Dams · DRP News Bulletin

DRP: 25 May 2020: Review Environment Clearance Approval for Etalin Project

This letter from SANDRP to MoEF and ETC on Etalin Project highlights how poor has been the EIA and E-flows reports of the Etalin Project and how flawed has been the Environmental Appraisal Process by the EAC. It also shows the shoddy Dibang Basin study for Cumulative Impact Assessment cum Carrying Capacity Study, shockingly done by the same consultant that also did the Etalin EIA, showing clearly that MoEF, EAC and CWC, all of whom were involved in the process, do not understand what is conflict of interest. The E flows study done by the CIFRI (Central Inland Fisheries Research Institute) does not even provide the list of fish they found in the Etalin project area! And shockingly, the EAC approved the biggest ever hydropower project of India based on such shoddy documents. The Environment Clearance approval needs to be reviewed, the EIA, E-flows and Dibang Basin CIA needs to be rejected and fresh studies need to be commissioned. https://sandrp.in/2020/05/23/open-letter-to-moef-river-valley-eac-review-recommendation-to-grant-ec-to-etalin-hep/  (23 May 2020)

Continue reading “DRP: 25 May 2020: Review Environment Clearance Approval for Etalin Project”
Arunachal Pradesh · brahmaputra · Hydropower

Open letter to MoEF & River Valley EAC: Review Recommendation to grant EC to Etalin HEP

The MoEF’s Expert Appraisal Committee (EAC) on River Valley Projects in its meeting in January 2017 recommended Environmental Clearance (EC) to the controversial 3097 MW Etalin Hydropower project in Dibang River Valley in Arunachal Pradesh. However, since the stage I forest clearance to Etalin HEP has not yet been accorded, the EC letter has not yet been issued. Hence there is an opportunity to stop EC to the project till the EAC reviews its decision.

It may be noted that Forest Advisory Committee (FAC) in its meeting on April 23, 2020, has decided in the context of Etalin Project: “As this is a large sized project in the Himalayas, inputs of IA (Impact Assessment) Division of the Ministry on whether environmental impacts of the proposed project and mitigating measures have been considered, will be obtained.” This provides an opportunity for the MoEF to direct the IA Division and EAC to review its decision to recommend EC to the Etalin Project.

Continue reading “Open letter to MoEF & River Valley EAC: Review Recommendation to grant EC to Etalin HEP”

Dams · Floods

Augmentation canal breaches becoming new normal in Haryana

On May 17, 2020 the residents of Ranwar village in Karnal woke up to find their village surrounded by gushing water current which was fast entering their homes. The cause of the flooding was a breach[i] in augmentation canal running close to the village.

The incident was allegedly caused by a small hole at 60.200 point on left bank of the canal around 03.00 am gradually turning into a 40 to 50 feet wide breach by the noon same day. Before the local administration could get into action, around 250 acres of farm lands around the village was flooded.

Continue reading “Augmentation canal breaches becoming new normal in Haryana”

Environment Impact Assessment · Ministry of Environment and Forests

Draft EIA 2020 will weaken every aspect of EIA process

Experience of the current Environment Impact Assessment (EIA) process under the current EIA notification of Sept 2006 tells us that the process needs strengthening in every aspect. The Narendra Modi government has now proposed a new EIA notification, whose draft has been made public, strangely during the lockdown period. The draft notification, in stead, proposes weakening of the whole EIA process in practically every aspect. Continue reading “Draft EIA 2020 will weaken every aspect of EIA process”

Dams · DRP News Bulletin

DRP: 18 May 2020: Signs of Impending Dam Floods in SW Monsoon 2020?

These are rather ominous signs. As per the latest reservoir storage bulletin of Central Water Commission dated May 14, 2020, the 123 reservoirs monitored by CWC has massive, 64.6 BCM (Billion Cubic Meters) in live storage capacity, which is about 165% of the capacity on same date last year and average of last ten years, even as monsoon is just weeks away. Most dams known to create DAM INDUCED FLOODS in the past, including Bhakra dams (we wrote about it earlier this month: https://sandrp.in/2020/05/07/are-we-ready-to-use-more-water-from-snow-melt-in-indus-basin-this-year/), Narmada dams, Odisha and W Bengal dams (Cyclone AMPHAN is going to bring a lot of water here in next few days, even before the monsoon), Krishna basin dams, Cauvery basin dams, Bansagar and Gandhi Sagar Dams, and Kerala dams among others. All these dams have above average storage situation.

Continue reading “DRP: 18 May 2020: Signs of Impending Dam Floods in SW Monsoon 2020?”
Himachal Pradesh · Hydro Disaster

UHL hydro project disaster needs independent probe

On May 16, 2020[i], the penstocks of the 100 MW Uhl III project at Lad Bhadol in Mandi in Himchal Pradesh, under testing, burst, leading to flooding of downstream power house. 30 people working at the project were trapped but all have been rescued to safety. The power house is about 150 m from the burst point in Chulla village. Continue reading “UHL hydro project disaster needs independent probe”

Rivers · Sand Mining

Why indiscriminate river bed mining is wrong, dangerous and unethical

Guest Blog by Manoj Misra

Uttarakhand government is reportedly keen on taking up widespread river bed mining to generate around Rs 750 crore as revenue during 2020-21. More states anxious to recover revenues lost to ‘lockdowns’ due to COVID19 pandemic might also follow suit. Such indiscriminate actions would be unnatural, wrong, dangerous and even unethical.     Continue reading “Why indiscriminate river bed mining is wrong, dangerous and unethical”

Dams · Sand Mining

Yamuna facing illegal, in-stream mining during lockdown

In April May 2020, local people and media reports have highlighted riverbed mining practices going on in the Yamuna river impacting river eco-system and riparian communities in gross violation of lock down norms during the Covid 19 crisis.

The first case is reported from Yamuna Nagar district, Haryana on April 30, 2020 by Times of India, where miners had created a bund across the river in the Gumthala-Jathlana area impending the natural flow of the river.

Continue reading “Yamuna facing illegal, in-stream mining during lockdown”

Dams

Integrated Kashang Hydropower project in geologically fragile and ecologically diverse, tribal area Kinnaur, Himachal

On the 30th of April 2020, a large portion of a steep mountain in Kinnaur district of Himachal Pradesh slipped down to village Pangi destroying apple orchards and killing one Nepali migrant worker. This area in the high Himalayas, falling in the Satluj Valley, which is known for its geological and ecological vulnerability, is also the site of Stage 1 of the 243 MW Integrated Kashang Hydropower Project, which is already operational. Stage II, III and IV are yet to be constructed close to the same location and have faced massive opposition from the local tribal population on the grounds that these will spell doom for their lives, livelihoods and biodiversity. Continue reading “Integrated Kashang Hydropower project in geologically fragile and ecologically diverse, tribal area Kinnaur, Himachal”

Dams · DRP News Bulletin

DRP: 11 May 2020: Jindal accepts Etalin HEP is unviable!

This must be the defining (and predictable, this was the lead story in our DRP NB of April 27, 2020, see: https://sandrp.in/2020/04/27/drp-nb-27-april-2020-for-whom-is-this-unviable-etalin-project-being-pushed/) moment in the campaign to save the Dibang Valley now from the proposed 3097 MW Etalin Hydropower Project. The CEO of Jindal Power Ltd has said in so many words that project is NOT an attractive investment, they will struggle to find buyers for the costly power and only support from government can help make the project viable. The CEO seemed to suggest that they would be happy to sell the project to NHPC or form a joint venture with NHPC to get the govt funding for the project. Again completely on predictable line. The question then is why should government spend previous public money on such an unviable project?

So the question remains the same, the one we asked on April 27, 2020: For whom is this unviable Etalin Project being pushed?

Continue reading “DRP: 11 May 2020: Jindal accepts Etalin HEP is unviable!”