December 27, 2016
Continue reading “Ken Betwa Link: Letter to Water Resources Minister and EAC in Dec 2016”
South Asia Network on Dams, Rivers and People
December 27, 2016
Continue reading “Ken Betwa Link: Letter to Water Resources Minister and EAC in Dec 2016”
Finally, tribals struggle wins, sends Jispa HEP company packing up Facing stiff opposition from the tribal community against the construction of 300 MW Jispa Dam in Lahaul-Spiti valley has forced the Himachal Pradesh Power Corportaion Ltd (HPPCL) to suspend the project for the time being. The dam which was declared a project of national importance now has residents from 14 villages oppose it. HPPCL has invested Rs 3 crore and has stated that it would begin study work only when locals extend their support.
Since 2009, people from the Todh valley in Lahaul-Spiti district were opposing the Jispa Dam project proposed over Bhaga river, a tributarJy of Chenab at Jispa village. The government had sanctioned Rs 7,000 crore for this project but local residents did not allow officials to work in smoothly for three years now.
Confirming the development, managing director, HPPCL, D K Sharma told that some people were continuously opposing the project without realizing that construction of project could have ushered development in the area. He said constant opposition of local people had resulted into wastage of limited human resource so HPPCL board had decided to withdraw the manpower as project was only at investigation stage.
Indeed, Rivers, including the Inter Linking of Rivers (ILR) needs democracy, in which dialogue is the starting point. The government, with all its powers, mandate and resources, needs to initiate this. Particularly when the government has taken such an ideological, fundamentalist position on ILR. So much so that the Union Minister says that anyone opposing the project is committing a national crime. And even goes to the extent of threatening even statutory regulators if the controversial Ken Betwa River Link proposal is not cleared in next meeting! That very minister is scheduled to conclude the “dialogue” of Aug 6, 2016 (to be held during 4-7 pm at Constitutional Club Rafi Marg, Delhi), is ironical to say the least. [As I was writing this, I got a call from Ms Uma Bharti ji’s home saying that she won’t be able to come for the meeting today as she is down with high fever. I hope she recovers soon and fully.] Continue reading “Rivers and ILR need democracy: There is none today; BUT THIS AUG 6 MEETING IS NO DIALOGUE”
Above: A fabulous view of Ken river. Nesting sites of Long-billed vultures are to the right. All will go under water if Ken-Betwa linkup is carried out, PHOTO by: AJT Johnsingh
It’s a curious case of Dam fundamentalism: now manifest as ILR fundamentalism. On June 7, 2016, (as widely reported by media[i]) Union Water Resources Minister Uma Bharti “threatened to go on hunger strike if the Ken-Betwa river linking project is further delayed and termed the attempt to delay the project by environmentalists as a “national crime”” as reported by Business Standard. The threat was directed against all those raising questions about Ken Betwa River Link proposal of her ministry. Continue reading “ILR fundamentalism: Union Minister threatens regulators, media and civil society”
New Hydro Policy: Govt unjustifiably pushing hydro through subsidies A comprehensive policy to promote hydropower generation is set to be announced by September—with viability gap funding for projects, compulsory hydropower purchase obligations for distribution companies and a set of good practices that states have to follow. The idea is to address factors that currently drive hydropower costs up way above those of other sources of power and give policy support in its market development, according to a government official, who asked not to be named. The policy being prepared by the power ministry will have provisions for viability gap funding, which will help in meeting the shortfall in project costs and reducing hydroelectricity tariffs for consumers. Hydropower is expensive and in some cases more than double the cost of power from coal-based thermal plants, which is available at Rs.3-5 per unit.The ministry will also expand the scope of power distribution companies’ renewable power purchase obligations to include hydropower from projects with a capacity greater than 25 Mw. At the moment only power from those with less than 25MW is considered renewable power. According to officials, compulsory hydropower purchase from large projects will either be made part of the existing renewable power purchase obligation of distribution companies or a separate requirement, so that its inclusion does not affect the market for other renewable sources of energy like wind, solar or biomass. Govt unjustifiably pushing hydro through subsidies in proposed new hydro policy can be lead story. It is not going to help push hydro. Continue reading “DRP News Bulletin 04 July 2016 (In Proposed Hydro Policy, Govt Unjustifiably Pushing Hydro Through Subsidies)”
Uma threatens stir over delay in Ken-Betwa interlinking Water Minister Uma Bharti on June 07 threatened an agitation if there were further delays to the wildlife clearances necessary for the storied Ken-Betwa river-interlinking project. This is TOO Much! Union Minister threatening to go on Fast, demanding environment clearance to Ken Betwa link! Calling it a national crime to stop clearance to Ken Betwa link. Saying if the project is not cleared in next meeting, she will go on fast! Claiming that the link will help Marathwada!! It wont help even Bundelkhand, but the Union Minister seems to be setting completely wrong, precedent, which also ultra legal. On the other hand The Hindu has been consistently underplaying the impacts of the Ken Betwa project and over playing the official lines. Very strange to see this from THE HINDU. Before this in its June 02 meeting the expert appraisal committee (EAC) of environment ministry has deferred environment clearance for the ambitious Rs.10,000cr Ken-Betwa river linking project in its last meeting on June 2, and has sought more clarity on its wildlife & hydrological impact. The meeting could not come to a conclusion as the members of the EAC had several doubts regarding the project’s hydrological feasibility, its impact on hydrology and wildlife too and found that many serious issues related to the project are yet to resolved. In the last week of May 2016, SANDRP in a letter to EAC has written about Ken-Betwa project & why EAC should not clear this. Please help us spread the word and urgently write to EAC if you agree. Himanshu Thakkar coordinator SANDRP points out that the Ken-Betwa link, in essence, Ken-Betwa link will facilitate transfer of water from the Ken River Basin (Bundelkhand) to Upper Betwa Basin (outside Bundelkhand), so it is actually exporting water out of Bundelkhand.
India will not have power deficit situation in FY17 India won’t need any new power plants for the next three years as it is flush with generation capacity, according to a government assessment. The country can manage for the next three years with existing plants that are currently under-utilised, and those that are under construction and upcoming renewable energy projects, assessment made by the power ministry for reviewing the National Electricity Policy shows. Govt declares for the first time in history that India is POWER SURPLUS in 2016-17 with 3.1% power surplus in peak hours and 1.1% power surplus in off peak hours, both figures in 2015-16 were -3.2% during peak hours and -2.1% in peak hours. The western and Southern regions will be power surplus, but Northern, Eastern and Northeastern regions will have deficits. At the same time Power Minister Piyush Goyal says that Big hydro power units may come under renewable energy According to Minister the Centre has begun studies to decide whether to include big hydro power plants under the ambit of renewable energy. When India will be energy surplus for next three years why then Govt. of India is continue to pursue disastrous hydro projects on ground. Where ASSOCHAM is asking Arunachal govt. to do away with adverse tax policies on Hydro power to boost construction of hydro projects in the State. NHPC has also raised relief amount for Kishanganga HEP around Rs 60 lakh and Rs 70 lakh to each family for the land acquired. And despite Delhi Govt. openly rejecting water from Renuka dam NGT panel has visited the area to look into the rehabilitation issue.

The official minutes of the 37th meeting of the Standing Committee of the National Board of Wild Life (NBWL) held on Feb 26, 2016, about the Ken Betwa Link Project (KBLP) Phase I have exposed the lies of project developer National Water Development Agency (NWDA) and its consultant for Environment Impact Assessment (EIA) about a number of crucial aspects of the project impact on the Panna Tiger Reserve, Vulture Habitat and Ken Ghariyal Sanctuary.
It now becomes clear that both NWDA and EIA consultant AFCL (formerly Agriculture Finance Corporation Ltd) are guilty of misleading the MoEF’s (Ministry of Environment, Forests and Climate Change) Expert Appraisal Committee (EAC) on River Valley Projects, when the KBPL was discussed by the EAC during Aug 24-25, 2015, Oct 26-27, 2015 and Feb 7-8, 2016. We hope the EAC will take appropriate action against the developer and the EIA consultant for misleading the statutory official agency. Continue reading “NWDA & EIA lies on Ken Betwa River Link nailed by IGF (WL): Will EAC take action against them now?”
Even as the Expert Appraisal Committee on River Valley and Hydropower Projects sits to decide about Environment Clearance to Ken Betwa River Link Proposal on Feb 8-9, 2016, a number of people have written to the committee against recommending clearance to the project. We are publishing here some of them: Continue reading “LETTERS TO EAC & MOEF: KEN BETWA LINK IS A TRAGEDY: DON’T BURN LIFEBOATS TO STAY WARM ON SINKING TITANIC SHIP”
Above: A fabulous view of Ken river. Nesting sites of Long-billed vultures are to the right. All will go under water if Ken-Betwa linkup is carried out, Photo by AJT Johnsingh
November 3, 2015
To
Chairman & Members, NBWL Standing Committee, MoEF&CC, New Delhi
Respected Chairman and members,
We have just learnt that NBWL standing committee is to meet tomorrow, that is Nov 4, 2015 and one of the proposals that the NBWL is to consider is the Ken Betwa River Link proposal INSIDE Panna Tiger Reserve. We are unable to find the agenda, agenda papers and names and contact details of the NWBL SC members. Prudent, transparent and democratic decision making requires that these should be in public domain at least two weeks in advance of the NWBL meeting, so that all concerned from any part of the nation can know about this, and write to NBWL with their views and concerns. We hope MoEF, full NBWL and NBWL standing committee will take urgent steps to ensure that until this minimum requirement is satisfied, no meeting of NBWL or NBWL SC is held, and we request you postpone the meeting proposed on Nov 4, 2015 till this requirement is fulfilled. Continue reading “Open Letter to NBWL Standing Committee Members: Why NBWL should not consider Ken Betwa River Link Proposal”