Arunachal Pradesh · Dams

Dibang Project Rejected Forest Clearance for the Second Time

PROJECT UNABLE TO SUBMIT SATISFACTORY PROPOSAL EVEN SIX YEARS AFTER PM LAID FOUNDATION STONE!

In a remarkable decision, the Forest Advisory Committee (FAC) of MoEF has rejected the forest clearance to 3000 MW Dibang multipurpose project for the second time in its meeting held on 29 -30 April 2014. In that meeting FAC considered the Dibang multipurpose project for diversion of massive 4577.84 ha of biodiversity rich forest land which would lead to cutting down of huge 3.24 lac trees.

Continue reading “Dibang Project Rejected Forest Clearance for the Second Time”

Dams

Six years after PM Laying the Foundation Stone: No Clearance, No Work for 3000 MW Dibang Dam

The foundation stone of 3000 MW Dibang Multipurpose Dam was laid on 31st January 2008, by Prime Minister Manmohan Singh. Six years have passed since then but the project is yet to get the necessary  forest and environment clearances. This in a way reflects the state of environment governance in India where the foundation stone of mega dam is laid without getting any necessary clearance. 

The affected people stopping the public hearing in 2008 since they knew that that was their only chance to be heard. Source: http://www.roingcorrespondent.in/this-circus-should-stop-no-public-hearing/
The affected people stopping the public hearing in 2008 since they knew that that was their only chance to be heard. Source: http://www.roingcorrespondent.in/this-circus-should-stop-no-public-hearing/

This project was considered for forest clearance in the FAC meeting held on July 11th and 12th 2013. The FAC meeting minutes noted “Felling of more than 3.5 lakh trees most likely to have adverse impact on general eco-system of the area, recovery of which may be very difficult through any type of mitigate measures”.

The Expert Appraisal Committee (EAC) on River valley and Hydroelectric projects considered Dibang multipurpose project in its 68th meeting on September 23rd 2013 for environment clearance but this was in complete violation of  norms. Following the “Lafarge vs Union of India and others” case of 2011, the Supreme Court of India had said that a project without forest clearance cannot be considered for environment clearance. SANDRP had pointed this out in our submission to EAC dated 20/09/2013. But EAC seemed to take no account of that.

Out of the 168 projects proposed for Arunachal Pradesh, this is the only multipurpose project. The minutes of 68th EAC meeting states that this project has dual objectives. The primary objective is flood moderation while electricity generation is its secondary objective. This is highly doubtful though since the project does not have the adequate storage capacity. On the other hand, the installed capacity of the project i.e. 3000 MW is also one of the highest among 168 hydropower projects.

The Dibang multipurpose dam is located 1.5 km upstream of confluence of Ashu Pani with Dibang river at Munli village in Lower Dibang Valley district. Construction of this dam involves two districts of  Arunachal  Pradesh  viz.  Lower Dibang Valley and  Dibang Valley districts. All the project components e.g. dam, power house will be are located in Lower Dibang Valley District while reservoir which will submerge 43 km length of the river will fall in both districts.  The total land requirement for this dam is 5794.142 ha out of the 5022.842 is forest area with very rich bio-diversity. Submergence of such a huge forest is one of the major concerns associated with this dam and that is why the Forest Advisory Committee (FAC) has refused forest clearance to this project.

The Dibang multipurpose project plans to construct 288 meter high concrete gravity dam with an underground dam toe power house. The reservoir of this project will submerge 40.09 sq km area. The total cost of the project at November 2007 price level was estimated at 15886.39 crores.

It is important to note that the public hearing for the project faced vehement opposition of the local people. The public hearing of the project has been halted for several times. The local people expressed serious concern regarding Dibang multipurpose project and feared that influx of outsiders for dam building will lead to a demographic imbalance in the Dibang valley. This is a serious issue since the primary inhabitants of Dibang valley are Mishmi (Idu) which is a very small community with a population of 11,023 according to 2001 census. According to NHPC estimation a workforce of 5800 people (labour and technical staff) would be needed for the Dibang multipurpose project. But All Idu Mishmi Students Union (AIMSU) has contested this figure and opined that a single project would bring about 15,000 people into the region. It is also reported that NHPC claim that the project will cause ‘negligible human displacement’ grossly undermines its harmful impacts on smaller ethnic community such as Idu Mishmis. A video of the protest by local people can be seen here – http://www.youtube.com/watch?v=m8TCUKh2hQY

No cumulative impact assessment of dams in Dibang valley has been conducted e even though 17 projects have been proposed for this region. The TOR clearance had been given to 86 MW Ithum and 3097MW Etalin HEP in the basin by EAC. Without any cumulative impact assessment study of the basin no project should be given environment clearance. People from Dibang valley has also written to previous EAC on demanding cumulative impact assessment study. A letter to EAC from a local person Raju Mimi, dated January 31st 2013 stated “Since the 3097 MW Etalin project is on agenda again for the 64th EAC meeting to be held on Feb 1st – 2nd 2013, we re-iterate our demand to have prior cumulative impact assessment of multiple hydropower projects by urgently commissioning a Dibang river basin study.”

Other Glaring Issues of Dibang Multipurpose Along with the above mentioned issues SANDRP had made detailed submission to EAC pointing to some of the glaring concerns associated with the project. Some of these issues are –

Incomplete and Shoddy Downstream Impact Assessment: The downstream impact assessment done for the Dibang multipurpose does not take into account impacts of the dam in Assam. The downstream impact assessment study does no assessment beyond   Dibru-Saikhowa and whatever has been done is also very much inadequate.

No Public Hearing Held in Assam: Even though the Dibang multipurpose will have severe impacts in downstream Assam, there was no public hearing held for the project in Assam.

Mining for the Dibang Multipurpose will lead to Catastrophes: Mining of boulder, sand and other construction material for the Dibang multipurpose project will have very severe impacts on the river as well as on the local environment. The amount of boulder required for the construction of this project is 193 lakh cubic meter as stated in the project document. This is really astonishing figure and impact of such mining on the river bed and nearby areas will be catastrophic. The fragility of the Himalayan mountain range is not unknown to anyone and mining in such a sensitive hilly area will area will only increase the risk of landslide and disaster. The catastrophe of Uttarakhand floods is a clear example of this.

No Climate Change Assessment Impact of climate change on the project and impact of the project on the local climate. No attempt has been made to assess the impact of green house gas emissions from the reservoir of the dam which extends to 43 km.

No assessment impacts of peaking power operations Impacts Detail assessment of impacts of peaking power operation during non-monsoon months not done. Impacts on the flow characters of the river due to this dam, what will be the changes and how these will impact downstream areas.

No Assessment of Disaster Potential Impact of the project on disaster potential in the project area as well in the downstream including Assam due to construction and also operation at various stages, say on landslides, flash floods, etc.

No Assessment of Silt Flushing Impact of changing silt flows downstream from desilting chamber and from silt flushing in monsoon on the downstream areas not analyzed. A detail account of how the silt from the dam would be flushed out annually and what would be the impact of this in the downstream  as well as on the geo morphology, erosion, stability of structures etc was not done.

What did the EAC say in 68th Meeting The EAC in its 68th meeting did not recommend environment clearance to the project and instead pointed out several issues in the EIA – EMP report. Some of the important issue pointed out by EAC are –

1. Attempts may be made to avoid  submergence  of huge area  of rich forest land. It merits mention that  due to the very high forest land  submergence,  forest clearance has not yet been accorded by FAC.

2. Environmental Flow in the diverted portion of about 1.2 km  i.e. between dam and TWL  of dam toe PH  is to be reassessed and  a  suitable quantity is to be proposed for release as per extant norms. 4% flow as suggested was found to be inadequate.

3. Numbers of Fish species  reported was found to be on lower side and NHPC was asked  to verify this and report accurately.

4. Number  of  plant  species  reported  also  appeared  to  be  on  lower  side    and  to  be rechecked by NHPC.

5.At  this  altitude  of  the  project  (about  3000m),  snow  leopard  should  have  been sighted. It may be erroneous to report that leopard was not found  in the study area. Therefore, this may be relooked.

6. Study  area  in back water/ submergence is also to be  extended for proper inventory of both flora, fauna/bio-diversity.

The impacts of the Dibang multipurpose project are going to severe on the river, people and overall ecology of Dibang river basin. But sad part is that no proper assessment of these impacts has been done till now. Looking back at the six years since the laying foundation stone for the project we reiterate what Forest Advisory Committee said about the project “ecological, environmental and social costs of diversion of such a vast tract of forest land, which is a major source of livelihood of the tribal population of the State, will far outweigh the benefits likely to accrue from the project.”

Parag Jyoti Saikia

Ministry of Environment and Forests

Open Letter to UPA Leadership: Please Remove Mr. Moily from Paryavaran Bhawan

OPEN LETTER TO UPA LEADERSHIP:

Do you know how much Aam people depends on Environment?

Do you understand what is conflict of interest?

Do you at all get the message from Aam people?

Please immediately remove Moily from MoEF if you do!

Dear Dr Manmohan Singh, Mrs Sonia Gandhi and Mr Rahul Gandhi,

On December 21, 2013, Congress Vice President Rahul Gandhi said at a FICCI meeting  (see the video of this clip uploaded by Indian National Congress: http://www.youtube.com/watch?v=URnr8OKTygg),  “Many of you expressed your frustrations with environmental clearances that they are delaying projects unduly. There is excessive pic 1administrative and judicial discretion. The loopholes are so big that you can drive a truck through some of them. Environmental and social damage must be avoided, but decisions must also be transparent, timely and fair.”

Mr Rahul Gandhi, you are right. The loopholes are so big in our environmental regulations that one can drive a truck through some of them. However, this is a grand understatement. The loopholes in our environmental regulations are in fact so big that even whole dams, mines, mountains and rivers can be driven through them. You are right that decisions must be transparent, timely and fair. Have you had a look at the official website of environmental clearances (http://environmentclearance.nic.in/) or forest clearances (http://forestsclearance.nic.in/) or CDM clearances (http://www.cdmindia.gov.in/), all under Union Ministry of Environment and Forests (http://envfor.nic.in/)? Please do go through the website and let us know if you manage to get the copy of the latest (timely) clearances (transparency) or understand how the decisions have been arrived at (fair decisions). Your statements, that too at the meeting of industrialists’ vested interest lobby like FICCI, only shows, sir, that you have been so poorly informed about the functioning of MoEF, to put it most charitably.

On the same day of Mr Gandhi’s statement, the Union Minister of State of Environment and Forests (Independent Charge) Mrs Jayanthi Natarajan resigned and the Prime Minister Dr Manmohan Singh handed over the charge of the Environment and Forests portfolio to Union Petroleum Minister Veerappa Moily. From day one in office at Paryavarahan Bhawan, Mr Veerappa Moily has earnestly started to dismantle whatever little and poor environmental regulation exists in this country. This is disastrous for the people and future of India and also for the future of UPA.

The Prime Minister Dr Manmohan Singh said at his press conference on Jan 3, 2014 (http://www.ndtv.com/video/player/news/pm-rules-out-third-term-says-he-will-hand-over-baton/303780?pfrom=home-topstories), “There were bottlenecks in terms of timely clearances of the projects from the point of view of environmental-forests clearances.” Mr Prime Minister, this only shows how ill-informed you are (again to put it most charitably) or you choose to be.   To give you just one instance, the Expert Appraisal Committee appointed by your government on River Valley and Hydropower projects have not rejected environment clearance a single project in last seven years (for details see: https://sandrp.in/env_governance/TOR_and_EC_Clearance_status_all_India_Overview_Feb2013.pdf). Even when all of the members of the standing committee of the National Board for Wildlife unanimously rejected Wildlife Clearance to Lower Demwe Dam in Arunachal Pradesh for its disastrous impacts on communities and ecosystems in downstream Assam, Jayanti Natarajan, as the chairperson of the Committee, sanctioned it. On Forest clearance also the story is almost same. pic 2 Here in rare event when the statutory Forest Advisory Committee (twice) rejected forest clearance for the 300 MW Alaknanda Badrinath Hydropower project, your minister Mrs Natarajan overturned the FAC decision and gave clearance (it should be clear that we are not writing this in defense of Mrs Natarajan’s tenure at MoEF). In another instance, when FAC said no to Kalu Dam near Mumbai in April 2012, a more pliable FAC was put in place and your party Chief Minister from Maharashtra wrote to FAC to clear it and lo and behold, in April 2013 it was cleared! Mr Prime Minister sir, you yourself have gone ahead and laid foundation stone for the 3000 MW Dibang Hydropower Project in Arunachal Pradesh on January 31, 2008, when the project did not have statutory environment and forest clearances, the project still does not have them, because the basic studies have still not been done. All this only shows how off the mark your statements are.

As we wrote in our blog (https://sandrp.wordpress.com/2013/12/21/veerappa-moily-as-environment-minister-has-the-upa-leadership-learnt-no-lessons-from-aap-experience/) on December 21, 2013, the appointment of Mr Veerappa Moily is most shocking and bizarre, showing that UPA leadership  do not seem to appreciate or understand the extent to which poor people of this country depend on environmental resources including forests, rivers, hills and biodiversity. You all also do not seem to understand the issue of conflict of interest: How can Petroleum minister be given the charge of environment and forests?

The petition on this issue (see: http://www.change.org/en-IN/petitions/government-of-india-the-same-minister-for-oil-and-environment-how-is-that-reasonable) has by now been signed by close to 700 people and more people continue to endorse it, I am writing this on behalf of all of them.

Mr Gandhi, while we agree that the decisions need to be transparent and fair, but they also need to be democratic, well-informed and professional, and that means much better Environmental Impact Assessments, people with understanding of environment at the helm of Appraisal Committees and of course, informed participation and consent of the impacted people in the impact assessment and in decision making too, as also credible compliance mechanism in place. That is one of the key messages that we can get from recent events in India, but it seems to be falling on deaf years.

Among other things, this whole episode highlights poor is the understanding of UPA leadership to the signals that Aam people of this country have been sending. You are ignoring these signals at your own peril.

The least we expect you to do is to remove Mr Veerappa Moily from the post of Minister of Environment and Forests and replace him with a credible person immediately. There is of course a lot more you can do if you are really interested in the well being and future of Aam people and environment of this country.

Yours Sincerely,

Himanshu Thakkar

To: pmosb@pmo.nic.in, manmohan@sansad.nic.in, soniagandhi@sansad.nic.in, chairperson@nac.nic.in, office@rahulgandhi.in