Disasters · Hydropower · Uttarakhand

Uttarakhand: Existing, under construction and proposed Hydropower Projects: How do they add to the state’s disaster potential?

 

As Uttarakhand faced unprecedented flood disaster and as the issue of contribution of hydropower projects in this disaster was debated, questions for which there have been no clear answers were, how many hydropower projects are there in various river basins of Uttarakhand? How many of them are operating hydropower projects, how many are under construction and how many more are planned? How many projects are large (over 25 MW installed capacity), small (1-25 MW) and mini-micro (less than 1 MW installed capacity) in various basins at various stages?

This document tries to give a picture of the status of various hydropower projects in various sub basins in Uttarakhand, giving a break up of projects at various stages, As per available information in July 2013.

River Basins in Uttarakhand Entire Uttarakhand is part of the larger Ganga basin. The Ganga River is a trans-boundary river, shared between India and Bangladesh. The 2,525 kms long river rises in the western Himalayas in the Indian state of Uttarakhand, and flows south and east through the Gangetic Plain of North India into Bangladesh, where it empties into the Bay of Bengal. The Ganga begins at the confluence of the Bhagirathi and Alaknanda rivers and forms what we have called Ganga sub basin till it exits Uttarakhand. Besides Bhagirathi, Alaknanda and Ganga sub basin, other river basins of Uttarakhand include: Yamuna, Ramganga (Western Ramganga is taken as Ramganga basin in this document, eastern Ramganga is considered part of Sharda basin) and Sharda. Sharda sub basin includes eastern Ramganga, Goriganga, Dhauliganga, Kaliganga and part of Mahakali basin.

Destroyed 400 MW Vishnuprayag HEP on Alaknanda. Photo: Matu Jan Sangathan
Destroyed 400 MW Vishnuprayag HEP on Alaknanda. Photo: Matu Jan Sangathan

Existing hydropower projects in Uttarakhand In the table below we have given the sub basin-wise list of existing hydropower projects in Uttarakhand along with their capacities. The list has been prepared based on various sources including Central Electricity Authority, Uttarakhand Jal Vidhyut Nigam (UJVNL), Uttarakhand Renewable Energy Development Authority (UREDA) and Report of Inter Ministerial Group on Ganga basin.

Existing Hydropower projects in Uttarakhand

 

Projects

Installed Capacity  (MW)

Projects in Alaknanda River Basin

1. Vishnu Prayag (P)

400

2. Tilwara

0.2

3. Soneprayag

0.5

4. Urgam

3

5. Badrinath II

1.25

6. Rajwakti (P)

3.6

7. Tapowan

1

8. Jummagad

1.2

9. Birahi Ganga (P)

7.2

10. Deval (P Chamoli Hydro P Ltd on Pinder)

5

11. Rishiganga (P)

13.5

12. Vanala (P Hima Urja P Ltd Banala stream)

15

13. Kaliganga I (ADB)

4

Alaknanda Total

455.45

Projects in Bhagirathi River Basin

14. Maneri Bhali-1 (Tiloth)

90

15. Maneri Bahli-2

304

16. Tehri St-I

1000

17. Koteshwar

400

18. Harsil

0.2

19. Pilangad

2.25

20. Agunda Thati (P Gunsola hydro Balganga river)

3

21. Bhilangana (P – Swasti)

22.5

22. Bhilangana III (P – Polyplex)

24

23. Hanuman Ganga (P – Regency Aqua)

4.95

Bhagirathi Total

1850.9

Projects in Ganga River sub basin downstream of confluence of Bhagirathi and Alaknanda

24. Chilla

144

25. Pathri

20.4

26. Mohamadpur

9.3

Ganga sub basin Total

173.7

Projects in Ramganga basin

27. Ramganga

198

28. Surag

7

29. Loharkhet (P Parvatiya Power P Ltd Bageshwar)

4.8

30. Kotabagh

0.2

31. Sapteshwar

0.3

32. Gauri

0.2

Ramganga Total

210.5

Projects in Sharda River Basin

33. Dhauliganga

280

34. Tanakpur

94.2

35. Khatima

41.4

36. Chirkilla

1.5

37. Taleshwar

0.6

38. Suringad

0.8

39. Relagad

3

40. Garaon

0.3

41 Charandev

0.4

42. Barar

0.75

43. Kulagad

1.2

44. Kanchauti

2

Sharda Total

426.15

Projects in Yamuna River Basin

45. Chibro

240

46. Dhakrani

33.75

47. Dhalipur

51

48. Kulhal

30

49. Khodri

120

50. Galogi

3

51. Tharali

0.4

Yamuna Total

478.15

Grand Total

3594.85

Note: (P) in the bracket suggests the project is in private sector, throughout this document. The eastern Ramganga river, which is part of Sharda basin, is included in Sharda basin. Where-ever Ramganga river is mentioned in this document, it refers to Western Ramganga, which is a tributary of Ganga.

Alaknanda flowing beyond the destroyed 400 MW Vishnuprayag Project Photo: Matu Jan Sangathan
Alaknanda flowing beyond the destroyed 400 MW Vishnuprayag Project Photo: Matu Jan Sangathan

In the next table we have given available list of existing mini and micro hydropower projects in Uttarakhand, based on UREDA information.

List of projects up to 1 MW under operation:

 

SN Project

Ins Cap (MW)

Dist Basin
1 Milkhet

0.1

Chamoli Alaknanda
2 Bamiyal

*

Chamoli Alaknanda
3 Bursol

0.2

Chamoli Alaknanda
4 Choting

0.1

Chamoli Alaknanda
5 Ghagaria

0.1

Chamoli Alaknanda
6 Ghagaria Extension

*

Chamoli Alaknanda
7 Ghes

0.1

Chamoli Alaknanda
8 Gulari

0.2

Chamoli Alaknanda
9 Niti

0.025

Chamoli Alaknanda
10 Sarma

0.1

Chamoli Alaknanda Nandakini/ Maini Gad
11 Wan

0.05

Chamoli Alaknanda
12 Bank

0.10

Chamoli Alaknanda Pinder
13 Gamsali Bampa

0.05

Chamoli Alaknanda Dhauliganga/Ganesh Ganga
14 Kedarnath II

0.2

Rudraprayag Alaknanda
15 Badiyakot

0.1

Bageshwar Alaknanda
16 Kunwari

0.05

Bageshwar Alaknanda
17 Borbalada

0.025

Bageshwar Alaknanda Pindar/ Chhiyaldi Gad
18 Dokti

0.02

Bageshwar Alaknanda
19 Dior IInd Phase

*

Pauri Alaknanda/ Ganga
20 Chandrabhaga Gad

*

Tehri Bhagirathi
21 Jakhana

0.1

Tehri Bhagirathi Bhilangana/Balganga
22 Gangotri-I

0.1

 UttarKashi Bhagirathi Kedar Ganga
23 Kanwashram

0.1

Pauri Ganga
24 Bilkot

0.05

Pauri Ramganga
25 Dior Ist Phase

0.1

Pauri Ramganga
26 Gogina II

0.05

Bageshwar Ramganga
27 Sattshwar

0.05

Bageshwar Ramganga
28 Toli

*

Bageshwar Ramganga
29 Ramgarh

0.1

Nainital Ramganga
30 Lathi

0.1

Bageshwar E Ramganga/Sharda
31 Liti

0.05

Bageshwar E Ramganga/Sharda
32 Liti-II

0.05

Bageshwar E Ramganga/Sharda
33 Ratmoli

0.05

Bageshwar E Ramganga/Sharda
34 Baghar

0.05

Bageshwar E Ramganga/Sharda
35 Baicham

0.1

Bageshwar E Ramganga/Sharda
36 Jugthana

0.1

Bageshwar E Ramganga/Sharda
37 Kanol gad

0.1

Bageshwar E Ramganga/Sharda
38 Karmi

0.05

Bageshwar E Ramganga/Sharda
39 Karmi -III

0.05

Bageshwar E Ramganga/Sharda
40 Karmi-II

0.05

Bageshwar E Ramganga/Sharda
41 Bhikuriya Gad

0.5

Pithoragarh Sharda
42 Kanchauti

*

Pithoragarh Sharda
43 Lamabager

0.20

Bageshwar Sharda Saryu
44 Lamchula

0.05

Bageshwar Sharda Saryu
45 Tarula

0.10

Almora Sharda Saryu/Jataya Ganga
46 Taluka

0.025

Uttarkashi Yamuna Tons/ Gattu Gad
47 Bhadri Gad

0.02

Tehri Yamuna

From http://ahec.org.in/, capacity of some of the projects is as per the UJVNL website. The capacity comes to 3.815 MW for the 41 projects for which capacity is available, for six mini-micro HEPs in Uttarakhand listed above, this information is not available..

 

5 MW Motigad Project in Pithorgarh District destroyed by the floods. Photo: Emmanuel Theophilus, Himal Prakriti
5 MW Motigad Project in Pithorgarh District destroyed by the floods. Photo: Emmanuel Theophilus, Himal Prakriti

Based on above two tables, in the following table we have provided an overview of operating hydropower projects and their capacity, with basin wise and size wise break up.

Uttarakhand has total of 98 existing hydropower projects, with total installed capacity of close to 3600 MW. At least eleven of these projects are in private sector with total capacity of over 503 MW. An additional about 1800 MW capacity is in central sector. It means that majority of the power generation capacity in the state is not owned by the state and there is no guarantee how much of that power would be available to the state.

 

Basin wise number of operating hydro projects in Uttarakhand

 

Basin Large Hydro projects (above 25 MW) Small Hydro projects (1-25 MW) Mini-micro Hydro projects (below 1 MW) Total Hydro projects
No of projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW
Alaknanda

1

400

10

54.75

21

2.22

32

456.97

Bhagirathi

4

1794

5

56.7

4

0.4

13

1851.1

Ganga Sub basin

1

144

2

29.7

1

0.1

4

173.8

Ramganga

1

198

2

11.8

9

1.05

12

210.85

Sharda

3

415.6

4

7.7

21

4.45

28

427.75

Yamuna

5

474.75

1

3

3

0.445

9

478.195

TOTAL

15

3426.35

24

163.65

59

8.665

98

3598.665

 

Here we should note that as per the Union Ministry of New  and Renewable  Energy sources, in Uttarakhand, by March 2013, 98 small hydro schemes has been installed with total capacity of 170.82 MW. If we add the small and mini-micro projects in above table, we have 83 operating schemes with installed capacity of 172.315 MW. This mis-match is not possible to resolve since MNRE does not provide full list of operating SHPs in Uttarakhand.

 

Under Construction Hydropower projects in Uttarakhand In the table below we have given available list of under construction hydropower projects in Uttarakhand. Actual list of under construction projects is likely to be larger than this, since clear and uptodate information is not available on official website. Please note that this does not include the list of mini and micro hydropower projects that are under construction. Even in case of small hydro projects (1-25 MW capacity), the list is not complete. According to this list, 41 projects with 2378.115 MW capacity are under construction in Uttarakhand. 6 of them are large hydropower projects and rest 35 are small or mini-micro hydro projects. Of the 6 large hydropower projects, three are in private sector and three are in central sector, none in state sector.

 

Mountains of Muck generated by under construction 330 MW Shrinagar Hydel Project
Mountains of Muck generated by under construction 330 MW Shrinagar Hydel Project

List of under construction projects:

 

SN Project Ins Cap (MW) Dist Sub-Basin
1 Srinagar

330

Pauri Alaknanda
2 Phata- Byung

76

Rudraprayag Alaknanda
3 Singoli-Bhatwari

99

Rudraprayag Alaknanda
4 Lata Tapovan

171

Chamoli Alaknanda
5 Tapovan Vishnugad

520

Chamoli Alaknanda
6 Madhmaheshwar (ADB)

10

Rudrprayag Alaknanda
7 Kaliganga-II (ADB)

6

Rudrprayag Alaknanda
8 Bgyunderganga (P)

24.3

Chamoli Alaknanda
9 Birahi Ganga-I (P)

24

Chamoli Alaknanda
10 Devali (P)

13

Chamoli Alaknanda
11 Kail ganga

5

Chamoli Pinder Alaknanda
12 Khiraoganga (P)

4

Uttarkashi Alaknanda
13 Sobla I

8

Pithoragarh Alaknanda
14 Hafla

0.2

Chamoli  Alaknanda Hafla Gad
15 Nigol Gad

0.1

Chamoli  Alaknanda Nigal Gad
16 Wachham

0.50

Bageshwar Alaknanda Pindar/SunderDhunga Gad
17 Tehri stage-II

1000

Tehri Bhagirathi
18 Asiganga-I

4.5

Uttarkashi Bhagirathi
19 Asiganga-II

4.5

Uttarkashi Bhagirathi
20 Suwarigad

2

Uttarkashi Bhagirathi
21 Limchagad

3.5

Uttarkashi Bhagirathi
22 Kaldigad (ADB)

9

Uttarkashi Bhagirathi
23 Balganga-II

7

Tehri Garhwal Bhagirathi
24 Jalandhari Gad (P)

24

Uttarkashi Bhagirathi
25 Kakora Gad (P)

12.5

Uttarkashi Bhagirathi
26 Kot-Buda Kedar (P)

6

Tehri Bhagirathi
27 Siyangad (P)

11.5

Uttarkashi Bhagirathi
28 KotiJhala

0.2

 Tehri Bhagirathi Bal Ganga
29 Pinsward

0.05

 Tehri Bhagirathi Bal Ganga
30 Dunao

1.5

Pauri Ganga sub basin
31 Gaudi Chida

0.25

Pauri Ganga sub basin E Nayar
32 Rotan

0.05

Pithoragarh Sharda E Ramganga/Rotan
33 Duktu

0.025

Pithoragarh Sharda Kali/ Nati Yanki
34 Nagling

0.05

Pithoragarh Sharda Kali/ Nagling Yanki
35 Sela

0.05

Pithoragarh Sharda Dhauli Ganga/ Seal Gad
36 Kutty

0.05

Pithoragarh Sharda Kali
37 Napalchu

0.05

Pithoragarh Sharda Kali/ Piear Yanki
38 Bundi

0.05

Pithoragarh Sharda Kali/ Pulung Gad
39 Rongkong

0.05

Pithoragarh Sharda Kali/ Dangiang Yanki
40 Chiludgad

0.10

Uttarakashi Yamuna Supin/Chilude Gad
41 Khapu Gad

0.04

Uttarakashi Yamuna Supin/Khapu Gad

Total Under Construction               2378.115 MW

Note: Projects like Loharinag Pala, Pala Maneri, Bhairoghati and other projects along Bhagirathi upstream of Uttarkashi along the Eco Sensitive zone have been dropped from this list. Rest of the list is from the IMG report or from UJVNL website. P in the bracket indicates the project is in the private sector. ADB in the bracket indicates that the project is funded by the Asian Development Bank.

 

Proposed hydropower projects in Uttarakhand In following tables we have provided available list of proposed hydropower projects in the Alaknanda, Bhagirathi, Yamuna, Sharda and Ramganga basins in Uttarakhand. The list is likely to be longer than the list in these tables since full and upto-date information is not available. Also there are different agencies  involved in proposing, sanctioning and executing these projects and there is no single agency which can provide comprehensive picture of what is happening in the basin. However, even this available list is frightening.

 

List of proposed projects in Alaknanda Basin

 

SN Project Ins Cap (MW) Dist Sub-Basin Status
1 Vishnugad Pipalkoti (WB)

444

Chamoli Alaknanda Construction to be started
2 Kotli Bhel (IB)

320

Pauri Alaknanda EAC ok/FAC u/consideration
3 Alaknanda (P Badrinath)

300

Chamoli Alaknanda EC & FC ok IA not signed
4 Devsari Dam

252

Chamoli Alaknanda EC & FC ok CEA concrnce?
5 Kotli Bhel II

530

Pauri Ganga sub basin EAC ok/FAC u/consideration
6 Bowla Nandprayag

300

Chamoli Alaknanda EAC TOR Approved
7 Tamak Lata

280

Chamoli Alaknanda EC ok, DPR under revision
8 Nand Prayag

100

Alaknanda DPR returned
9 Jelam Tamak

108

Chamoli Alaknanda EAC ok in June 2013
10 Maleri Jelam

55

Chamoli Alaknanda PFR prepared
11 Rishiganga I

70

Chamoli Alaknanda PFR prepared
12 Rishiganga II

35

Chamoli Alaknanda PFR prepared
13 Gohana Tal

60

Chamoli Alaknanda PFR prepared
14 Rambara

24

Rudraprayag Alaknanda IMG report
15 Birahi Ganga-II (P)

24

Chamoli Alaknanda DPR under revision
16 Melkhet (P)

56

Chamoli Alaknanda Pinder Proposed
17 Urgam-II

3.8

Chamoli Alaknanda Under S&I
18 Bhyunder Ganga

243

Chamoli Alaknanda FC under consideration
19 Nand Pyayag Langasu

141

Chamoli Alaknanda EAC TOR Approved
20 Rambara

76

Rudraprayag Alaknanda EAC TOR u/consideration
21 Bagoli

90

Chamoli Alaknanda Proposed
22 Bangri

44

Chamoli Alaknanda Pinder
23 Madhya Maheshwar

350

Chamoli Alaknanda Proposed
24 Ming Nalgaon

114

Chamoli Alaknanda Pinder
25 Padli

66

Chamoli Alaknanda Proposed
26 Thapli

44

Chamoli Alaknanda Proposed
27 Utyasu-I

70

Chamoli Alaknanda Proposed
28 Utyasu-II

205

Chamoli Alaknanda Proposed
29 Utyasu-III

195

Chamoli Alaknanda Proposed
30 Utyasu-IV

125

Chamoli Alaknanda Proposed
31 Utyasu-V

80

Chamoli Alaknanda Proposed
32 Utyasu-VI

70

Chamoli Alaknanda Proposed
33 Rampur Tilwari

25

Rudraprayag Alaknanda Proposed
34 Chunni semi

24

Rudraprayag Alaknanda Proposed Mandakini
35 Kosa

24

Chamoli Alaknanda Dhauliganga
36 Vijay nagar- Rampur

20

Rudraprayag Alaknanda Proposed
37 Nandakini-III

19.5

Chamoli Alaknanda Proposed
38 Nayar

17

Pauri Ganga sub basin Nayar
39 Alaknanda I

15

Chamoli Alaknanda Proposed
40 Buara

14

Bageshwar Alaknanda Pindar
41 Duna Giri

10

Chamoli Alaknanda Dhauliganga
42 Alaknanda II

10

Chamoli Alaknanda Proposed
43 Balkhila-II

10

Chamoli Alaknanda Proposed
44 Mandani Ganga

10

Rudraprayag Alaknanda Mandakini Mandani ganga
45 Rishiganga

8.25

Chamoli Alaknanda Proposed
46 Subhain

8

Chamoli Alaknanda Dhauliganga
47 Son

7

Rudraprayag Alaknanda Mandakini son gad
48 Kalp ganga

6.25

Chamoli Alaknanda Proposed kalpganga
49 Lustar

6

Rudraprayag Alaknanda Mandakini Lustar
50 Madhya maheshwar -II

6

Rudraprayag Alaknanda Mandakini madmaheshwar
51 Hom 6

6

Chamoli Alaknanda Dhauliganga
52 Amrit ganga

6

Chamoli Alaknanda Amrit ganga balsuti gadera
53 Gaddi

5.25

Chamoli Alaknanda dhauliganga Gaddi Gadera
54 Deval

5

Chamoli Alaknanda Proposed
55 Ghrit Ganga

5

Chamoli Alaknanda Proposed
56 Jumma

5

Chamoli Alaknanda Proposed
57 Ringi

5.5

Chamoli Alaknanda Dhauliganga
58 Tamak

5

Chamoli Alaknanda Proposed
59 Balkhila-I

5.5

Chamoli Alaknanda Proposed Balkhila
60 Basti -I

4

Rudraprayag Alaknanda Proposed
61 Basti -II

4

Rudraprayag Alaknanda Proposed
62 Laxmanganga

4

Chamoli Alaknanda Proposed
63 Nil ganga

3

Chamoli Alaknanda Proposed
64 Santodhar – I

2

Pauri Ganga sub basin W Nayar
65 Santodhar – II

2

Pauri Ganga sub basin W Nayar
66 Birahiganga

4.8

Chamoli Alaknanda Proposed
67 Byaligaon

2.25

Pauri Ganga sub basin E Nayar
68 Ghirit Ganga

1.3

Chamoli Alaknanda Proposed
69 Jummagad

1.2

Chamoli Alaknanda Proposed
70 Kailganga

3

Chamoli Alaknanda Proposed
71 Kakra

1

Rudraprayag Alaknanda Proposed
72 Kali Ganga

3

Chamoli Alaknanda Proposed
73 Garud Ganga

0.6

Chamoli Alaknanda Proposed
74 Gansali Bampa

0.05

Chamoli  Alaknanda Dhauliganga/Ganesh Ganga
Alaknanda Total

5199.25

     

 

List of proposed projects in Bhagirathi Basin

 

SN Project Ins Cap (MW) Dist Sub-Basin Status
1 Kotli Bhel (IA)

195

Pauri Bhagirathi EC/FAC stage 1
2 Jhalakoti (P)

12.5

Uttarkashi Bhagirathi Proposed dharamganga
3 Bhilangana II A

24

Uttarkashi Bhagirathi Proposed
4 Karmali

140

Uttarkashi Bhagirathi IMG, on Eco-sensitive zone?
5 Jadhganga

50

Uttarkashi Bhagirathi IMG: PFR prepared
6 Bhilangana IIB

24

Tehri Bhagirathi Under S&I
7 Bhilangana IIC

24

Tehri Bhagirathi Under S&I
8 Pilangad-II

4

Uttarkashi Bhagirathi Proposed
9 Bhela Tipri

100

Uttarakashi Bhagirathi Proposed
10 Nelong

190

Uttarakashi Bhagirathi Proposed
11 Asiganga-III

9

Uttarkashi Bhagirathi Proposed
12 Gangani (P)

8

Uttarkashi Bhagirathi Proposed
13 Balganga-I

5

Tehri Garhwal Bhagirathi Proposed
14 Khirao ganga

4

Uttarkashi Bhagirathi Proposed
15 Lagrasu (P)

3

Tehri Garhwal Bhagirathi Proposed
16 Songad

3

Uttarkashi Bhagirathi Proposed
17 Jalandhari Gad

3

Uttarakashi Bhagirathi Proposed
18 Jalkurgad I

2

Tehri Garhwal Bhagirathi Proposed jalkur gad
19 Rataldhara

0.4

Tehri Garhwal Bhagirathi Proposed Jalkur Gad
20 Lamb Gaon

0.4

Tehri Garhwal Bhagirathi Proposed Jalkur gad
21 Dhatirmouli

0.4

Tehri Garhwal Bhagirathi Proposed Jalkurgad
22 Gangi-Richa

0.2

Tehri Tehri Bhagirathi Bhilangana/ Re Gad
Bhagirathi Total

801.9

     

 

List of proposed projects in W Ramganga Basin

 

Golden Mahseer in Ramganga
Golden Mahseer in Ramganga
SN Project Ins Cap (MW) Dist Sub-Basin Status
1 Babas Dam

88

Almora Ramganga Proposed
2 Khati

63

Bagehwar Ramganga Proposed
3 Lumi

54

Bagehwar Ramganga Proposed
4 Kuwargarh

45

Bagehwar Ramganga Proposed
5 Bawas Gaon

34

Nainital Ramganga Proposed
6 Jamrani Dam

30

  Ramganga Proposed
7 Khutani

18

Bageshwar Ramganga Proposed
8 Sarju Stage-II (P)

15

Bageshwar Ramganga Proposed
9 Sarju Stage-III (P)

10.5

Bageshwar Ramganga Proposed
10 Sheraghat

10

Almora Ramganga Kho
11 Baura

14

Bageshwar Ramganga Proposed
12 Sarju Stage-I (P)

7.5

Bageshwar Ramganga Proposed
13 Balighat

5.5

Bageshwar Ramganga Proposed
14 MehalChaura-I

4

Pithoragarh Ramganga Proposed
15 MehalChaura-II

3

Pithoragarh Ramganga Proposed
16 Agarchatti

2

Pithoragarh Ramganga Proposed
17 Kho I

2

Pauri Ramganga Kho
18 Kho II

2

Pauri Ramganga Proposed
19 Harsila

0.7

Bageshwar Ramganga Proposed harsila gad
20 Kalsa

0.3

Nainital Ramganga Proposed
Ramganga Total

408.5

     

 

List of proposed projects in Sharda Basin

 

SN Project Ins Cap (MW) Dist Sub-Basin Status
1 Mapang Bogudhiyar (P)

200

Pithoragarh Sharda EAC TOR Approved
2 Bogudhiyar Sarkaribhyol (P)

170

Pithoragarh Sharda EAC TOR Approved
3 Sarkaribhyol Rupsiabagar

210

Pithoragarh Sharda EAC TOR Approved
4 Rupsiabagar Khasiabara

260

Pithoragarh Sharda EAC Ok / FAC Rejected
5 Bokang Baling

330

Pithoragarh Sharda Proposed THDC
6 Chungar Chal

240

Pithoragarh Sharda Proposed NHPC
7 East Ram Ganga Dam

30

Pithoragarh Sharda Proposed
8 Khartoli Lumti Talli

55

Pithoragarh Sharda Proposed
9 Budhi

192

Pithoragarh Sharda Mahakali
10 Garba Tawaghat

610

Pithoragarh Sharda-Mahakali Proposed NHPC
11 Garbyang

131

Pithoragarh Sharda Mahakali
12 Lakhanpur

160

Pithoragarh Sharda Proposed
13 Malipa

138

Pithoragarh Sharda Mahakali
14 Pancheshwar

6000

Pithoragarh Sharda Indo Nepal Project
15 Purnagiri Dam

1000

Champawat Sharda Indo Nepal Project
16 Tawaghat – Tapovan

105

Pithoragarh Sharda Mahakali
17 Taopvan Kalika

160

Pithoragarh Sharda Mahakali
18 Tapovan Chunar

485

Pithoragarh Sharda Proposed
19 Sela Urthing

230

Pithoragarh Sharda Proposed
20 Urthing Sobla (P)

340

Pithoragarh Sharda Proposed
21 Sobla Jhimjingao

145

Pithoragarh Sharda Proposed
22 Kalika – Baluwakot

120

Pithoragarh Sharda Mahakali
23 Kalika Dantu

230

Pithoragarh Sharda Proposed
24 Dhauliganga Intermediate

200

Pithoragarh Sharda Proposed NHPC
25 Gauriganga III A & B

140

Pithoragarh Sharda Proposed NHPC
26 Madkini (P)

39

Pithoragarh Sharda Proposed
27 Burthing – Purdam

5

Pithoragarh Sharda Proposed Jakula
28 Jimbagad

7.7

Pithoragarh Sharda Proposed
29 Suringad-II

5

Pithoragarh Sharda Proposed
30 Tanga (P)

5

Pithoraharh Sharda Proposed
31 Tankul

12

Pithoragarh Sharda Proposed
32 Motighat (P)

5

Pithoraharh Sharda Proposed
33 Painagad

9

Pithoragarh Sharda Proposed
34 PhuliBagar- Kwiti

4

Pithoragarh Sharda Proposed Jakula
35 Kumeria- Garjia (Bawas)

12.5

Nainital Sharda Kosi
36 Balgad

8

Pithoragarh Sharda E Ramganga
37 Kuti SHP

6

 Pithoragarh Sharda Maha Kali/ Kuti yangti
38 Palang SHP

6.5

 Pithoragarh Sharda Maha Kali/ Plang gad
39 Najyang SHP

5.5

 Pithoragarh Sharda Maha Kali/ Najyang gad
40 Simkhola SHP

8.75

 Pithoragarh Sharda Maha Kali/ Simkhola gad
41 Birthi

1

Pithoragarh Sharda Balchinn
42 Baram

1

Pithoragarh Sharda Dhauli Ganga/ Baram Gad
43 Unchiya

0.05

Pithoragarh Sharda Dhauli Ganga/ Khari Gad
44 Murtoli

0.02

Pithoragarh Sharda Goriganga/ Martoligad
45 Burphu

0.03

Pithoragarh Sharda Goriganga/ Martoligad
46 Ralam

0.03

Pithoragarh Sharda Goriganga/ Ralangad
47 Ram Gad-II

0.1

Nainital Sharda Kosi/ Ramgad
48 Watcm

0.1

Pithoragarh Sharda Ramgad E/ Watchraila

Total Sharda Basin

12022.28

     

 

List of proposed projects in Yamuna Basin

 

SN Project Ins Cap (MW) Dist Sub-Basin Status
1 Lakhwar

300

Dehradun Yamuna EAC TOR Approved
2 Vyasi

120

Dehradun Yamuna EAC Recommended
3 Arakot Tuni

81

Uttarkashi Yamuna EAC TOR Approved
4 Tuni Plasu

66

Dehradun Yamuna EAC TOR Approved
5 Mori-Hanol (P)

63

Uttarkashi Yamuna EAC TOR Approved
6 Naitwar Mori (Dewari Mori)

60

Uttarkashi Yamuna EAC Recommended
7 Hanol Tuni (P)

60

Uttarkashi Yamuna EAC Recommended
8 Jakhol Sankri

45

Uttarkashi Yamuna EAC TOR Approved
9 Kishau

600

Dehradun Yamuna Proposed
10 Chammi Naingaon

540

Uttarakashi Yamuna Proposed
11 Chatra Dam

300

Uttarakashi Yamuna Proposed
12 Taluka Sankri

140

Uttarkashi Yamuna Proposed
13 Taluka Dam

112

Uttarakashi Yamuna Proposed
14 Sankri Mori

78

Uttarakashi Yamuna Proposed
15 Barkot Kuwa

42

Uttarakashi Yamuna Proposed
16 Hanuman Chatti Sianachatti

33

Uttarakashi Yamuna Proposed
17 Barnigad Naingaon

30

Uttarakashi Yamuna Proposed
18 Rupin Stage V (P)

24

Uttarkashi Yamuna Proposed
19 Damta – Naingaon

20

Uttarkashi Yamuna Proposed
20 Tons

14.4

Uttarkashi Yamuna Proposed
21 Supin

11.2

Uttarkashi Yamuna Proposed
22 Rupin Stage IV (P)

10

Uttarkashi Yamuna Proposed
23 Rupin Stage III (P)

8

Uttarkashi Yamuna Proposed
24 Barnigad

6.5

Uttarakashi Bhagirathi Proposed
25 Pabar

5.2

Dehradun Yamuna Proposed
26 Badyar (P)

3

Uttarkashi Yamuna Proposed
27 Lagrasu

3

Tehri Yamuna Proposed
28 Rayat (P)

3

Tehri Yamuna Proposed
29 Ringali

1

Tehri Garhwal Yamuna Proposed Aglar Ringaligad
30 Purkul

1

 Dehradun Yamuna Tons
31 Paligad

0.3

Uttarkashi Yamuna Proposed Paligad
32 Rikhani Gad

0.05

Uttarkashi Yamuna Rikhanigad
33 Bijapur

0.2

 Dehradun Yamuna Tons
Yamuna Total 2780.85 MW
Grand Total 21212.78 MW

Note: EAC: Expert Appraisal Committee of MoEF; FAC: Forest Advisory Committee of MoEF; EC: Environment Clearance: FC: Forest Clearance; TOR: Terms of Reference (of EIA); for Alaknanda, the first 17 projects are listed as given in IMG report and for Bhagirathi first 8 projects are as listed in IMG report. However, many of these projects have been recommended to be dropped by the WII (Wildlife Institute of India) report. Also, IMG and other have said that no further projects should be taken up in Bhagirathi and Alaknanda basins. The projects listed above in the Bhagirathi basin beyond serial number 8 and those in Alaknanda basin beyond 17 would, in any case, not be taken up.

In the table below we have provided and overview of proposed hydropower projects in Uttarakhand based on the information from above five tables.

Overview of Proposed Hydropower Projects in Uttarakhand

 

Basin Large Hydro projects (above 25 MW) Small Hydro projects (1-25 MW) Mini-micro Hydro projects (below 1 MW) Total Hydro projects
No of projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW
Alaknanda

29

4823

43

375.6

2

0.65

74

5199.25

Bhagirathi

5

675

13

125.5

4

1.4

22

801.9

Ramganga

6

314

12

93.5

2

1

20

408.5

Sharda

26

11920

16

101.95

6

0.33

48

12022.28

Yamuna

17

2670

13

110.3

3

0.55

33

2780.85

TOTAL

83

20402

97

806.85

17

3.93

197

21212.78

 

Overview of hydropower projects in Uttarakhand In the table below we have put together the number and capacities of existing, under construction and proposed hydropower projects in various basins of Uttarakhand. Uttarakhand government has plans to have total of 337 hydropower projects with total capacity of 27191.89 MW. Largest number (124) of such projects are in Alaknanda basin, the largest capacity is proposed to be in Sharda basin at 12450.905 MW.

In the table below we have given basin wise figures of total large, small and mini-micro hydropower proejcts (including existing, under construction and proposed) projects in Uttarakhand. According to Union Ministry of New and  Renewable energy, total potential of small hydro  in Uttarakhand is 1707.87 MW from 448 small hydro projects. If we take that into account the figures in the following tabes would change (go up) accordingly.

Basin wise total capacities for large, small and mini HEPs in Uttarakhand

 

Basin Large Hydro projects (above 25 MW) Small Hydro projects (1-25 MW) Mini-micro hydro projects (<1 MW) Total Hydro projects
No of projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW
Alaknanda

35

6419

61

524.65

26

3.67

122

6947.32

Bhagirathi

10

3469

28

266.7

10

2.05

48

3737.75

Ganga Sub basin

1

144

3

31.2

2

0.35

6

175.55

Ramganga

7

512

14

105.3

11

2.05

32

619.35

Sharda

29

12335.6

20

109.65

35

5.155

84

12450.405

Yamuna

22

3144.75

14

113.3

8

1.135

44

3259.185

TOTAL

104

26024.35

140

1150.8

92

14.41

336

27189.56

In the table below we have given basin wise figures of existing, under construction and proposed hydropower projects of all sizes in Uttarakhand.

Overview of all Hydropower projects in Uttarakhand

 

Basin Existing Hydro projects Under construction projects Proposed hydropower projects Total Hydro projects
No of projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW No of Projects Capacity, MW
Alaknanda

32

456.97

16

1291.1

74

5199.25

122

6947.32

Bhagirathi

13

1851.5

13

1084.75

22

801.9

48

3737.75

Ganga Sub basin

4

173.8

2

1.75

6

175.55

Ramganga

12

210.8

20

408.5

32

619.35

Sharda

28

427.75

8

0.375

48

12022.28

84

12450.405

Yamuna

9

478.195

2

0.14

33

2780.85

44

3259.185

TOTAL

98

3598.665

41

2378.115

197

21212.78

336

27189.56

Basin Maps Maps of Hydroelectric Projects in various sub basins of Uttarakhand are available at the following links. Please note that the maps are based on information available when the maps were created in 2011:

https://sandrp.in/basin_maps/Hydropower_Projects_in_Ganga_Basin.pdf

https://sandrp.in/basin_maps/Bhagirathi%20150411.jpg

https://sandrp.in/basin_maps/Alaknanda%20150411.jpg

https://sandrp.in/basin_maps/Mandakini150411.jpg

https://sandrp.in/basin_maps/Goriganga150411.jpg

https://sandrp.in/basin_maps/Major_Hydro_Projects_in_Yamuna_Basin.pdf

 

How do the hydropower projects increase the scale of disaster?

This is a question that a lot of journalists and TV anchors have been asking me since the Uttarakhand disaster. Here is a quick response:

Þ     Almost all hydropower projects of Uttarakhand involve deforestation. Deforestation directly increases the potential of erosion, landslides and floods since water now just runs off to the rivers. Moreover the compensatory afforestation and catchment area treatment, even when done, usually involves planting of commercially important variety of trees like pine and teak and not broad leaf tress like oaks which not only adds humus in the soil, but also allows rich under growth. Pine does not allow this to happen. This change in character of forests is something Gandhiji’s disciple Mira Behen has been warning since independence, but there is little impact of this on the forest department.

Þ     In fact largest proportion of deforestation in Uttarakhand has happened basically for hydropower projects.

Þ     All run of the river projects involve building of a dam, diversion structure, desilting mechanism, tunnels which could have length of 5 to 30 km and width sufficient to carry three trains side by side, as also roads, townships, mining, among other components. All of these components increase the disaster potential of the area in one or the other way. Cumulative impacts of all the components of any one project and all projects together  in a given basin is likely to be larger than the addition of the impacts of individual projects in many cases.

Þ     Massive blasting of massive proportions is involved in construction of all these components, which adds to landslide risks. In fact Uttarakhand’s Disaster Mitigation and Management Centre in their report of Oct 2012 after the Okhimath disaster of Sept 2012 recommended that no blasting should be allowed for any development activity anywhere in Uttarakhand, but Uttarakhand government did nothing about this recommendation.

Þ     The massive tunneling by itself weakens the young and fragile Himalayan mountains, increasing the disaster potential.

Þ     Each of the hydropower project generates immense amount of muck in tunneling, blasting and other activities. A large hydropower project could typically generate millions of cubic meters of muck. The large projects are supposed to have muck disposal plan, with land acquired for muck disposal, transportation of muck to the designated sites above the High Flood levels, creation of safety walls and stabilization process. But all this involves costs. The project developers and their contractors find it easier to dump this muck straight into the nearby rivers. In the current floods, this illegally dumped muck created massive disaster in downstream areas in case of 330 MW Srinagar HEP, the 76 MW Phata Byung HEP and the 99 MW Singoli Bhatwari HEP. When the flooded rivers carry this muck, boulders and other debris, has much greater erosion capacity and also leaves behind massive heaps of this muck in the flooded area. In Srinagar town about 100 houses are buried in 10-30 feet depth of muck. Such debris laden rivers also create massive landslides along the banks.

Muck Disposal directly into the Alaknanda river by Srinagar Project Photo: Matu janSangathan
Muck Disposal directly into the Alaknanda river by Srinagar Project Photo: Matu janSangathan

Þ     Wrong operation of hydropower projects can also create greater disasters in the downstream areas. For example the operators of 400 MW Vishnuprayag HEP on Alaknanda river did not open the gates when the river was flooded on June 16-17, possibly to maximize power generation. However, this lead to accumulation of massive quantities of boulders (for photos of dam filled with such boulders see: http://matuganga.blogspot.in/) behind the dam, so much so that that there was no space for water to flow. The river then bypassed the dam and started flowing by the side of the dam, creating a new path for its flow. This created a sudden flashflood in the downstream area, creating a new disaster there.

Boulders devouring the Vishnuprayag Project. 26th June 2013 Photo: Matu jan Sangathan
Boulders devouring the Vishnuprayag Project. 26th June 2013 Photo: Matu jan Sangathan

Þ     The incomplete, broken and ill designed protection wall of the Maneri Bhali projects in Uttarkashi lead to erosion and landslides in the downstream areas.

 

DAMAGED HYDRO PROJECTS A large number of hydropower projects are likely to have suffered damage due to the flood disaster in Uttarakhand. Some of the projects that have suffered damage include:

  • According to the update from http://www.energylineindia.com/on June 27, 2013, the 520 MW under construction Tapovan Vishnugad HEP has suffered damaged by rains on June 16, 2013: “While construction of diversion tunnel was completed in April this year, the same was washed away due to heavy rains on June 16. Diversion dyke has washed away and damages have been observed in chormi adit approach road. In August last year, the flash floods had caused serious damages in the coffer dam of the project.”
  • 400 MW Vishnuprayag HEP of JP Associates has suffered serious, but as yet unassessed damage(http://www.indianexpress.com/news/jaiprakash-power-tanks-15–as-plant-shuts-down-in-uttarakhand/1133083/). As per MATU PR (http://matuganga.blogspot.in/), the project has also been cause of damage in Lambagad village, which was also flahsed on front page of TOI on June 25, 2013, though without mentioning the project. The blog also provides the before and after pictures of the upstream and downstream of the project.
  • 76 MW Phata Byung HEP of Lanco in Mandakini Valley in Uttarakhand
  • 99 MW Singoli Bhatwari HEP of L&T in Mandakini Valley in Uttarakhand NDTV India reported that the water level of the river has gone up due to the silt dumped by dams. This is likely to be due to the Phata Byung and Singholi Bhatwari HEPs.
  • Kali Ganga I, Kali Ganga II and Madhyamaheshwar HEP, all in Mandakini Valley, all of UJVNL, all hit by mudslides (http://www.indianexpress.com/news/uttarakhands-r500-crore-request-to-prevent-landslides-pending-since-2009/1132351/)
  • Assiganga projects on Assiganga river in Bhagirathi basin in Uttarakhand
  • 5 MW Motighat I HEP in Goriganga basin in Pithoragarh (Himalprakriti report)
  • 280 Dhauliganga Project of NHPC in Pithoragarh district of Uttarakhand (reports said the power house was submerged, but is now working, part of the township was submerged.)
  • The Himalaya Hydro (HH) Tanga Phase I for 5 MW, located along the Paina gad in Goriganga basin, is badly damaged. The dam has got smashed by a deluge of huge boulders. One sluice gate is torn through. The metal filter-gates are all choked with boulder debris, and the remnant concrete and gate pulleys of the dam are now stranded mid-river, with both banks eroded and the river now running along the true-left bank. (Himalprakriti report)
  • The UREDA 500 KW Motigad microhydel on Moti gadh (a tributary of Paina gadh) at Bindi (Dani Bagad) is also badly damaged. The water has broken through the wall, cut under the foundation, inundated the turbines with water and debris, and smashed the housing for the electrical distribution system. (Himalprakriti report)
  • The 5.5′ diameter head race waterpipes taking water to the HH Phase II, located on the Gori opposite Seraghat, has also been damaged. The generator and housing for the HH Ph II has collapsed into the river. All this damage is said to have happened on the evening of 17th June. People working as non-skilled labour have been sent home for a few months, but welding work on the new pipes feeding the powerhouse is still underway! (Himalprakriti report)

It has been now reported in Business Standard (http://www.business-standard.com/article/companies/gvk-l-t-hydel-projects-hit-by-floods-113062300394_1.html) that the 330 MW Srinagar project, a cause for downstream destruction, has itself suffered massive damages on June 17, 2013, with breach of its protective embankment. The report also mentions the damage to the L&T’s Singoli Bhatwari HEP on Mandakini river.

Down to Earth (http://www.downtoearth.org.in/content/hydropower-projects-suffer-severe-damage) has given some details of damage to some of the hydropower projects, quoting UJVNL sources. It says: 19 small hydropower projects have been completely destroyed, while others have been damaged by the raging waters (see table below)

Project Location Capacity Estimated Loss
Dhauli Ganga Pithoragarh  280 MW Rs 30 crore (project completely submerged)
Kaliganga I Rudraprayag 4 MW Rs 18-19 crore (power house and 4 houses washed away)
Kaliganga II Rudraprayag 6 MW Rs 16 crore (power house and 4 houses washed away)
Sobla Pithoragarh 8 MW Rs 14 crore (completely washed away)
Kanchauti Pithoragarh 2 MW Rs 12 crore (totally washed away)
Chirkila Pithoragarh 1.5 MW Rs 20 crore (part of the project washed away)
Maneri Bhali I&II Uttarkashi 304+90 MW Rs 2 crore + Rs 5 crore (walls collapsed, silt in barrages)

In addition, a large  number of projects had to stop generation temporarily due to high silt content, including Maneri Bhali I and II, Tanakpur, Dhauli Ganga, Kali Ganga I, some of the Yamuna basin projects among others.

 

Conclusion This article was intended to give an overview of hydropower projects in Uttarakhand. However, we should add that there are many glaring issues related to these hydropower projects, some of the key issues include:

  • Most of these projects are out of the environmental governance. Projects below 25 MW do not require EIA, Social Impact Assessment, public consultation, environmental clearance, environmental management plan or monitoring. This is clearly wrong as all projects have environmental impacts, and they are particularly serious in Himalayan region with multiple vulnerabilities. We have for years demanding that all projects above 1 MW should need environment clearance, EIA and so on.
  • Even for projects above 25 MW we do not have any credible environmental or social impact assessment. Former Environment Minister Jairam Ramesh is on record having accepted that most EIAs are dishonest cut and paste jobs. We do not have any credible process in place to ensure that EIAs are proper and those that are not are rejected and consultants are black listed. Jairam Ramesh did put in place a process of registration of EIA consultants under the Quality Council of India, but that is completely non transparent, unaccountable and ineffective process. It is amazing that reputed NGOs like the Centre for Science and Environment are on board of this process, but they have completely failed to achieve any change and have chosen to remain quiet.
  • The Environment clearances of the River Valley Projects (which includes hydro projects and dams) is considered by the Expert Appraisal Committee on River Valley Projects appointed by Union Ministry of Environment and Forests. However, the ministry chooses members of the EAC such that they rarely object to any project. As per SANDRP analysis in six years ending in Dec 2012, the EAC had not said NO to any project for environment clearance. Its appraisal of projects, EIAs, public consultation process and its own minutes were found to be inconsistent, unscientific and loaded in favour of the project developers.
  • Our environment compliance system is non-existing. The projects are supposed to implement the environment management plan pari passu with the project work, they are supposed to follow the conditions of environment clearance, follow the environmental norms, but who is there to ensure this actually happens? The Union Ministry of Environment and Forests which is supposed to ensure this compliance has no capacity the officials tell us. The officials do not have time to even check if six monthly compliance reports are being submitted or make any surprise visits. However they do not even seem to have will, since we have seen no change in this situation for decades. Nor do they seem to have willingness, since even when NGOs present photographic and video and other evidence of violations they refuse to take action.
  • One way to achieve compliance is to have a project monitoring committee for each project where over 50% of the members are from local communities and other independent persons and such committees ok must be required each stage for the project to go ahead. We have been suggesting this for long, but the MoEF has shown no willingness to follow this.
  • More pertinently, none of the assessment reports look at the impact on the disaster potential of the area. Each of these projects have significant impact on the disaster potential of the area, particularly in the context of a vulnerable state like Uttarakhand. This should be a must for all such projects.
  • Similarly the projects must also be assessed in the context of climate change, again in vulnerable area like the Himalayas. How the project will impact the local climate, how it will have impact on adoption capacity of the local communities and also how the project itself will be impacted in changing climate. This again we have been writing to the MoEF numerous times, but without any success so far.
  • Most significantly, the only impact assessments that we have is for specific projects of over 25 MW capacity. However, we have no credible cumulative impact assessment for any of the river basins of Uttarakhand, which also takes into account carrying capacity of the river basins and all the interventions that are happening in the basins. As our critique of so called cumulative impact assessment of Bhagirathi-Alaknanda basins done by AHEC of IIT Roorkee shows (see:  http://www.sandrp.in/hydropower/Pathetic_Cumulative_Impact_Assessment_of_Ganga_Hydro_projects.pdf), it was not much of a cumulative impact assessment. WII (Wildlife Institute of India, Dehradun) report was somewhat better within the mandate given to it (assessment of hydro projects on aquatic and terrestrial biodiversity), but the most important recommendation of the WII report that at least 24 projects should be dropped has not been accepted by the MoEF, so what is the use of the cumulative impact assessment in such a situation?

Unless we address all of the above issues in a credible way, there is little wisdom in going ahead with more hydropower projects in Uttarakhand. They will invite greater disasters. Uttarakhand has many other options for development.

  • Firstly people of  Uttarakhand should get first right over all the power that is getting generated within Uttarakhand.
  • Secondly, this is not a plea for no projects, but to address the crucial issues without addressing which we are in no situation to even know the impacts or address the issues.
  • Thirdly, Uttarakhand needs to take up power generation options that do not accentuate the disaster potential of the area. Such options include micro hydro, hydro kinetics, and solar and biomass based power in addition to better utilization of existing infrastructure.

Going ahead with more hydropower projects in current situation would be invitation to greater disasters. In fact, the Uttarakhand government should not allow even the damaged and under construction hydropower projects until al the conditions mentioned above are satisfied.

Some of the hydropower projects that have surely seem to have added to the disaster proportions of current Uttarakhand flood disaster include the 400 MW Vishnuprayag HEP, the 280 MW Dhauliganga HEP, the 330 MW Shrinagar HEP, the 304 and 90 MW Maneribhali II and I HEPs, the 99 MW Singoli Bhatwari HEP and the 76 MW Phata Byung HEP, the last two on Mandakini river.

In response to my question on a programme on Headlinestoday channel anchored by Rahul Kanwal on July 8, 2013 (in presence of panel that also included Dr Vandana Shiva and Vimlendu Jha), the Uttarakhand Chief Minister Shri Vijay Bahuguna agreed that he will institute an enquiry into the damage due to these hydropower projects and hold them accountable for such damage.

Let us see how soon and how independent and credible enquiry he institutes.

Himanshu Thakkar

 South Asia Network on Dams, Rivers & People (www.sandrp.in)                                                        July 2013

References:

1. http://envfor.nic.in

2. http://www.uttarakhandjalvidyut.com/eoi/list_of_projects_self.pdf and many other UJVNL documents.

3. http://www.ahec.org.in/shp%20sites/uttarakhand/Hydropower%20stations%20in%20operation%20and%20under%20construction%20in%20uttarakhand.pdf

4. http://cleanhydropower.blogspot.in/2009/07/brief-description-of-small-hydro-power.html

5. http://ureda.uk.gov.in/pages/show/130-micro-hydro-programme and other sites of UREDA.

6. https://sandrp.in/env_governance/TOR_and_EC_Clearance_status_all_India_Overview_Feb2013.pdf

7. https://sandrp.in/IMG_report_on_Ganga_has_Pro_Hydro_Bias_June2013.pdf

8. http://www.sandrp.in/hydropower/Pathetic_Cumulative_Impact_Assessment_of_Ganga_Hydro_projects.pdf

9. 2012-13 Annual report of Ministry of New and Renewable Energy: http://mnre.gov.in/file-manager/annual-report/2012-2013/EN/chapter3.html

SANDRP blogs on Uttarakhand disaster :

1. https://sandrp.wordpress.com/2013/06/21/uttarakhand-deluge-how-human-actions-and-neglect-converted-a-natural-phenomenon-into-a-massive-disaster/

2. https://sandrp.wordpress.com/2013/06/23/uttarakhand-floods-disaster-lessons-for-himalayan-states/

3. https://sandrp.wordpress.com/2013/06/25/uttarakhand-and-climate-change-how-long-can-we-ignore-this-in-himalayas/

4. https://sandrp.wordpress.com/2013/06/25/central-water-commissions-flood-forecasting-pathetic-performance-in-uttarkhand-disaster/

5. https://sandrp.wordpress.com/2013/06/28/uttarakhand-floods-truth-about-thdc-and-central-water-commissions-claims-about-tehri/

6. https://sandrp.wordpress.com/2013/06/29/lessons-from-uttarakhand-disaster-for-selection-of-river-valley-projects-expert-committee/

7. https://sandrp.wordpress.com/2013/06/25/climate-justice-statement-on-the-uttarakhand-catastrophe/

30 thoughts on “Uttarakhand: Existing, under construction and proposed Hydropower Projects: How do they add to the state’s disaster potential?

  1. Thanks a lot for very valuable information. I am working for the preparation of CAT Plans of Satluj and Beas River in HP, Cloud burst happened in2011 ina small area near Manali and did the same type of damage.What are the remedies. What are the strategies for future management of river systems interfered by large number of hydro-electric projects.

    Like

    1. Thanks, Dr Grewal, Can you let us know a bit more about the CAT plans you are doing? Is it for government (of HP?) or some private developers?

      Part of the answer to your question is given in the blog. FIRST assess the carrying capacity, and cumulative impacts. Till that is done (and this has not happened for either Sutlej or Beas) in over exploited basins like Sutlej and Beas would be invitation for HUGE disasters. So stop all such projects that increase the vulnerability and disaster potential of the basins. Put in place a community driven environment compliance system, we have none today. Even CAT plans formulation and implementation has to happen in consultation with the gram sabhas and they should not be just instruments to push more projects as is the case currently.

      For example, in case of the World Bank funded Luhri hydropower project in Sutlej basin, the project is completely unjustifiable, the EIA-EMP-CAT done for the project by the CISMHE team lead by Prof Maharaj Pandit is so pathetically inadequate. The EIA does not even take into account the impacts of the world’s longest tunnel planned for the project. There is no free flowing river distance between Luhri and upstream Rampur project and also Lurhi and downstream Koldam project. In such a case, no amount of CAT plans are going to help. It is amazing that the World Bank that is actually responsible for funding such disastrous projects is now going to fund Uttarakhand disaster mitigation and management efforts!

      Like

  2. The existing gap between EMP as laid down in reports and that implemented at site must be bridged. True, EAC rejects very few projects but clears the rest only after a number of sittings for improvement of quality of project reports.

    Like

    1. Dear Prof Mazumder,

      Many thanks for your comment, really appreciate you posting comment here. Yes, EMP and conditions of clearance are supposed to be implemented, but we all know they are not getting implemented and this situation prevails for decades now without much change. If we do not have capacity, will or willingness to ensure implementation of EMP and conditions of clearances, is there any justification for such clearances? More importantly, EAC is in eminently suitable position to do a lot about this, we have written to EAC on this, but EAC has done nothing about this.

      You are saying “EAC rejects very few projects”. Sir, in last six and half years, EAC on RVP has not said no to EC for a single project. I do not know what you mean by saying EAC clears “only after a number of sittings for improvement of quality of project reports”. If you are saying the EIAs were bad but improved after EAC recommendations in most cases, sir I am afraid that is not the case in most projects. If there is no cumulative impact assessment or carrying capacity, if there is no assessment of disaster potential or climate change context, what did EAC do to ensure that the projects are not cleared without these? If the EIAs were not adequate in the first place and it is no longer a state secret that they are mostly dishonest jobs, in how many cases did EAC reject such flawed EIAs and ask for black listing of EIA consultants? If public consultations were not proper, EIA is not even available in local language, why did the EAC okayed such projects? Sorry, sir, even after giving specific evidence and inadequacies, EAC has refused to take action.

      To give a couple of specific examples, in case of Jelam Tamek HEP in Alaknanda basin in Uttarakhand, when I wrote to EAC members including you, that WII has recommended rejection of the project and even BK Chaturvedi com has said that project should only be considered only after IIT Consortium report, why did EAC recommended clearance to the project on June 6, 2013? This when it was pointed out in my letter how many concessions the EAC has given to the project, violating its own norms? In case of Luhri project, it was pointed out through our letter endorsed by over 50 groups all over India, that the project has no free flowing river upstream and downstream, its EIA done by team lead by Prof Maharaj Pandit of CISMHE was fundamentally flawed, it did not even assess the impact of world’s longest hydropower tunnel, why did the EAC clear the project? In case of Seli project in Chenab basin, why did the EAC clear the project without cumulative impact assessment when even affected people wrote to EAC about the violations?

      Amazingly, sir, EAC or its members neither respond to our numerous letters, nor ask project developers to respond to the issues, nor acknowledge such letters in the EAC minutes in most cases. We certainly need better environment governance that this, sir.

      Thanks again for your response,

      Himanshu Thakkar

      Like

      1. Dear Dr Grewal and Prof Mazumder,

        A highly relevant issue has been raised: “What are the strategies for future management of river systems interfered by large number of hydro-electric projects.”

        May I suggest that a fundamental approach to the whole issue of hydel projects (whether in Himalayas or in plains) is to objectively question the very need for these projects from the energy security’s perspective, and analyse the overall costs to the society from these projects as compared to the meager benefits ? Unfortunately our society has not been able to make these two requirements as a mandatory part of the approval mechanism. There is an urgent need to bring about this change in the entire economic decision making process.

        A natural extension of this decision making mechanism is to compare the dam based hydro power option with very many benign options available to bridge the growing gap between the demand and supply of electricity. A quick look at the DPR (detailed project report) of any hydel project proposal will reveal that generally no alternatives are even mentioned. There are many alternatives for our country.

        As a society, do we care for such diligent processes?

        Shankar Sharma
        Power Policy Analyst
        Western Ghats, Karnataka

        Like

    1. While going through this report certain false statement has been observed and there is no scientific case has been built to justify the views of the Author. The author may know real cause of the disaster and he may be trying to hide the real scientific facts so that he can successfully blame the development of hydro power projects. It is because the Author fundamentally would not like any hydro power project to be built in this developing country. Noting the facts summarized, it appears that the Author written this article with predetermined mind set.
      First of all, the disaster happened due to unprecedented rainfall and also cloudburst at higher altitude of Himalayan region where there is no hydro power projects exists or under construction. Majority of the scientists carry a view that the event took place on account of global climatic change phenomena. It is the fact, but surprisingly, the Author failed to analysis reason and major attributes for such global climatic changes and more surprisingly shift the entire blame on hydro power development which is one of the cleanest & renewal source of energy and also contributes to CO2 emission reductions. It is sad to note such false propaganda without analyzing the facts.
      Another important fact to be discussed that the extent of forest land as diverted for construction of hydro power projects in the state of Uttarakhand is less than 1% of total forest cover. While the fact is like this, how one can claim that the hydro power construction resulting into deforestation?. Further it is to be noted that, even for this forest land diversion, there are adequate compensation packages exists in the government policy. We should put effort and focus to implement the compensatory afforestation and CAT plan in proper manner instead of putting effort to divert the facts through false propaganda.
      The Author also needs to understand the positive environmental and social benefits of hydro power project post construction. The sad part is no one even made attempt to analysis the facts and positive benefits of a Dam and hydro power projects during the project operation phase. In many cases, it was demonstrated that post construction of hydro power project, the regional environmental and ecology substantially improved. As per the statement of this Author, it is learnt that Uttarakhand has hydro power potential of about 28000 MW. The Author needs to understand that this much quantum of clean and renewable energy would directly contribute to 10.08 Crs. Tons of CO2 emission reductions with 50% of power load factor for years. Is it not positive impact on the global climatic changes which is serious threat to the entire globe?. It is also necessary to debate that, if 28000 MW to be generated through alternate fossil fuel sources like coal, gas and other liquid fuel and its negative impact on the local environment and also in turn its negative impact contribution on global climatic changes. These sources of energy would be causing continuous long term negative impacts/ pollution to the local environment. However, in the scenario of hydro power development, post construction the local environment and socio economic development substantially improve and it is demonstrated in the country/World through various Dam & RoR based hydro power projects which were built by the GoI, State Governments and IPPs against great resistance from certain vested interested groups and NGOs. It is also evident that most of the Dam based project turned out to be tourist and recreational destination which is also one of the revenue source supports the local livelihood.
      If scientifically analysis the matter, it can be safely established that hydro power development is nothing to do with the recent disaster in Uttarakhand. It is primarily on account of global climate changes which resulted unprecedented rainfall and floods. The loss of life and property is on account of combination of unauthorized construction and encroachments and also improper planning and regulation in tourism sector.

      Like

      1. Any truly scientific inquiry will establish that hydropower projects hugely increased the proportion of disaster in several different ways. Now that the Supreme Court has also acknowledged this through their order on Aug 13, 2013, let us wait to see how independent an inquiry is conducted and if the truth comes out.

        Like

  3. बहुत अच्छा लिखा है
    इस पुरे लेख पर कोई बुक है क्या?

    Like

  4. A very nice & detailed article Himanshu. If there is a right intent of the politicians, really innovative means can actually be employed to improve the environment & ensure the rights & development of the locals. Unfortunately, very little, in fact nothing has been done in this direction so far – and a small step in the name of “eco-sensitive” zone that was taken by the center is being vehemently opposed by all parties in state. This growing contractor/builder lobby is killing the state & soon, if this is left unchecked – the threat will multiply many folds.

    Like

  5. An excellent piece. Extremely disturbed to see the callousness of the government there and the political parties. Ofcourse, this politician builder nexus started soon after the state was created. As a native of Uttarakhand, it is sad commentary on the state of affairs but I hope we all will learn a lesson from this. Hope your inspiring reports will compel the government and others to think over it. Looking forward for more information on this probably in the book form.

    Like

  6. very well said facts. All developed nations first build their hydro power projects and latter utalizing scarces fassil fuel based non renewable resources. It is also fact that dam is one the best flood control mechanisim.

    Like

    1. We do not have to repeat the mistakes of others. Experience has shown that dams can also be source of massive floods as happened with Tehri in Sept 2010, with Ukai in August 2006, with Hirakud in Sept 2009 and with Krishna basin dams in 2009.

      Like

  7. Hydro-power projects suffers allot due to the disaster happened in uttarakhnad. Its effects life there allot. so many projects have to shut down due to this disaster. It really shakes the life of many projects

    Like

    1. Yes, that is true, equally true, they have added to the disaster proportions and also invited disaster by lack of proper impact assessment, implementation of environment management plans and proper operations.

      Like

  8. The issue is not clear as to the disaster happened because of Hydro projects or Global warming or Cliamte change.

    Like

  9. hi in summer rivers and dams have large quantity of water.have plan to recycle water to clean in dams.in aisa how to stop flood of damages ? new dam construct in aisa as three gorges in china ?

    Like

  10. Very useful Article Sir. Can you please help me with the list of all the players(private and government) who will be executing these proposed projects. Thanks

    Like

Leave a comment

This site uses Akismet to reduce spam. Learn how your comment data is processed.