Dams · DRP News Bulletin

DRP: 11 May 2020: Jindal accepts Etalin HEP is unviable!

This must be the defining (and predictable, this was the lead story in our DRP NB of April 27, 2020, see: https://sandrp.in/2020/04/27/drp-nb-27-april-2020-for-whom-is-this-unviable-etalin-project-being-pushed/) moment in the campaign to save the Dibang Valley now from the proposed 3097 MW Etalin Hydropower Project. The CEO of Jindal Power Ltd has said in so many words that project is NOT an attractive investment, they will struggle to find buyers for the costly power and only support from government can help make the project viable. The CEO seemed to suggest that they would be happy to sell the project to NHPC or form a joint venture with NHPC to get the govt funding for the project. Again completely on predictable line. The question then is why should government spend previous public money on such an unviable project?

So the question remains the same, the one we asked on April 27, 2020: For whom is this unviable Etalin Project being pushed?

Continue reading “DRP: 11 May 2020: Jindal accepts Etalin HEP is unviable!”
Dams · DRP News Bulletin

DRP: 04 May 2020: Wildlife Institute of India doing quid pro quo with hydro developers?

WII skips multi-seasonal study on Etalin, cheats its way to compile a conservation plan; MoEFCC and FAC ignore all FANTASTIC REPORT The Wildlife Institute of India (WII) spent only four months on field while compiling a multi-seasonal replicate study on the Jindals’ 3097 mw Etalin Hydro Electric Power Company Ltd (EHEPCL) in Dibang Valley in Arunachal, and it relied on earlier studies conducted in the region. The forest advisory committee (FAC) of the union ministry of environment, forests & climate change (MoEFCC) and the ministry itself did not bother to ask any questions as to how the study was compiled, even though one of its own reports states that four months’ study was carried out. Instead, the FAC formed a subcommittee to look into the “concerns related to tree enumeration process and the aspects highlighted in biodiversity assessments study by WII.” The wildlife study done by the WII is accepted in toto by the subcommittee, the subcommittee report says. The subcommittee included a member of the WII who was part of the team that cheated its way to compile a questionable report on Etalin.  https://arunachaltimes.in/index.php/2020/05/03/wii-skips-multi-seasonal-study-on-etalin-cheats-its-way-to-compile-a-conservation-plan-moefcc-and-fac-ignore-all/  (03 May 2020)

Continue reading “DRP: 04 May 2020: Wildlife Institute of India doing quid pro quo with hydro developers?”
Dams · DRP News Bulletin

DRP: 27 April 2020: For whom is this unviable Etalin project being pushed?

In the ongoing debate on forest clearance for the controversial Etalin Hydropower project in Dibang Valley in Arunachal Pradesh between the Forest Advisory Committee, The Hindustan Times’s consistent reporting and Sanctuary magazine launching a campaign along with others, one (of the many) key question that remains unanswered is: for whom this economically (in addition to socially, environmentally and from climate change perspective) unviable, massively expensive project being pushed in a power surplus country?

Electricity from hydropower projects is no longer economically viable, since cheaper options are available. Some misguided people are claiming virtue in hydropower project claiming it provides peaking power. The fact is India is today not only power surplus, the peak power deficit has been just around 1% or less for long time. This when there is no attempt to either monitor as to how much of the electricity produced from existing hydropower projects provides peaking power, nor is there any attempt to achieve optimisation of operation of existing hydro projects to produce maximum possible hydropower. Nor is there any attempt to even manage the peaks either through pricing or other policy measures. In such a situation there is clearly no justification for more hydro for peaking. Moreover, the storage option is becoming increasingly cost effective, reducing the peaking power needs. So then for whom this project whose cost won’t be less than Rs 30000 crores at most conservative estimates, being pushed? The contractors, the equipment suppliers, the hydro lobby, the consultants, the timber lobby, the dam lobby, or the kickbacks?

Continue reading “DRP: 27 April 2020: For whom is this unviable Etalin project being pushed?”
Dams · Sand Mining

Himachal Pradesh sand mining 2020: No Replenishment study, district foundation

Himachal Pradesh is a hilly state where large scale, mechanized mining of riverbed minerals has been going on for past many years. The damaging impacts on rivers, streams and dependent communities are evident and on the rise. However the state government has failed to bring any change in the scenario as can be seen in this overview covering the related developments during 2019-20.

Continue reading “Himachal Pradesh sand mining 2020: No Replenishment study, district foundation”

Dams · DRP News Bulletin

DRP: 20 April 2020: Solutions to Covid 19 & Climate change are same?

This proposition clearly sounds simplistic and seems devoid of science or logic. But the case studies of the epidemics since 1980 and loss of forests, biodiversity and sustainability shows that this is not to be dismissed that easily. In fact the following interview with Dr Aaron Bernstein makes a powerful case to show why this indeed has a lot of science and logic behind it. It also hence makes a case that yesterday (our “normal”), is no longer a good model for better tomorrow.

Continue reading “DRP: 20 April 2020: Solutions to Covid 19 & Climate change are same?”
Dams · Sand Mining

J&K Riverbed Mining 2020: Rivers exposed to mechanized mining

Unsustainable, unscientific excavation of riverbed minerals has been having significant impact on river eco-system and riparian communities for past several years. Since 2016, to develop better understanding and highlight the problems SANDRP has been preparing state wise annual overview of riverbed minerals (RBM) mining activities. Having putting together year end round up for Gujarat, Maharashtra, Goa, Rajasthan, Madhya Pradesh, Punjab, Haryana states, this compilation attempts to cover prevailing situation in Jammu & Kashmir (J&K) over the last one year. The link of 15 overviews in 2018 can be see here.

Continue reading “J&K Riverbed Mining 2020: Rivers exposed to mechanized mining”

Dam Safety · Dams

Singrauli Fly Ash Dam Breach: Who regulates these dams in India?

A fly ash Dam of Sasan Ultra Mega Power Project of Reliance Company has breached[i] in the evening of April 10, 2020, near village Harrahva in Singrauli district of Madhya Pradesh, killing six people and destroying downstream river and fields. Following the breach there was massive flash flood of coal ash mixed sludge reportedly affecting hundreds of villages and destroying crops on thousands of acres.

Of the six people feared to have been killed in the flash floods, dead bodies of two have been found in faraway areas, while four are still missing. Two women injured in the aftermath are reported to be in stable condition in local hospital. Reports also suggest that many people could be trapped in their homes because of the poisonous sludge.

Continue reading “Singrauli Fly Ash Dam Breach: Who regulates these dams in India?”

Dams · DRP News Bulletin

DRP: 6 April 2020: Ganga-Yamuna-Cauvery flow cleaner in lockdown: What can we learn?

A number of reports have appeared that show that the state of a number of rivers of India, including Hindon, Yamuna, Ganga and Cauvery has improved during the current lockdown due to Covid 19 crisis. That is indeed great news. At Kanpur and Varanasi there are reports that suggest the dissolved oxygen level has gone above 8 ppm and BOD level has gone down below 3 ppm at a number of places. While lack of industrial effluents entering the rivers due to closure of industrial units is a major reason, there are other reasons that has led to this situation, including above average winter rainfall, high snowfall now melting with onset of summer, reduction of irrigation water demand and also stoppage of sand mining along the rivers. The reduction of cultural activities including puja, bathing and cremations have also contributed to this situation.

The biggest lesson we can learn from this cleaner rivers after so many decades is that if our pollution control boards at the state and central level were doing their duty to ensure that no untreated effluents from the industries and also urban sewage enter the rivers, it is not that difficult to achieve cleaner rivers. But unfortunately there is no political will to achieve this simple and legally enforceable objective.

Continue reading “DRP: 6 April 2020: Ganga-Yamuna-Cauvery flow cleaner in lockdown: What can we learn?”
Dams · Yamuna River

Yamuna Jayanti 2020: Bridges-Connecting People, Disconnecting River?

Bridges are essential infrastructure for human and cargo mobility across a river. They have also allowed us stop over and gaze on the beauty of flowing water streams without any risk of getting drowned or getting ourselves drenched in water. More and more bridges are being built on rivers without understating their impacts. There is hardly any debate or discussion on governance and decision making process or minimum distances to be maintained between two bridges or limiting the number of bridges on given stretch, considering what the river can support. This report takes a look at the situation of bridges on river Yamuna and describes few examples how they have been impacting the river eco-system. 

Continue reading “Yamuna Jayanti 2020: Bridges-Connecting People, Disconnecting River?”

Dams · DRP News Bulletin

DRP: 16 March 2020: Invitation to another Kedarnath floods tragedy?

This remarkable TOI report on March 14, 2020 (there was a Hindustan Times Report on March 9, 2020, we found out later: https://www.hindustantimes.com/india-news/scientist-flags-kedarnath-project-worries/story-1DoLBHLeMOmYLI3OPFOq1M.html) says that rampant redevelopments termed as “unabated unscientific work in the valley” around Kedarnath is likely to create dangerous situation leading to 2013 like catastrophe. We could not find report about such an important development in any other media.

But this detailed report, not contradicted by any of the quoted sources, seems sufficient reason to be alarmed by all concerned.

Experts of the Wildlife Institute of India, Wadia Institute of Himalayan Geology, Uttarakhand Space Application Centre (USAC) and even the Principle Science advisor to the Prime Minister K VIjay Raghavan and also the contractors, Woodstone Constructions along with other state and central govt officials were present where officials made some candid presentations. It seems there has been neither any impact assessment studies or clearances for the controversial interventions happening, including 9 km long approach road for Kedarnath on the left bank of Mandakini river, (left band has basically loose glacial sediments and hence is unstable and could get affected by avalanches and landslides) and a massive 50 ft deep and 100 m wide pit just 50 m behind Kedarnath for the Samadhi sthal. MPS Bisht, the Director of USAC in his presentation called the pit an extremely dangerous for future. He asked: “Why are we creating a situation for another disaster like the 2013 tragedy to take place again?” Scientists from the Wadia Institute are quoted saying: “The Road being built to Kedarnath is being made on the most vulnerable of Kedarnath Valley and may any day collapse under the pressure of so many glacier shoots which are directly opening on the road.” Raghavan called these revelations tipping points.

Continue reading “DRP: 16 March 2020: Invitation to another Kedarnath floods tragedy?”