DRP News Bulletin

DRP News Bulletin 1 March 2021: Actions speak louder than words on PM’s appeal for water, river conservation

In his #MannKiBaat on Feb 28, 2021, India’s Prime Minister Shri Narendra Modi appealed to people to conserve our Rivers, Water, referring to Magh Purnima on Feb 27 2021 and Sant Ravi Das teachings. He also said that India’s traditions, festivals, scriptures, etc have so much place for rivers, also mentioning the Kumbh mela this year at Haridwar. He mentioned that a 100 day campaign will be launched soon by the Jal Shakti Ministry for rainwater harvesting. He gave several examples from across the country where individuals and groups have taken up such words.

All that sounds fine and welcome. But the trouble is that his all-powerful government is working consistently and with increasing intensity towards opposite direction. This very week his Power Minister expressed ignorance if hydropower projects have any environmental adverse impact, right in the face of destruction wrought by the hydropower projects in Chamoli disaster in Uttarakhand on Feb 7, 2021. Why is the Union Government still pushing hydropower projects which are no longer even economically viable, they never were environmentally sustainable or socially acceptable.

Continue reading “DRP News Bulletin 1 March 2021: Actions speak louder than words on PM’s appeal for water, river conservation”
Hydro Disaster

Rishiganga HEP: A foretold disaster for River, People and Chipko legacy

The February 7 2021 Chamoli deluge has completely destroyed Rishiganga Hydro Electric Project (HEP). The 13.2 MW run of the river project has also become graveyard for over 50 innocent workers and villagers. The damages to homes, bridges, forest and river eco-system is additional which cannot be restored easily.

In fact, the disaster is among the threats against which experts and locals had been warning the authorities time and again. Sadly, the past history of struggle and destruction shows that not only the state government but the judiciary also failed miserably to address the pleas of locals and assess the disaster risks in a timely manner.

Continue reading “Rishiganga HEP: A foretold disaster for River, People and Chipko legacy”
Dams · DRP News Bulletin

DRP NB 22 Feb 2021: Case against NTPC for criminal negligence in Tapovan Project?

(Feature image: NDRF personnel carry out rescue and restoration work at damaged Tapovan Vishnugad barrage after the massive flash flood. PTI/Arun Sharma)

Consider these facts: The NTPC, the project developer, failed to appraise that the 520 MW Tapovan Vishnugad Hydropower project, where maximum damage and deaths occurred in Chamoli Avalanche disaster that started on Feb 7, 2021 morning, is in Paraglacial influence zone. Such an appraisal would have meant a number of implications, including possibly a decision that the project is geologically unviable.

NTPC failed to take any action to save the workers even after it was known upto 10-20 minutes before the disaster struck. Something that Mangshri Devi could do to save about 25 lives, NTPC could not do.

The project had faced several disasters since 2008, but fails to put in early warning system in place. For several days post disaster, reports say that NTPC failed to share even the detailed map of the tunnel where over 30 workers were stuck. NTPC’s disaster management system showed no signs of existence throughout the disaster. Reports say that the barrage gates were closed, which if they were open, it may have helped the flow of the flood debris downstream, which in turn could have possibly meant more time and saving of more lives.

Continue reading “DRP NB 22 Feb 2021: Case against NTPC for criminal negligence in Tapovan Project?”
Hydro Disaster

Tapovan Vishnugad HPP: delays, damages and destructions

(Feature image of rescue operations at Tapovan Vishnugad barrage following Feb. 7, 2021 deluge in Dhauliganga river, Chamoli. PTI Photo/Arun Sharma)

The tragic Chamoli flash flood episode has become latest and one of most vivid examples of how hydro power projects (HPP) are a recipe for disaster in geologically delicate and climatically sensitive regions of Himalaya.

Even 10 days after the deluge the Alaknanda Basin Rivers are following with muddier water. Death toll is mounting. The immense damages to infrastructure including roads, bridges, homes and hydro projects is still to be fully assessed.

The catastrophic event has offered authorities many valuable lessons: not to be blind to the preventable disasters the hydro projects are inviting frequently.

Initial findings have established that the reason behind the flash flood was detachment of snow and rocks. The fact that the hydro projects and other man made mistakes have led to most human casualties and financial losses is undisputable.

Continue reading “Tapovan Vishnugad HPP: delays, damages and destructions”