

34

Dardu HEP

ARP

Pare

H

60

 

Approved

8/9/2012

 

 

82.7

35

Par HEP

ARP

Pare

H

60

 

Approved

8/9/2012

 

 

28.25

36

Turu HEP

ARP

Pare

H

66

 

Approved

8/9/2012

 

 

29.49

37

Tato-II

ARP

Siang

H

700

 

 

Recommended

21/12/2010

371.49

38

Pauk HEP

ARP

Siang

H

145

 

Approved

17/09/2011

 

 

300 (Combined fig)

39

HEO

ARP

Siang

H

240

 

Approved

17/09/2011

 

 

40

Tato-I

ARP

Siang

H

186

 

Approved

17/09/2011

 

 

41

Hirit HEP

ARP

Siang

H

28

 

Approved

21/08/2008

 

 

120

42

Hirong HEP

ARP

Siang

H

800

 

Approved

15/10/2007

Waiting

23/11/2012

 

43

Kangtanshiri

ARP

Siang

H

80

 

Approved

8/9/2012

 

 

 

44

Lower Siang HEP

ARP

Siang

H

2700

 

Approved

23/11/2012

 

 

 

45

Lower Yamne St-I

ARP

Siang

H

88

 

Approved

11/2/2012

 

 

128.25

46

Lower Yamne St- II

ARP

Siang

H

90

 

Approved

11/2/2012

 

 

105.89

47

Naying HEP

ARP

Siang

H

1000

Approved

22/06/2007

 

 

600

48

Phangchung HEP

ARP

Siang

H

36

 

Approved

18/06/2008

 

 

25.5

49

Rapum HEP

ARP

Siang

H

80

 

Approved

1/6/2012

 

 

40

50

Rego HEP

ARP

Siang

H

70

 

Approved

16/12/2008

 

 

 

51

Simang-I HEP

ARP

Siang

H

67

 

Approved

12/10/2012

 

 

 

52

Simang-II HEP

ARP

Siang

H

66

 

Approved

23/03/2010

 

 

85

53

Tagurshit HEP

ARP

Siang

H

74

 

Approved

31/03/2012

 

 

41.7

54

Yamne -I HEP

ARP

Siang

H

60

 

Approved

19/09/2008

 

 

400

55

Yamne -II HEP

ARP

Siang

H

96

 

Approved

23/11/2012

 

 

300

56

Jerong

ARP

Siang

H

90

 

Waiting

8/9/2012

 

 

108.35

57

Pema Shelphu

ARP

Siang

H

70

 

Waiting

29/07/2009

 

 

63

58

Nalo HEP

ARP

Subansiri

H

360

 

Approved

12/11/2011

 

 

662.94

59

Subansiri Middle

ARP

Subansiri

H

1600

 

Approved

12/10/2012

 

 

3180

60

Subansiri Upper

ARP

Subansiri

H

2000

 

Approved

22/01/2011

 

 

3155

61

Tawang HEP St-I

ARP

Tawang

H

600

 

Recommended

21/01/2011

305.60

62

Tawang HEP St-II

ARP

Tawang

H

800

 

Recommended

21/01/2011

452.6

63

Mago Chu HEP

ARP

Tawang

H

96

 

Approved

20/01/2010

 

 

30

64

New Melling HEP

ARP

Tawang

H

96

 

Approved

20/01/2010

 

 

 

65

Nyamjang Chhu

ARP

Tawang

H

780

 

Approved

17/01/2008

Recommended

17/09/2011

254.55

66

Nyukcharong Chu

ARP

Tawang

H

96

 

Approved

20/01/2010

 

 

25

67

Rho HEP

ARP

Tawang

H

141

 

Approved

7/10/2010

 

 

35.39

68

Tsachu-I Lower

ARP

Tawang

H

69

 

Approved

21/07/2012

 

 

19.5

69

Tsachu-II Lower

ARP

Tawang

H

79

 

Approved

21/07/2012

 

 

38.89

Assam

70

Karbi Langpi Upper St

Assam

Kopili

H

60

 

Waiting

21/11/2008

 

 

 

71

Lower Kopili HEP

Assam

Kopili

H

150

 

Waiting

26/12/2012

 

 

1577

Manipur

72

Loktak Downstream

Manipur

Barak

H

66

 

 

Recommended

12/10/2012

211.57

73

Tipaimukh (Multipurpose)

Manipur

Barak

H

1500

 

 

Recommended

19/09/2008

31,950

Meghalaya

74

Kynshi Stage- I

Meghalaya

Barak

H

300

 

Approved

21/12/2010

 

 

185

75

Kynshi Stage- II

Meghalaya

Barak

H

400

 

Waiting

31/03/2012

 

 

4200

76

Mawhu HEP

Meghalaya

Kopili

H

120

 

Approved

18/04/2007

 

 

65

77

Nongkohlait HEP

Meghalaya

Kopili

H

120

 

Approved

14/12/2007

 

 

400

78

Umduna HEP

Meghalaya

Kopili

H

57

 

Approved

8/5/2008

 

 

 

79

Umngi HEP

Meghalaya

Kopili

H

100

 

Approved

14/12/2007

 

 

495

80

Umjaut HEP

Meghalaya

Kopili

H

69

 

Waiting

8/5/2008

 

 

 

81

Myntdu HEP

Meghalaya

Myntdu

H

42[13]

 

 

Recommended

17/07/2008

 

82

Myntdu Leshka Stage -II

Meghalaya

Myntdu

H

280

 

Approved

23/03/2010

 

 

 

Mizoram

83

Kolodyne-II HEP

Mizoram

Kolodyne

H

460

 

Approved

27/12/2011

 

 

720

Nagaland

84

Dikhu HEP

Nagaland

Dikhu

H

186

 

Approved

26/12/2012

 

 

 

Sikkim

85

Dickchu HEP

Sikkim

Teesta

H

96

 

 

Recommended

21/02/2008

39.07

86

Rangit –II

Sikkim

Teesta

H

66

 

 

Recommended

14/05/2009

64.93

87

Tashiding HEP

Sikkim

Teesta

H

97

 

 

Recommended

30/06/2010

17.854

88

Ting Ting

Sikkim

Teesta

H

99

 

 

Recommended

22/01/2011

25.4924

89

Lethang HEP

Sikkim

Teesta

H

96

 

Approved

20/01/2010

 

 

 

90

Suntaley Tar

Sikkim

Teesta

H

40

 

Approved

8/9/2012

 

 

39.02

91

Teesta Stage –I

Sikkim

Teesta

H

280

 

Approved

18/04/2007

 

 

 

92

Teesta Stage-II

Sikkim

Teesta

H

150

 

Waiting

23/11/2012

 

 

NA

93

Teesta Stage -III[14]

Sikkim

Teesta

H

1200

 

 

Recommended

4/8/2006

 

94

Teesta Stage -IV

Sikkim

Teesta

H

520

 

Approved

14/05/2009

Waiting

23/11/2012

324

95

Chakung Chu

Sikkim

Teesta

H

90

 

Waiting

28/04/2012

 

 

 

96

Lingza HEP

Sikkim

Teesta

H

120

Waiting

20/09/2007

 

 

97

Panan HEP

Sikkim

Teesta

H

300

 

Waiting

31/03/2012

 

 

 

98

Ralong

Sikkim

Teesta

H

120

 

Waiting

28/04/2012

 

 

 

Multistate

99

Sankosh-Teesta canal

Multistate

Sankhosh

H

4000

400000

Waiting

16/12/2008

 

 

 

                               

Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available

 

State-wise Overview of Projects in North-East India

 

 

Projects

Ins Cap

Irrigation

Land Req

Land requirement info available for projects

State wise Projects

Nos

MW

CCA (Ha)

(Ha)

Nos

Total Projects

99

46658

76768.27

72

ARP

69

35474

36454.34

56

Sikkim

14

3274

510.37

6

Meghalaya

9

1488

5345

6

Manipur

2

1566

32161.57

2

Assam

2

210

1577

1

Nagaland

1

186

NA

0

Mizoram

1

460

720

1

Multi state

1

4000

400000

NA

0

 

Overview of Status of clearance of projects in North East India

 

TOR & EC Status

Nos

MW

CCA

Land Req

Land Req Info available for projects

TOR approved

70

31541

31180.47

55

TOR not approved

1

420

3764

1

TOR Waiting

16

9301

400000

8223.2

6

TOR approved prior to this EAC

12

4940

33600.6

10

Env Clearance Recommended

17

8256

35682.58

15

Env Clearance Waiting

2

1320

324

1

Env Clearance rejected

0

0

0

0

0

 

Basin-wise overview of projects in North East India

 

Projects on basins

Nos

MW

CCA

Lohit

10

10250

Siang

21

6766

Kameng

14

4060

Kopili

7

676

Teesta

14

3274

Sankhosh

1

4000

400000

Myntdu

2

406

Dikhu

1

186

Barak

4

2266

Dibang

9

8615

Tawang

9

2757

Subansiri

3

3960

Kolodyne

1

460

Pare

3

186

 

EAST INDIA

TOR & Environment Clearance status in East India

 

The region comprises of Bihar, W Bengal, Jharkhand, Chhattisgarh and Orissa. Among all regions, the least number of projects came to EAC from Eastern region at 20. Interestingly, not one project from Jharkhand has come to the EAC in this period. However, TOR clearance given for the 16.54 lakh CCA in this region is highest among all states and total proposed CCA among all regions is second highest for the Eastern region. This highest contribution for this large CCA from the Eastern region is coming from the proposed Saptakoshi High Dam at 15 lakh Ha (of which 9.76 lakh ha is supposed to be in India), the project also has the highest proposed installed capacity (3000 MW), but that project is supposed to come up in Nepal and there is little likelihood of the project going ahead in near future.

 

SN

Project

State

Basin

I/H/M

Ins Cap (MW)

CCA (Ha)

TOR

Meeting date

Env Clearance

Meeting date

Total Area Req (Ha)

Bihar (BH)

1

Dagmara Hydro Power Project

BH

Kosi

H

130

0

Approved

12/10/2012

Waiting

31/03/2012

NA

2

Saptkoshi High Dam[15]

BH

Kosi

M

3000

1500000

Approved

18/09/2008

NA

Chhattisgarh (CG)

3

Arpa Bhaisajhar Barrage  project

CG

Mahanadi

I

25000

Approved

26/12/2012

 

 

NA

4

Kelo Major Irrigation Project

CG

Mahanadi

I

22,800

Recommended

17/07/2008

NA

5

Kanhar HEP

CG

Son

H

50

0

Waiting

23/03/2010

NA

Orissa (OR)

6

Khandohota Medium Irrigation Project

OR

Brahmani

I

350

Approved

19/06/2008

 

 

16.8

7

Rukura Irrigation Project

OR

Brahmani

I

5750

Recommended

16/10/2008

NA

8

Samakoi Irrigation Project

OR

Brahmani

I

9990

Approved

20/03/2009

1064.43

9

Brutang Major Irrigation Project

OR

Mahanadi

I

23,300

 

 

Recommended

7/9/2012

NA

10

Jeera Irrigation Project

OR

Mahanadi

I

4800

Approved

21/08/2010

831.5

11

Ong Dam project

OR

Mahanadi

I

30000

 

 

Recommended

15/11/2007

NA

12

Daha Irrigation Project

OR

Rushikulya

I

270

 

 

Recommended

16/10/2008

NA

13

Sindol 1- Deogaon HEP

OR

Mahanadi

H

100

0

Approved

30/04/2011

NA

West Bengal (WB)

14

Dwarkeshwar Irrigation Project

WB

Hoogly

I

38,500

Recommended

17/07/2008

NA

15

Siddheswari-Noonbeel Irrigation Project`

WB

Hoogly

I

29,000

Waiting

21/08/2010

NA

16

Subarnarekha Barrage Project

WB

Subarnrekha

I

114,200

Approved

25/09/2009

5,500

17

Rammam stage-III

WB

Teesta

H

120

0

Recommended

19/09/2007

72

18

Teesta Intermediate HEP

WB

Teesta

H

144

0

Approved

16/06/2009

NA

19

Teesta Low Dam-V HEP

WB

Teesta

H

80

Waiting

13/10/2012

157.05

20

TLDP –I & II HEP

WB

Teesta

H

60

0

Approved

16/06/2009

NA

Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available

 

 

State-wise Overview of Projects in East India

 

 

Projects

Ins Cap

Irrigation

Land Req

Land Req Info available for projects

State wise Projects

Nos

MW

CCA (Ha)

(Ha)

Nos

Total Projects

20

3684

1279960

16809.24

9

West Bengal

7

404

181700

5729

3

Orissa

8

100

74460

1912.73

3

Bihar

2

3130

976000

7,595.35

1

Chhattisgarh

3

50

47,800

1572.105

2

 

Overview of Status of clearance of projects in East India

 

TOR & EC Status

Nos

MW

CCA

Land Req

Land Req Info available for projects

TOR approved

10

3434

1654340

15810.185

6

TOR not approved

0

0

0

0

0

TOR Waiting

3

130

29000

927.05

2

TOR approved before this committee

7

120

120620

72

1

Env Clearance Recommended

7

120

120620

72

1

Env Clerance Waiting

1

130

0

7595.35

1

Env Clearance not Recommended

0

0

0

72

1

 

Basin-wise overview of projects in East India

 

Projects on basins

Nos

MW

CCA

Teesta

4

404

0

Mahanadi

6

100

105900

Brahmani

3

0

16090

Rushikulya

1

0

270

Kosi

2

3130

1500000

Hoogly

2

0

67500

Subernrekha

1

0

114,200

Son

1

50

0

 


WEST INDIA

TOR & Environment Clearance status in West India

 

49 projects came to EAC from this region (comprising of states of Gujarat, Maharashtra, Madhya Pradesh, Rajasthan and Goa), most of them were irrigation projects, unlike the situation in North and North East India where most projects that came to EAC during the study period were hydropower projects. Out of these, land availability figures are available only for 14 projects, the least % of the total projects compared to all regions. Land availability figure for none of the 20 projects of MP is mentioned in the EAC minutes. Within the region, highest number of 21 projects came from Maharashtra and close second was Madhya Pradesh. Maharashtra incidentally has the largest number (10) of giant lift irrigation schemes coming for approval before the EAC. Two of the biggest projects came up before the EAC were from Gujarat, the Kalpsar (Gulf of Khambat Development Project) and Par Tapi River Link Project. It was strange to see the EAC clearing the Par Tapi Narmada and the Ken Betwa Phase 1 river link proposals, both for TOR clearance. Both are facing strong opposition. Stranger it is to see the EAC noting in a latter meeting that the MoEF has conveyed to NWDA that the Ken Betwa Phase I link proposal cannot be cleared due to huge submergence it will entail in the Panna Tiger Reserve. Why did the EAC not review its decision regarding the TOR clearance in that case? Parwan irrigation project in Chambal basin in Rajasthan is another project that is facing massive opposition on ground, but the EAC has recommended it for final clearance. Even more shockingly, in its meeting on Nov 20, 2008, EAC opined that the Damanganga Pinjal link (involving several massive dams) does not require any environment clearance since it is a drinking water project. Its clear from these decisions how callous has been the treatment of the EAC to such massive projects.

 

SN

Project

State

Basin

I/H/M

Ins Cap (MW)

CCA (Ha)

TOR

Meeting date

Env Clearance

Meeting date

Total Area Req (Ha)

Gujarat (GJ)

1

Gulf of Khambat development project

GJ

Multiple

M

NA

Waiting

25/09/2010

Maharashtra (MH)

2

Ajansara Barrage

MH

Godavari

I

30004

Approved

18/03/2008

NA

3

Dhapewada LIS-II

MH

Godavari

I

67,506

Approved

22/08/2008

Recommended

21/12/2010

NA

4

Upper Penganga Project Stage -II

MH

Godavari

I

28,600

Recommended

2/6/2011

NA

5

Upper Pravara Irrigation Project

MH

Godavari

I

64260

Waiting

20/09/2007

3504

6

Kanhan River Project

MH

Godavari

M

Approved

14/05/2009

Recommended

12/11/2011

1434.54

7

Malshej Ghat Pumped Storage Sch

MH

Kalu

H

600

Approved

22/08/2008

511.06

8

Ekrukh Lift Irrigation Scheme

MH

Krishna

I

25,240

Approved

17/07/2010

NA

9

Expansion of Krishna – Koyna LIS

MH

Krishna

I

40219

Recommended

16/06/2009

NA

10

Janai Shirsai Lift Irrigation Scheme

MH

Krishna

I

14080

Waiting

22/08/2008

NA

11

Jihe Kathapur Lift Irrigation

MH

Krishna

I

27500

Recommended

8/5/2008

218.46

12

Krishna Marathwada Irrigation Prjct

MH

Krishna

I

92141

Approved

16/10/2008

2819.7

13

Purander Lift irrigation

MH

Krishna

I

21500

Approved

15/11/2007

NA

14

Shirapur Lift Irrigation Scheme

MH

Krishna

I

10,000

Waiting

26/12/2012

507.43

15

Thembu Lift Irrigation Project

MH

Krishna

I

 

Recommended

19/07/2007

NA

16

Wakurde Lift Irrigation Scheme

MH

Krishna

I

28,035

Recommended

17/07/2010

865

17

Humbarli Pumped Storage Scheme

MH

Krishna

H

400

Approved

19/08/2009

NA

18

Augmnetation Project at Bhira

MH

Krishna

H

100

Waiting

19/07/2007

NA

19

Bodwad Parisar Sinchan Yojana

MH

Tapi

I

42,420

Approved

17/02/2009

Recommended

19/02/2012

1729.64

20

Kurha Badoda Islampur Upsa

MH

Tapi

I

14586

Approved

20/03/2009

NA

21

Lower Pedhi irrigation project

MH

Tapi

I

12230

 

 

Recommended

14/12/2007

2532

22

Lower Tapi LIS

MH

Tapi

I

54500

Approved

30/06/2010

Waiting

26/12/2012

6913.25

Madhya Pradesh (MP)

23

Kundaliya Major Irrigation Project

MP

Chambal

M

Approved

27/12/2011

NA

24

Mohanpura Major Irrigation Project

MP

Chambal

M

65000

Approved

17/12/2011

NA

25

Punasa Lift Irrigation Scheme

MP

Narmada

I

35008

Recommended

26/05/2007

NA

26

Sip Kolar Medium Irrigation Project

MP

Narmada

I

6400

Approved

12/10/2012

NA

27

Upper Narmada Project

MP

Narmada

I

21276

Approved

18/04/2007

Recommended

19/08/2009

NA

28

Halon Irrigation Project

MP

Narmada

I

16782

Recommended

16/11/2009

NA

29

Integrated Raghavpur, Rosara, Basania with Bargi Multipurpose Prjt

MP

Narmada

i

 

Waiting

21/08/2010

NA

30

Bauras HEP

MP

Narmada

H

55

Waiting

17/07/2008

NA

31

Handia HEP

MP

Narmada

H

51

Waiting

15/11/2007

NA

32

Hoshangabad HEP

MP

Narmada

H

60

Waiting

17/07/2008

NA

33

Lower Goi irrigation project

MP

Narmada

M

13760

Recommended

14/12/2007

NA

34

Morand & Ganjal Complex Irrigation

MP

Narmada

M

58,052

Approved

21/07/2012

NA

35

Chinki Multipurpose Project

MP

Narmada

M

73,979

Approved

2/6/2012

NA

36

Barrage on Gopad River

MP

Son

WS

 

Approved

16/07/2011

NA

37

Bansujara Dam Project

MP

Yamuna

I

49,373

Approved

21/07/2012

NA

38

Ghogra Minor Irrigation Project

MP

Yamuna

I

1650

Approved

21/07/2012

NA

39

Lower Orr Project[16]

MP

Yamuna

I

44791

Waiting

26/12/2012

NA

40

Ken-Betwa River Linking Project -I

MP

Yamuna

M

Approved

21/12/2010

NA

41

Pancham Nagar Multipurpose Prjct

MP

Yamuna

M

Waiting

17/09/2011

NA

42

Bina Complex IMultipurpose Project

MP

Yamuna

M

Approved

8/5/2008

Waiting

11/2/2011

NA

Rajasthan (RJ)

43

Kalisindh Major irrigation project

RJ

Chambal

I

22,000

Approved

24/11/2012

NA

44

Parwan Major Irrigation-cum-DWS

RJ

Chambal

M

1,31,400

Recommended

21/12/2010

NA

Multi State

45

Lendi Major Irrigation Project

MH/AP

Godavari

I

Approved

20/09/2007

Waiting

12/11/2011

2621.42

46

Bandra Nala Project

MH/KN

Krishna

H

Approved

2/6/2012

152

47

Bhandora Nala Project

MH/KN

Krishna

H

Approved

2/6/2012

286.08

48

Pale Parmar Nalla Project

MH/KN

Krishna

H

320

Approved

2/6/2012

203.99

49

Par-Tapi – Narmada Link Project

MH/GJ

Multiple

M

188414

Approved

14/05/2009

7560

Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available, LIS: Lift Irrigation Scheme; DWS: Drinking Water Scheme

 

 

State-wise Overview of Projects in West India

 

 

Projects

Ins Cap

Irrigation

Land Req

Land Req Info available for projects

State wise Projects

Nos

MW

CCA (Ha)

(Ha)

Nos

Total

49

1586

1300706

31858.57

15

MH

21

1100

572821

21035.08

10

GJ

1

NA

0

RJ

2

0

153400

NA

0

MP

20

166

386071

NA

0

Multi state

5

320

188414

10823.49

5

 

Overview of Status of clearance of projects in West India

 

TOR & EC Status

Nos

MW

CCA

Land Req

Land Req Info available for projects

TOR approved

28

1320

834041

24231.68

10

TOR not approved

0

0

0

0

0

TOR Waiting

11

266

133131

4011.43

2

TOR approved before this committee

10

0

333534

3615.46

3

Env Cl. Recommended

14

0

464736

3639.91

3

Env Cl. Waiting

3

0

54500

2594.64

2

Env Clearance not Recommended

0

0

0

0

0

 

Basin-wise overview of projects in West India

 

Projects on basins

Nos

MW

CCA

Godavari

6

0

190370

Krishna

14

1120

258715

Tapi

4

0

123736

Kalu

1

600

0

Chambal

5

0

218400

Multiple

2

0

188414

Yamuna

5

0

95814

Narmada

11

166

225257

Son

1

0

0

 

SOUTH INDIA

TOR & Environment Clearance status in South India

 

SN

Project

State

Basin

I/H/M

Ins Cap (MW)

CCA (Ha)

TOR

Meeting date

Env Clearance

Meeting date

Land Req (Ha)

Andhra Pradesh (AP)

1

Pranahitha Chevella Sujala – Srvanthi Project

AP

Godavari

I

663700

Approved

16/06/2009

9810

2

Diversion from Pranahita to Sripada Sagar

AP

Godavari

I

548000

Waiting

14/12/2007

31424

3

Lower Penganga Irrigation Project

AP

Godavari

I

19,233

Approved

26/12/2012

509.261

4

Kanthanapally Sujala Sravanthi

AP

Godavari

H

280

304000

Waiting

26/03/2011

4170

5

Polavaram[17] Multipurpose Project

AP

Godavari

M

NA

NA

 

 

Waiting

17/02/2009

6

Dummugundem Nagarjuna Sagar tail pond link canal project

AP

Krishna

I

NA

Waiting

22/01/2011

7

Modernisation of Krishna Delta sys

AP

Krishna

I

529000

Recommended

14/05/2009

Kerala

8

Pathrakadavu HEP

Kerala

Bharatpuzha

H

70

 

 

 

Waiting

16/05/2007

 

9

Pambar HEP

Kerala

Cauvery

H

40

 

Approved

16/12/2009

 

 

45.034

10

Athirapally HEP[18]

Kerala

Chalakudy

H

163

 

 

 

Recommended

16/05/2007

 

11

Achencovil HEP

Kerala

Pamba

H

30

 

Approved

21/08/2008

 

 

 

Karnataka (KN)

12

Shivasamudram Seasonal Power

KN

Cauvery

H

270

Approved

29/07/2009

70

13

Kali Pumped Storage Scheme

KN

Kali

H

600

 

Waiting

20/03/2009

 

14

Singtalur Lift Irrigation Project

KN

Krishna

I

77,198

Approved

26/12/2012

3171

15

Sri Rameshwara Lift Irrigation Sch

KN

Krishna

I

13800

Recommended

16/06/2009

353.7

16

Upper Bhadra Lift Irrigation Prjct-I

KN

Krishna

I

107265

Recommended

22/10/2009

5245.37

17

Gundia HEP

KN

Netravathi

H

200

Recommended

21/07/2012

1041.64

18

Shiggaon Lift Irrigation Scheme

KN

Varada

I

9900

Approved

21/12/2010

775

19

Dandavathy Reservoir Project

KN

Varada

I

6,933

Waiting

19/02/2012

Tamil Nadu (TN)

20

Moyar Ultimtae Ph-I

TN

Cauvery

H

25

 

Waiting

22/08/2008

 

 

 

21

Kundah PPS

TN

Cauvery

H

500

 

 

 

Recommended

18/04/2007

130.5

22

Inter-Linking of Tambiraparani, Karumeniyar and Nambiyar Rivers

TN

Multiple

I

17002

Waiting

12/11/2011

653.317

Purpose: H- Hydropower; I- Irrigation; M- Multipurpose.; NA- Not available

 

State-wise Overview of Projects in South India

 

 

Projects

Ins Cap

Irrigation

Land Req

Land Req Info available for projects

State wise Projects

Nos

MW

CCA (Ha)

(Ha)

Nos

Total

22

2178

2296031

57398.82

13

Kerala

4

303

0

45.031

1

TN

3

525

17002

783.82

2

KN

8

1070

215096

10656.71

6

AP

7

280

2063933

45913.26

4

 

Overview of Status of clearance of projects in South India

 

TOR & EC Status

Nos

MW

CCA

Land Req

Land Req Info available for projects

TOR approved

7

340

770031

14380.30

6

TOR not approved

0

0

0

0

0

TOR Waiting

7

905

875935

36247..32

3

TOR approved before this committee

8

933

650065

6771.21

4

Env Cl. Recommended

6

863

650065

6771.21

4

Env Cl. Waiting

2

70

0

NA

0

Env Clearance not Recommended

0

0

0

0

0

 

Basin-wise overview of projects in South India

 

Projects on basins

Nos

MW

CCA

Bharatpuzha

1

70

0

Cauvery

4

835

0

Chalakudy

1

163

0

Godavari

5

280

1534933

Kali

1

600

0

Krishna

5

0

727263

Multiple

1

0

17002

Netravathi

1

200

0

Pamba

1

30

0

Varada

2

0

16833

 

 

 


[2] See Central Water Commission’s National Register of Large Dams, 2012: http://www.cwc.gov.in/main/webpages/NRLD%20FORMAT%202012.pdf

[7] SANDRP had written to EAC about the glaring errors in the minutes of the 60th and 61st meetings of the EAC, pointing out the errors in capacities, names of places and even names of river in the minutes, but the EAC neither acknowledged the letter or errors, nor bothered to correct them.

[9] EAC has remained on rather steep learning curve on a number of issues, including on Environmental flows. It first questioned the wisdom or need for e-flows, than graduated to recommending 10% of minimum lean season flow, than 15%, later changing to 20% and now it has a little more detailed norms, still far from asking for actual assessment for each river stretch.

[11] Both the documents authored by Himanshu Thakkar and Bipin Chandra Chaturvedi, Bipin has done the detailed compilation for the two documents. Thanks a due to Parineeta Dandekar (for all the charts in addition to valuable comments, Dr Latha Anantha, Shripad Dharmadhikary and Neeraj Vagholikar for some very useful comments and suggestions.

[13] Clearance sought for adding the third 42 MW unit to the existing 84 MW project.

[14] The project is listed here since it came back before the EAC in Feb 2010 as it had yet to get NBWL clearance.

[15] The TOR clearance was only for the irrigation component in India, the main dam, barrage and headwords will all be in Nepal, which is beyond the jurisdiction of EIA notification 2006 of India.

[16] Part of Ken Beta Link River Link project phase II

[17] The Polavaram project got Environment Clearance in Oct 2005, however, came back to EAC for clearance of the embankments in Orissa and Chhattisgarh as these were not part of the proposal cleared by EAC. The Ministry of Environment and Forests had asked the project authority to get these components cleared and hence the embankment portion came to EAC for clearance. The EAC noted that there has been no public hearings conducted in Orissa and Chhattisgarh as required under EIA notification and asked project authorities to come back to EAC after conducting the public hearings. The project authorities have yet to comply with this requirement and hence the clearance to the project is yet to be recommended by the EAC.

[18] The Athirapally project, following directions by Kerala High Court to KSEB (the MoEF show cause notice of Jan 4, 2010 could also be a factor, but there is no mention of that in the EAC minutes), came back before EAC in March 2010 and was again discussed in April 2010 and July 2010, till when no conclusion could be reached by EAC and EAC had asked for more information and clarifications. There is no mention of the project in any of the subsequent minutes of meetings.

Expert Appraisal Committee · Ministry of Environment and Forests · Sutlej

MoEF’s Exp App Com damns the Sutlej

ImageImage
It is well-known that India’s environment governance is very weak. The work of the Expert Appraisal Committees (EAC) in the clearance process is shoddy, unscientific and largely catering to vested interests. But with the recent recommendation of an environment clearance for the 775 MW Luhri hydropower project on the Sutlej river in Himachal Pradesh, the Union Ministry of Environment and Forests’ (MoEF) EAC on River Valley and Hydropower Projects seems to have touched a new low.

First, the Sutlej was known to be an already over developed basin when the Luhri project came up for first stage clearance before the EAC in April 2007. The EAC should have refused to consider the project without an independent credible cumulative basin level study looking into its carrying capacity with respect to various aspects. The fact that the EAC did not even discuss this then, even though the issue was brought before it, showed the EAC members’ complete lack of understanding of the importance of the basin level cumulative impact assessment study.

The minutes of the EAC meeting in April 2007, where the Terms of Reference (TOR) of the EIA came up for approval for the Luhri project, say that the project is going to have a 45 m high dam affecting a maximum of 45 project affected families and 13 villages. Now from the EIA it is clear that the dam height is not 45 m but 86 m, that the project will affect not 45 but 2,337 landowners and 9,674 persons and impact not 13 but over 100 villages. Any competent body would have questioned the very serious nature of changes in basic project parameters, but competence is clearly not the correct description of the EAC. The EAC did not even ask the project promoter for an explanation, leave aside penalise them for their misrepresentations.

Even legally, the TOR clearance is supposed to be valid only for two years. When the project came up for final environmental clearance before the EAC towards the end of March 2012, it was almost five years since the TOR was cleared. The TOR clearance was no longer valid but the EAC was completely blind to the illegalities.

The legally mandatory public hearings for the project were held in May and August 2011, but the EIA, made available a month before the public hearing as required under the EIA notification, did not have basic information about the names and impacts on the 78 villages along the path of the tunnel of the projects. The local groups had written to the ministry, the Pollution Control Board that is supposed to conduct the hearings and the EAC about these and other issues. But the EAC did not even take note of such serious legal lapses. On this count of violations alone, in the public hearing process, the EAC should have refused to consider the project. But the EAC did not even discuss this issue!

In repeated representations to the EAC, the Sutlej Bachao Sangharsh Samiti and Himdhara have been bringing to the EAC’s notice that there has been no compliance with the Forest Rights Act (FRA) for the forest land required for the project and that the local administration has been indulging in manipulations and pressure tactics to get the mandatory gram sabha resolutions for the FRA compliance.

In fact, these groups have been sending representations to the EAC on all these issues since October 2011. Already, five representations have been sent, but the EAC has never even acknowledged, leave aside discussed any of these representations in its meetings.

The EAC should have invited the people who sent such representations, heard them and allowed them to be present when the project was discussed in the EAC. The EAC did none of these things clearly showing their bias for the projects and not for the environment and people which are the basic mandates of the EAC. This behaviour of the EAC is also in violation of the Delhi High Court order in the Utkarsh Mandal case where the High Court has expressly asked the EAC to show that it has applied its mind to each representation it receives and the decision it takes in that regard.

The EIA itself has such serious inadequacies that even the EAC notes in the minutes of the March 2012 meeting that “the EIA/EMP report is inadequate,” and the consultant has presented “poor quality of material.” The EAC minutes record many of the serious deficiencies of the EIA in its March 2012 meeting. The EIA was so inadequate, so full of contradictions and misrepresentations that the EAC should have rejected it and asked for a fresh EIA while recommending blacklisting of the consultant. None of these issues were resolved in the November 2012 meeting when EAC next discussed the project. By then the EAC had also received representations from affected people, and the issues raised, which too remained unresolved. And yet, the EAC decided to quietly recommend environment clearance to the project without referring to its own observations or those of the representations. The most charitable explanation is that the EAC is inconsistent, incompetent and arbitrary. Reality is rarely that charitable.

The response of the developer and consultant to the issues raised by the EAC in the March 2012 meeting was supposed to be made available at least 10 days before the next EAC meeting in November 2012 when it met to consider the project, as per the orders of the Central Information Commission (CIC) in Febuary 2012 and the CIC notice to the MoEF following SANDRP’s appeal in May 2012. Violating the CIC orders, the responses were not in the public domain.

Even more shockingly, the project violated the EAC’s own norms, but amazingly, the EAC did not even discuss it. Let us see how. The Full Reservoir Level of the Luhri dam is 862.9 m and the tail water level of the immediate upstream Rampur project is also 862.9 m, which means there is zero distance of flowing river between the two projects. This is in complete violation of the recommendations of the Avay Shukla (former additional Chief Secretary of Himachal Pradesh) Committee appointed by the Himachal Pradesh High Court and the reported recommendation of the BK Chaturvedi Committee appointed by the National Ganga River Basin Authority, headed by the Prime Minister. Both the committees’ recommendations are for a minimum of five km distance of flowing river between any two projects. Even the EAC has been following the recommendation of at least a one km distance between the two projects. But the EAC did not even discuss this issue.

Even more disturbingly, the full reservoir level of the downstream Kol dam is 642 m, whereas the invert level of the Tail Race Channel of Luhri dam is one metre below this that is 641 m, which means again there is zero length of flowing river between the two projects. The EAC again violated the recommendations of the Avay Shukla Committee and its own norms. Why did the EAC not even discuss this issue? Why did the SJVN and the EIA consultants, who were familiar with the EAC norm did not raise these issues for both the upstream and downstream situation? Why did the MoEF officials who are part of the EAC and knew the importance of these issues did not raise them either? This collective silence, indicating collective collusion, raises too many questions for anyone’s comfort.

It should be noted that the Luhri project has a head race tunnel length of 38.14 km, which is the longest in the world. As the EAC itself noted, the tunnel will bypass over 50 km length of the river, in addition to the 6.8 km long reservoir. So the project will destroy close to a length of 60 km of the mighty, already over-dammed Sutlej river. To see the callous treatment the EAC has given to such an unprecedentedly impactful project is most reprehensible.

It’s clear that the whole episode of the EAC recommending environment clearance to the Luhri HEP is shameful. As if to keep that appalling decision away from the public gaze, the publication of the November 2012 meeting of the EAC was delayed beyond the next meeting, unlike the usual practice. The only possible option left for the EAC to clear the air and its own name from this disgraceful situation is an urgent, transparent review of this decision it has taken. Let us hope the EAC will use that opportunity soon.
Himanshu Thakkar (ht.sandrp@gmail.com)
http://civilsocietyonline.com/pages/Details.aspx?263